Planning Lead time-Item Vendors Maintenance window

Previously used manufacturing and MRP in v9 and the Planning Lead time on the 
Item Vendors Maintenance window (bottom left corner), we used to enter 7 for 
the number of days in 1 week.  MRP then suggested to place PO's using these 7 
days as one week.

Now when we enter 35 for example ( V9 calculated 5 weeks for placing the PO)

Now since V10 it looks like it is calculating 7 weeks lead time (35 days 
divided by 5 days)

Did something change with V10 on this field and how MRP uses it with the 
Request Resolution window?

thanks!
-- 
Doug
0
Doug4515 (774)
7/31/2008 3:25:02 PM
greatplains 29623 articles. 6 followers. Follow

1 Replies
903 Views

Similar Articles

[PageSpeed] 58

The system now looks at calendars and can consider/skip down days.  Check out 
the setups for MRP and some of the other manufacturing modules.
-- 
Richard L. Whaley
Author / Consultant / MVP 2006-2008
Documentation for Software Users

Get our Free Tips and Tricks Newsletter and check out our books at 
http://www.AccoladePublications.com



"Doug" wrote:

> Previously used manufacturing and MRP in v9 and the Planning Lead time on the 
> Item Vendors Maintenance window (bottom left corner), we used to enter 7 for 
> the number of days in 1 week.  MRP then suggested to place PO's using these 7 
> days as one week.
> 
> Now when we enter 35 for example ( V9 calculated 5 weeks for placing the PO)
> 
> Now since V10 it looks like it is calculating 7 weeks lead time (35 days 
> divided by 5 days)
> 
> Did something change with V10 on this field and how MRP uses it with the 
> Request Resolution window?
> 
> thanks!
> -- 
> Doug