Need Help, Task Start Date wrong

I’m using MS Project 2007, have several task linked with finish to start.  I 
have set date to schedule from, hours per day set to 8 and Working Monday 
thru Friday. 

My schedule shows Task 1 Duration 4 days, start Wed 6/2/10, Finish Mon 6/7/10
Task 2 Duration 3 days, start Mon 6/7/10, Finish Thu 6/10/10

Task 2 should have a Start Date of 6/8/10 not 6/7/10; what is causing this?

Thanks in advance for your help.

0
Utf
5/24/2010 11:47:01 PM
project 1276 articles. 0 followers. Follow

5 Replies
3791 Views

Similar Articles

[PageSpeed] 2

Player,

Turn on the display of time.  Tools > Options, View tab and 
select a format that shows time as well as date.  That may help 
figure out what is going on.

You mention that you have the standard setting hours per day of 
8.  Have you modified the calendar in Tools > Change Working time?

I hope this helps.  Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project

On 5/24/2010 7:47 PM, player wrote:
> I’m using MS Project 2007, have several task linked with finish to start.  I
> have set date to schedule from, hours per day set to 8 and Working Monday
> thru Friday.
>
> My schedule shows Task 1 Duration 4 days, start Wed 6/2/10, Finish Mon 6/7/10
> Task 2 Duration 3 days, start Mon 6/7/10, Finish Thu 6/10/10
>
> Task 2 should have a Start Date of 6/8/10 not 6/7/10; what is causing this?
>
> Thanks in advance for your help.
>
0
JulieS
5/25/2010 12:00:59 AM
ok display of time shows start 8am and Finish 8am on the next day for a 1 Day 
duration task

and yes I have modified the calendar in Tools >options, calender Tab to  
7:00am to 12:00pm 12:30pm to 3:30pm

Start dates still show starting on same date as predecessors finish Date

Dont know why start time is 8am and finish time is 8am on next day for 1 day 
task?

"JulieS" wrote:

> Player,
> 
> Turn on the display of time.  Tools > Options, View tab and 
> select a format that shows time as well as date.  That may help 
> figure out what is going on.
> 
> You mention that you have the standard setting hours per day of 
> 8.  Have you modified the calendar in Tools > Change Working time?
> 
> I hope this helps.  Let us know how you get along.
> 
> Julie
> Project MVP
> 
> Visit http://project.mvps.org/ for the FAQs and additional
> information about Microsoft Project
> 
> On 5/24/2010 7:47 PM, player wrote:
> > I’m using MS Project 2007, have several task linked with finish to start.  I
> > have set date to schedule from, hours per day set to 8 and Working Monday
> > thru Friday.
> >
> > My schedule shows Task 1 Duration 4 days, start Wed 6/2/10, Finish Mon 6/7/10
> > Task 2 Duration 3 days, start Mon 6/7/10, Finish Thu 6/10/10
> >
> > Task 2 should have a Start Date of 6/8/10 not 6/7/10; what is causing this?
> >
> > Thanks in advance for your help.
> >
> .
> 
0
Utf
5/25/2010 12:57:01 AM
OK what I did was made a new schedule using project default calender and 
working times and all is good for now.

I would like to change working time from 7am to 3:30pm with 1/2 hour lunch 
from 12 to 12:30 but I need to submitt this in the AM. so I just turned off 
view times for now.

Thanks for your help

"player" wrote:

> ok display of time shows start 8am and Finish 8am on the next day for a 1 Day 
> duration task
> 
> and yes I have modified the calendar in Tools >options, calender Tab to  
> 7:00am to 12:00pm 12:30pm to 3:30pm
> 
> Start dates still show starting on same date as predecessors finish Date
> 
> Dont know why start time is 8am and finish time is 8am on next day for 1 day 
> task?
> 
> "JulieS" wrote:
> 
> > Player,
> > 
> > Turn on the display of time.  Tools > Options, View tab and 
> > select a format that shows time as well as date.  That may help 
> > figure out what is going on.
> > 
> > You mention that you have the standard setting hours per day of 
> > 8.  Have you modified the calendar in Tools > Change Working time?
> > 
> > I hope this helps.  Let us know how you get along.
> > 
> > Julie
> > Project MVP
> > 
> > Visit http://project.mvps.org/ for the FAQs and additional
> > information about Microsoft Project
> > 
> > On 5/24/2010 7:47 PM, player wrote:
> > > I’m using MS Project 2007, have several task linked with finish to start.  I
> > > have set date to schedule from, hours per day set to 8 and Working Monday
> > > thru Friday.
> > >
> > > My schedule shows Task 1 Duration 4 days, start Wed 6/2/10, Finish Mon 6/7/10
> > > Task 2 Duration 3 days, start Mon 6/7/10, Finish Thu 6/10/10
> > >
> > > Task 2 should have a Start Date of 6/8/10 not 6/7/10; what is causing this?
> > >
> > > Thanks in advance for your help.
> > >
> > .
> > 
0
Utf
5/25/2010 2:03:01 AM
This is a multi-part message in MIME format.

------=_NextPart_000_00C1_01CAFBE6.B4C21AB0
Content-Type: text/plain;
	charset="Windows-1252"
Content-Transfer-Encoding: quoted-printable

Hi Player,

You might like to see FAQ Item: 5. Default Working Hours

FAQs, companion products and other useful Project information can be =
seen at this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :-)

Mike Glen
Project MVP
See http://tinyurl.com/2xbhc for my free Project Tutorials=20
  "player" <player@discussions.microsoft.com> wrote in message =
news:2C1F8AE2-2931-4E41-8C2A-3588E813AED3@microsoft.com...
  OK what I did was made a new schedule using project default calender =
and=20
  working times and all is good for now.

  I would like to change working time from 7am to 3:30pm with 1/2 hour =
lunch=20
  from 12 to 12:30 but I need to submitt this in the AM. so I just =
turned off=20
  view times for now.

  Thanks for your help

  "player" wrote:

  > ok display of time shows start 8am and Finish 8am on the next day =
for a 1 Day=20
  > duration task
  >=20
  > and yes I have modified the calendar in Tools >options, calender Tab =
to =20
  > 7:00am to 12:00pm 12:30pm to 3:30pm
  >=20
  > Start dates still show starting on same date as predecessors finish =
Date
  >=20
  > Dont know why start time is 8am and finish time is 8am on next day =
for 1 day=20
  > task?
  >=20
  > "JulieS" wrote:
  >=20
  > > Player,
  > >=20
  > > Turn on the display of time.  Tools > Options, View tab and=20
  > > select a format that shows time as well as date.  That may help=20
  > > figure out what is going on.
  > >=20
  > > You mention that you have the standard setting hours per day of=20
  > > 8.  Have you modified the calendar in Tools > Change Working time?
  > >=20
  > > I hope this helps.  Let us know how you get along.
  > >=20
  > > Julie
  > > Project MVP
  > >=20
  > > Visit http://project.mvps.org/ for the FAQs and additional
  > > information about Microsoft Project
  > >=20
  > > On 5/24/2010 7:47 PM, player wrote:
  > > > I=E2=80=99m using MS Project 2007, have several task linked with =
finish to start.  I
  > > > have set date to schedule from, hours per day set to 8 and =
Working Monday
  > > > thru Friday.
  > > >
  > > > My schedule shows Task 1 Duration 4 days, start Wed 6/2/10, =
Finish Mon 6/7/10
  > > > Task 2 Duration 3 days, start Mon 6/7/10, Finish Thu 6/10/10
  > > >
  > > > Task 2 should have a Start Date of 6/8/10 not 6/7/10; what is =
causing this?
  > > >
  > > > Thanks in advance for your help.
  > > >
  > > .
  > >
------=_NextPart_000_00C1_01CAFBE6.B4C21AB0
Content-Type: text/html;
	charset="Windows-1252"
Content-Transfer-Encoding: quoted-printable

<!DOCTYPE HTML PUBLIC "-//W3C//DTD HTML 4.0 Transitional//EN">
<HTML><HEAD>
<META content=3Dtext/html;charset=3DWindows-1252 =
http-equiv=3DContent-Type>
<META name=3DGENERATOR content=3D"MSHTML 8.00.7600.16535"></HEAD>
<BODY style=3D"PADDING-LEFT: 10px; PADDING-RIGHT: 10px; PADDING-TOP: =
15px"=20
id=3DMailContainerBody leftMargin=3D0 topMargin=3D0 =
CanvasTabStop=3D"true"=20
name=3D"Compose message area">
<DIV><FONT face=3D"Comic Sans MS">Hi Player,</FONT></DIV>
<DIV>&nbsp;</DIV>
<DIV><FONT face=3D"Comic Sans MS">You might like to see FAQ Item: 5. =
Default=20
Working Hours</FONT></DIV>
<DIV>&nbsp;</DIV>
<DIV><FONT face=3D"Comic Sans MS">FAQs, companion products and other =
useful=20
Project information can be seen at this web address: <A=20
href=3D"http://project.mvps.org/faqs.htm">http://project.mvps.org/faqs.ht=
m</A></FONT></DIV>
<DIV>&nbsp;</DIV>
<DIV><FONT face=3D"Comic Sans MS">Hope this helps - please let us know =
how you get=20
on :-)</FONT></DIV>
<DIV>&nbsp;</DIV>
<DIV><FONT face=3D"Comic Sans MS">Mike Glen<BR>Project MVP<BR>See <A=20
href=3D"http://tinyurl.com/2xbhc">http://tinyurl.com/2xbhc</A> for my =
free Project=20
Tutorials </FONT></DIV>
<BLOCKQUOTE=20
style=3D"BORDER-LEFT: #000000 2px solid; PADDING-LEFT: 5px; =
PADDING-RIGHT: 0px; MARGIN-LEFT: 5px; MARGIN-RIGHT: 0px">
  <DIV>"player" &lt;<A=20
  =
href=3D"mailto:player@discussions.microsoft.com">player@discussions.micro=
soft.com</A>&gt;=20
  wrote in message <A=20
  =
href=3D"news:2C1F8AE2-2931-4E41-8C2A-3588E813AED3@microsoft.com">news:2C1=
F8AE2-2931-4E41-8C2A-3588E813AED3@microsoft.com</A>...</DIV>OK=20
  what I did was made a new schedule using project default calender and=20
  <BR>working times and all is good for now.<BR><BR>I would like to =
change=20
  working time from 7am to 3:30pm with 1/2 hour lunch <BR>from 12 to =
12:30 but I=20
  need to submitt this in the AM. so I just turned off <BR>view times =
for=20
  now.<BR><BR>Thanks for your help<BR><BR>"player" wrote:<BR><BR>&gt; ok =
display=20
  of time shows start 8am and Finish 8am on the next day for a 1 Day =
<BR>&gt;=20
  duration task<BR>&gt; <BR>&gt; and yes I have modified the calendar in =
Tools=20
  &gt;options, calender Tab to&nbsp; <BR>&gt; 7:00am to 12:00pm 12:30pm =
to=20
  3:30pm<BR>&gt; <BR>&gt; Start dates still show starting on same date =
as=20
  predecessors finish Date<BR>&gt; <BR>&gt; Dont know why start time is =
8am and=20
  finish time is 8am on next day for 1 day <BR>&gt; task?<BR>&gt; =
<BR>&gt;=20
  "JulieS" wrote:<BR>&gt; <BR>&gt; &gt; Player,<BR>&gt; &gt; <BR>&gt; =
&gt; Turn=20
  on the display of time.&nbsp; Tools &gt; Options, View tab and =
<BR>&gt; &gt;=20
  select a format that shows time as well as date.&nbsp; That may help =
<BR>&gt;=20
  &gt; figure out what is going on.<BR>&gt; &gt; <BR>&gt; &gt; You =
mention that=20
  you have the standard setting hours per day of <BR>&gt; &gt; 8.&nbsp; =
Have you=20
  modified the calendar in Tools &gt; Change Working time?<BR>&gt; &gt; =
<BR>&gt;=20
  &gt; I hope this helps.&nbsp; Let us know how you get along.<BR>&gt; =
&gt;=20
  <BR>&gt; &gt; Julie<BR>&gt; &gt; Project MVP<BR>&gt; &gt; <BR>&gt; =
&gt; Visit=20
  <A href=3D"http://project.mvps.org/">http://project.mvps.org/</A> for =
the FAQs=20
  and additional<BR>&gt; &gt; information about Microsoft =
Project<BR>&gt; &gt;=20
  <BR>&gt; &gt; On 5/24/2010 7:47 PM, player wrote:<BR>&gt; &gt; &gt; =
I=E2=80=99m=20
  using MS Project 2007, have several task linked with finish to =
start.&nbsp;=20
  I<BR>&gt; &gt; &gt; have set date to schedule from, hours per day set =
to 8 and=20
  Working Monday<BR>&gt; &gt; &gt; thru Friday.<BR>&gt; &gt; =
&gt;<BR>&gt; &gt;=20
  &gt; My schedule shows Task 1 Duration 4 days, start Wed 6/2/10, =
Finish Mon=20
  6/7/10<BR>&gt; &gt; &gt; Task 2 Duration 3 days, start Mon 6/7/10, =
Finish Thu=20
  6/10/10<BR>&gt; &gt; &gt;<BR>&gt; &gt; &gt; Task 2 should have a Start =
Date of=20
  6/8/10 not 6/7/10; what is causing this?<BR>&gt; &gt; &gt;<BR>&gt; =
&gt; &gt;=20
  Thanks in advance for your help.<BR>&gt; &gt; &gt;<BR>&gt; &gt; =
..<BR>&gt;=20
&gt;</BLOCKQUOTE></BODY></HTML>

------=_NextPart_000_00C1_01CAFBE6.B4C21AB0--

0
Mike
5/25/2010 7:46:02 AM
You're welcome player.  You can certainly change the working time 
in Tools> Change working time.  As Mike Glen, notes in the 
reference to the FAQ, the working time needs to be modified as 
you did, but you also need to change he default start and end 
time as well in Tools > Options, Calendar.

Also check the start time of your project in Project > Project 
Information.  My guess is your project starts at 8:00 not 7:00 -- 
thus the finish at 8:00 the next day.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project

On 5/24/2010 10:03 PM, player wrote:
> OK what I did was made a new schedule using project default calender and
> working times and all is good for now.
>
> I would like to change working time from 7am to 3:30pm with 1/2 hour lunch
> from 12 to 12:30 but I need to submitt this in the AM. so I just turned off
> view times for now.
>
> Thanks for your help
>
> "player" wrote:
>
>> ok display of time shows start 8am and Finish 8am on the next day for a 1 Day
>> duration task
>>
>> and yes I have modified the calendar in Tools>options, calender Tab to
>> 7:00am to 12:00pm 12:30pm to 3:30pm
>>
>> Start dates still show starting on same date as predecessors finish Date
>>
>> Dont know why start time is 8am and finish time is 8am on next day for 1 day
>> task?
>>
>> "JulieS" wrote:
>>
>>> Player,
>>>
>>> Turn on the display of time.  Tools>  Options, View tab and
>>> select a format that shows time as well as date.  That may help
>>> figure out what is going on.
>>>
>>> You mention that you have the standard setting hours per day of
>>> 8.  Have you modified the calendar in Tools>  Change Working time?
>>>
>>> I hope this helps.  Let us know how you get along.
>>>
>>> Julie
>>> Project MVP
>>>
>>> Visit http://project.mvps.org/ for the FAQs and additional
>>> information about Microsoft Project
>>>
>>> On 5/24/2010 7:47 PM, player wrote:
>>>> I’m using MS Project 2007, have several task linked with finish to start.  I
>>>> have set date to schedule from, hours per day set to 8 and Working Monday
>>>> thru Friday.
>>>>
>>>> My schedule shows Task 1 Duration 4 days, start Wed 6/2/10, Finish Mon 6/7/10
>>>> Task 2 Duration 3 days, start Mon 6/7/10, Finish Thu 6/10/10
>>>>
>>>> Task 2 should have a Start Date of 6/8/10 not 6/7/10; what is causing this?
>>>>
>>>> Thanks in advance for your help.
>>>>
>>> .
>>>
0
JulieS
5/25/2010 9:45:34 AM
Reply:

Similar Artilces:

Not sure if Excel can do what i need
Hello all, I am obviously a new user to excel. I have a psychological assessmen that needs to be computerised for ease of use in obtaining results. Here is what i would like to happen. I have 28 questions with fiv Likert scale options(0-4) for answers. Each question addresses 1 of different personality traits. So questions 1, 6, 8, 22 look at anger. Where as questions 2, 9, 28 look at happiness. What i would like is fo excel to group the answers and give me the total number for each trait. Then based on that number, give out a prewritten (which i would provide result of the assessment. ...

Need Min Value from Row and Heading Value that Corresponds to it.
I have a table that looks somewhat like this w/o the *'d headings: h1 h2 h3 h4 h5 h6 h7 *Min Price *Heading $5.00 $6.00 $3.00 $4.00 $9.00 $1.00 $9.00 $1.00 h6 $3.00 $6.00 $8.00 $65.00 $9.00 $2.00 $4.00 $2.00 h6 $4.00 $9.00 $5.00 $7.00 $1.00 $2.00 $8.00 $1.00 h5 $9.00 $7.00 $6.00 $3.00 $9.00 $8.00 $2.00 $2.00 h7 $7.00 $8.00 $9.00 $7.00 $9.00 $8.00 $8.00 $7.00 h1 I have several SKU's with various price contract/programs. I want to find the best price in one cell and the heading that would correspond to that cell in another. I was trying to do this with an expression ...

Date shows as 01/01/00
We have a spreadsheet that we want to enter a date in a cell. I have changed the format to Date 03/01/01 format but no matter what I do, any date is converted to 01/01/00. I have tried inserting a column, copying to another spreadsheet, etc. I know this is probably simple, but it's driving me crazy. Help please. In an un-used cell enter: =TODAY() if this is not the correct date, then touch CNTRL-ALT-F9 on the keyboard post what happens. -- Gary''s Student "Kmagg" wrote: > We have a spreadsheet that we want to enter a date in a cell. I have changed > the...

Excel need help
I have 2 columns a and b . a contains payment b contains balance. I have the entire col b with the formula. my ? is when the balance appearsin b it is in all the cells in that column.I only want it in the used ones, not the unused ones:( example $270.00 16,730.00 $270.00 16,460.00 $100.00 16,360.00 $300.00 16,060.00 $270.00 15,790.00 15,790.00 15,790.00 15,790.00 15,790.00 15,790.00 this 15790.00 is in col b...not a...I want no bal in unused cells -- fiftieslady ------------------------------------------------------------------------ fiftieslady's Profile: http://www.excelforum.co...

assign task from public folder
I am willing to have a task public folder to centralize all the task of my users. I find it impossible to assign a taks to someone from a public folder ? How can I manage to do this? Thanks Cyril ...

HELP.....Setting up Outlook express again
I've just installed everything on my computer again and im having trouble with outlook express. its asking for my incoming and outgoing server names and i have no idea what they are or where i get them, so i can access or set my account up again. if anyone knows can they please help me thanks!!!! you can reach me at : bl182ink@hotmail.com Amanda Arbuckle what type of account? who is the email provider? have you checked their website for assistance? -- "Amanda" <bl182ink@hotmail.com> wrote in message news:A37A86BC-5E22-4B1F-B6E3-9459C70971C1@microsoft.com... > I...

Need Help Linking Sheets
How can I link 2 pages without using the actual sheet as a reference? In other words, can I have two sheets linked by Identifying the same exact names one on each sheet? ...

Excel newbie needs help from math wiz (poker related)
I want to create a Excel workbook that will help in specific poker situations. Short version: I want to be able to calculate how often my opponent will need to fold for an all-in raise to show a positive expectation. Explanation: In poker you can win a hand by having the best hand at the end OR getting your opponent to fold. A common situation comes up where you have a "drawing hand" and face a bet by your opponent. In this situation you know you are currently behind in the hand, but have a chance to win if you catch some of your "outs" (cards that will give you th...

Wrong time in Outlook
Hi, I've got a really strange problem. My Mails in Outlook have all the wrong time - 9 hours back. This affects incoming and outgoing mails. It can't be a matter of the e-mail-provider because I've got accounts in gmx, web, yahoo, gmail and all have the same problem. Where can outlook get the wrong time ? The system time is correct of course. Thanks for your help. Ralf is the system time zone correct? whois shows your posting IP is in Germany... and windows defaults to pacific time zone so that would account for the difference. -- Diane Poremsky [MVP - Outlook] Author, Te...

Macro help needed........
How do I sort a particular column in ascending order and change the pag setup to landscape and margins to 0.25 using a macro code ? does anyone have a macro code for this ????? -- Message posted from http://www.ExcelForum.com Hi you have already received some answers in your previous threads please don't multipost! -- Regards Frank Kabel Frankfurt, Germany > How do I sort a particular column in ascending order and change the > page setup to landscape and margins to 0.25 using a macro code ? > > does anyone have a macro code for this ?????? > > > --- > Me...

Date Format Conversion?
I have a tab delimited text file with a column of dates. I copied and pasted a selection of them below as a reference, there are in reality over 35,000 rows of these dates. These text dates must be converted to the following date format and saved back into a text file as such: mm/dd/yyyy That includes leading zeroes in months and dates. E.g. 01/01/1999 To complicate matters, I need to explain the process to others. Does anyone even know where I should begin? THANK YOU, - Chris +++++++++++++++++++++++++++ 9031989 8131990 9201989 1271990 10291989 1081990 3041990 10051989 4191990 10...

Need to test a mobo
I had a power surge about 3 weeks ago - lost a drive, now making ticking noises. I had another two drive that seem to work sporadically now. So, I thought it might have been my power supply. Bought a tester and found out that all seems well. Next, I bought a new hard drive and found that it was also acting up - making noises like whirring up and down (like the other drives I thought were dead). So I am starting to wonder if it is my mobo - but how can I test this out? I am using a dual boot - Win XP and Win 7 - both drives work and don't work. Up and down. Right now my Win7 ...

Help needed
is there anyway you can see what links to other workbooks are associated with the workbook you have open. The problem i am having is when i open the workbook in question a message appears and states "The workbook you opened contains automatic links to information in another workbook. do you want to update this workbook with changes made to the other workbook" Yes....... No. if i click No the workbook opens, however if i click Yes the workbook just hangs and i have to go into task manager to shut down the system. I can only assume that there is a problem with one of the links....

Need help on this....thanks
I have an Excel worksheet which stored a survey outcome of over 1200 members. There are over 30 questions in the survey and the first column captured the member ID. The problem is 3 of the survey questions that allow multiple answers, instead the answer for those three questions are captured in seperate column, the answers are stored in a single column and it makes it very difficult to analysis those result. As a result I created addittional columns depending on the total number of the answers available for that question and assign the result manually to that column. It is very time consuming ...

Why is a .WAV file NOT automatically playing when I start the PPT
I inserted a .wav file in my powerpoint show and when I go to "view show," the animations work but the sound file does not play - either automatically OR on mouse click. The other animations and their "effect options" sounds play fine, but NOT the sound icon. I have checked with our school technician and it is not a hardware problem b/c windows media player works fine. Can you help me? I am a middle school special educator and I teach autistic students. I need to run the Powerpoint I created for my disabled student to interact with. Can you help me? Th...

Help with formula 12-17-09
Let's say I have in cell A1 a combo box with options: 1. Expense 2. Refund 3. Tax In cell B1 I will type a number In cell C3 I want a formula like this: If in cell A1 I have selected 1. Expense than calculate B1*25 If in cell A1 I have selected 2. Refund than calculate B1*50 If in cell A1 I have selected 3. Tax than calculate B1*150 How can I apply the combo box to entire column, like if I go to row 2 to find in B1 the combo box from A1 and in C2 the formula from C1 Thanks for the help In c1: =IF(A1="Expense",B1*25,IF(A1="Refund",B1*50,B1*150)) Micky ...

Help with Error
I got this error recently, and just want to make sure I'm reading it right. Logon Failure on database "First Storage Group\Mailbox Store (EXCHANGE)" - Windows 2000 account PARADIGM\user1; mailbox /o=Paradigm/ou=First Administrative Group/cn=Recipients/cn=user2. Error: -2147221231 Does this mean the user1 tried to access the user2 mailbox and failed? Thanks in advance hello albert, well, this looks familiar to: http://support.microsoft.com/default.aspx?scid=kb;en-us;260782 and http://support.microsoft.com/default.aspx?scid=kb;en-us;309113 regards, Alex "AlbertP&quo...

I need Help
I have a random popup that i cant stop,when it does come up it seems to know what i was looking at,like when i was looking for registry cleaner it popped up and showed me one,any help would be great. On Jan 22, 6:57=A0am, Larry <La...@discussions.microsoft.com> wrote: > I have a random popup that i cant stop,when it does come up it seems to k= now > what i was looking at,like when i was looking for registry cleaner it pop= ped > up and showed me one,any help would be great. To eliminate questions and guessing, please provide additional information about your sys...

need help badly
How do you print ole objects.. Thanks lachanda -- Message posted via AccessMonster.com http://www.accessmonster.com/Uwe/Forums.aspx/access-forms/200710/1 On Wed, 03 Oct 2007 18:13:40 GMT, "misschanda via AccessMonster.com" <u36612@uwe> wrote: >How do you print ole objects.. >Thanks >lachanda What *kind* of OLE objects? Many of them are binary blobs (such as programs) which are inherently not printable. More details please! John W. Vinson [MVP] ...

Stuck in review and need to be in design.
I am using Visio 2007. I need to complete the diagram that I have been working on and I hit the review key by mistake. How do I get back to the design screen? On Wed, 4 Nov 2009 16:14:01 -0800, cameron <cameron@discussions.microsoft.com> wrote: >I am using Visio 2007. I need to complete the diagram that I have been >working on and I hit the review key by mistake. How do I get back to the >design screen? menu Tools -> Track Markup and then close the Review window. -- Regards, Paul Herber, Sandrila Ltd. DFD/SSADM for Visio http://www.visio-dfd.sa...

help with a table
now that I set up a table through importing the data. I realized that I had some other data being emailed to me. how do i import it in that same table? On Fri, 29 Jun 2007 11:39:05 -0700, Maggie <schmidt.margaret@gmail.com> wrote: >now that I set up a table through importing the data. I realized that >I had some other data being emailed to me. how do i import it in that >same table? Use File... Get External Data... Link to link to a textfile containing the information from the EMail, and run an Append query to append it into your stored table. John W. Vinso...

Help, MVP!
Milly, Sue, Vince.. Can you help 'fix' this- I have still not found the cure, thank you! Outlook 2000 (Internet Only) is set to check for mail ever five minutes. However, when it does so, Outlook now insists on displaying the dialog box stating that the "Requested tasks were completed successfully." The dialog box has a "Hide this message" box which is checked, and the push pin is not 'set'. I must have messed up a setting when I reset my toolbars... (issue resolved - I accidentally pinned the toolbar to the desktop, went nuts till I figure out a doub...

Need Help Despertly!
I am in a desperate situation. I had to reformat my hard drive. Prior to do this, I copied my entire User Profile to another drive. I can now access my User Profile information from Windows Explorer. Now that I installed Microsoft Outlook, I do not see any of my Contacts. I need to restore my Contacts to the new Outlook installation. Again, I did save my entire "User Profile" from my previous installation of Windows 2000 Professional. I just do not know how to access my Contact information from Outlook that included addresses and phone numbers and such. Any help would be greatly appr...

CRM 1.2 Security Service Not starting
I have CRM 1.2 and SQL on the same box. When the server is restarted, the CRM Security Service fails to start. I must manually start the service. Any ideas? TIA -RS See TechKnowledge Error "The Microsoft CRM Security Service Failed to Start" During the Microsoft CRM Server Installation When Microsoft CRM and SQL Server 2000 are Installed on the same machine Mounim >-----Original Message----- >I have CRM 1.2 and SQL on the same box. >When the server is restarted, the CRM Security Service fails to start. >I must manually start the service. >Any ideas? >TIA ...

Plug in needed
Looking for an Outlook plug in which, on reply to a e-mail, will:- a) allow selective quoting only, and b) not top quote. Anything around at all? Much to my horror (sorry guys) the Boss wants us to use Outofluck at work! -- On the carpool lane lane to Nirvana. John Phillips <flatulentdingo@deadspam.com> wrote: > Looking for an Outlook plug in which, on reply to a e-mail, will:- > > a) allow selective quoting only, and > > b) not top quote. > > Anything around at all? The best Outlook adjunct I've found for quote handling on replies is Outlook-Quotef...