Does MS Project 2007 automatically flag a holiday that falls on the weekend 
to the prior/following work day or is this something that I can change?  
Example, July 4, 2010 was marked as a holiday, but it is showing up as July 5 
being a non-working day for the holiday.  The same thing happens for Christmas
0
Utf
5/25/2010 3:13:01 PM
project 1276 articles. 0 followers. Follow

5 Replies
1603 Views

Similar Articles

[PageSpeed] 30

Amy --

No, Microsoft Project 2007 does NOT automatically flag holidays that occur 
on a Saturday and Sunday, and then reschedule them to the preceding Friday 
or following Monday.  The reason the software does not do this is because 
every organization has different policies concerning what happens when a 
holiday falls on a weekend.  In the 13+ years I have worked with this tool, 
I have seen the following company policies for weekend holidays:

-- If the holiday falls on a Saturday, the preceding Friday is the 
recognized holiday; if the holiday falls on a Sunday, the following Monday 
is the recognized holiday (this is the most common, but not every company 
does this).

-- If the holiday falls on a weekend, the preceding Friday is always the 
recognized holiday.

-- If the holiday falls on a weekend, the following Monday is always the 
recognized holiday.

-- If the holiday falls on a weekend, there is no recognized holiday on the 
preceding Friday or following Monday.  Instead, each worker gets one 
additional personal holiday which he/she can use as he/she wishes.

Given the above scenarios, see why Microsoft Project 2007 doesn't do what 
you hoped it would do in regard to weekend holidays?  So, what you need to 
do is to create additional instances of the holiday according to your 
company's policy.  For example, Independence Day this year falls on a 
Sunday.  So, you would need to create one additional instance of 
Independence Day to set July 5th as the holiday.  Also, when you create your 
company holidays, click the Details button for each holiday and set the 
holiday to recur 2 or more years into the future.  I personally like to 
create 5 years of holidays to minimize the amount of work I must do.

Hope this helps.

-- 
Dale A. Howard [MVP]
VP of Educational Services
msProjectExperts
http://www.msprojectexperts.com
http://www.projectserverexperts.com
"We write the books on Project Server"


"Amy U" <Amy U@discussions.microsoft.com> wrote in message 
news:6F1FCE17-A786-4F45-989E-AE771E2D0C88@microsoft.com...
> Does MS Project 2007 automatically flag a holiday that falls on the 
> weekend
> to the prior/following work day or is this something that I can change?
> Example, July 4, 2010 was marked as a holiday, but it is showing up as 
> July 5
> being a non-working day for the holiday.  The same thing happens for 
> Christmas 

0
Dale
5/25/2010 8:51:08 PM
Dale,

In my case, in the Enterprise global the holiday is marked as July 5 vs. 
July 4 and I am wondering how to go about changing that.  Please advise.  
Thanks!

"Dale Howard [MVP]" wrote:

> Amy --
> 
> No, Microsoft Project 2007 does NOT automatically flag holidays that occur 
> on a Saturday and Sunday, and then reschedule them to the preceding Friday 
> or following Monday.  The reason the software does not do this is because 
> every organization has different policies concerning what happens when a 
> holiday falls on a weekend.  In the 13+ years I have worked with this tool, 
> I have seen the following company policies for weekend holidays:
> 
> -- If the holiday falls on a Saturday, the preceding Friday is the 
> recognized holiday; if the holiday falls on a Sunday, the following Monday 
> is the recognized holiday (this is the most common, but not every company 
> does this).
> 
> -- If the holiday falls on a weekend, the preceding Friday is always the 
> recognized holiday.
> 
> -- If the holiday falls on a weekend, the following Monday is always the 
> recognized holiday.
> 
> -- If the holiday falls on a weekend, there is no recognized holiday on the 
> preceding Friday or following Monday.  Instead, each worker gets one 
> additional personal holiday which he/she can use as he/she wishes.
> 
> Given the above scenarios, see why Microsoft Project 2007 doesn't do what 
> you hoped it would do in regard to weekend holidays?  So, what you need to 
> do is to create additional instances of the holiday according to your 
> company's policy.  For example, Independence Day this year falls on a 
> Sunday.  So, you would need to create one additional instance of 
> Independence Day to set July 5th as the holiday.  Also, when you create your 
> company holidays, click the Details button for each holiday and set the 
> holiday to recur 2 or more years into the future.  I personally like to 
> create 5 years of holidays to minimize the amount of work I must do.
> 
> Hope this helps.
> 
> -- 
> Dale A. Howard [MVP]
> VP of Educational Services
> msProjectExperts
> http://www.msprojectexperts.com
> http://www.projectserverexperts.com
> "We write the books on Project Server"
> 
> 
> "Amy U" <Amy U@discussions.microsoft.com> wrote in message 
> news:6F1FCE17-A786-4F45-989E-AE771E2D0C88@microsoft.com...
> > Does MS Project 2007 automatically flag a holiday that falls on the 
> > weekend
> > to the prior/following work day or is this something that I can change?
> > Example, July 4, 2010 was marked as a holiday, but it is showing up as 
> > July 5
> > being a non-working day for the holiday.  The same thing happens for 
> > Christmas 
> 
0
Utf
6/3/2010 5:33:01 PM
Amy U --

You have to be a Project Server administrator to perform the following 
steps:

1.  Log into PWA and then click the Server Settings link in the Quick Launch 
menu.
2.  Click the Enterprise Calendars link in the Enterprise Data section of 
the Server Settings page.
3.  Select the Standard calendar (assuming that is the calendar your 
organization uses) and click the Edit Calendar button.

The system opens the enterprise Standard calendar for editing in Microsoft 
Project 2007.

4.  Set the holidays according to your company's standards.
5.  Click the OK button.

Hope this helps.

-- 
Dale A. Howard [MVP]
VP of Educational Services
msProjectExperts
http://www.msprojectexperts.com
http://www.projectserverexperts.com
"We write the books on Project Server"


"Amy U" <AmyU@discussions.microsoft.com> wrote in message 
news:8A9B8386-EDF0-435C-BB04-552B798D2931@microsoft.com...
> Dale,
>
> In my case, in the Enterprise global the holiday is marked as July 5 vs.
> July 4 and I am wondering how to go about changing that.  Please advise.
> Thanks!
>
> "Dale Howard [MVP]" wrote:
>
>> Amy --
>>
>> No, Microsoft Project 2007 does NOT automatically flag holidays that 
>> occur
>> on a Saturday and Sunday, and then reschedule them to the preceding 
>> Friday
>> or following Monday.  The reason the software does not do this is because
>> every organization has different policies concerning what happens when a
>> holiday falls on a weekend.  In the 13+ years I have worked with this 
>> tool,
>> I have seen the following company policies for weekend holidays:
>>
>> -- If the holiday falls on a Saturday, the preceding Friday is the
>> recognized holiday; if the holiday falls on a Sunday, the following 
>> Monday
>> is the recognized holiday (this is the most common, but not every company
>> does this).
>>
>> -- If the holiday falls on a weekend, the preceding Friday is always the
>> recognized holiday.
>>
>> -- If the holiday falls on a weekend, the following Monday is always the
>> recognized holiday.
>>
>> -- If the holiday falls on a weekend, there is no recognized holiday on 
>> the
>> preceding Friday or following Monday.  Instead, each worker gets one
>> additional personal holiday which he/she can use as he/she wishes.
>>
>> Given the above scenarios, see why Microsoft Project 2007 doesn't do what
>> you hoped it would do in regard to weekend holidays?  So, what you need 
>> to
>> do is to create additional instances of the holiday according to your
>> company's policy.  For example, Independence Day this year falls on a
>> Sunday.  So, you would need to create one additional instance of
>> Independence Day to set July 5th as the holiday.  Also, when you create 
>> your
>> company holidays, click the Details button for each holiday and set the
>> holiday to recur 2 or more years into the future.  I personally like to
>> create 5 years of holidays to minimize the amount of work I must do.
>>
>> Hope this helps.
>>
>> -- 
>> Dale A. Howard [MVP]
>> VP of Educational Services
>> msProjectExperts
>> http://www.msprojectexperts.com
>> http://www.projectserverexperts.com
>> "We write the books on Project Server"
>>
>>
>> "Amy U" <Amy U@discussions.microsoft.com> wrote in message
>> news:6F1FCE17-A786-4F45-989E-AE771E2D0C88@microsoft.com...
>> > Does MS Project 2007 automatically flag a holiday that falls on the
>> > weekend
>> > to the prior/following work day or is this something that I can change?
>> > Example, July 4, 2010 was marked as a holiday, but it is showing up as
>> > July 5
>> > being a non-working day for the holiday.  The same thing happens for
>> > Christmas
>> 
0
Dale
6/3/2010 6:30:43 PM
I am the administrator and had looked at the steps that you mentioned, 
however, the Standard calendar looks to be checked out and so the Edit 
Calendar is grayed out and I cannot choose it.  Next steps?

"Dale Howard [MVP]" wrote:

> Amy U --
> 
> You have to be a Project Server administrator to perform the following 
> steps:
> 
> 1.  Log into PWA and then click the Server Settings link in the Quick Launch 
> menu.
> 2.  Click the Enterprise Calendars link in the Enterprise Data section of 
> the Server Settings page.
> 3.  Select the Standard calendar (assuming that is the calendar your 
> organization uses) and click the Edit Calendar button.
> 
> The system opens the enterprise Standard calendar for editing in Microsoft 
> Project 2007.
> 
> 4.  Set the holidays according to your company's standards.
> 5.  Click the OK button.
> 
> Hope this helps.
> 
> -- 
> Dale A. Howard [MVP]
> VP of Educational Services
> msProjectExperts
> http://www.msprojectexperts.com
> http://www.projectserverexperts.com
> "We write the books on Project Server"
> 
> 
> "Amy U" <AmyU@discussions.microsoft.com> wrote in message 
> news:8A9B8386-EDF0-435C-BB04-552B798D2931@microsoft.com...
> > Dale,
> >
> > In my case, in the Enterprise global the holiday is marked as July 5 vs.
> > July 4 and I am wondering how to go about changing that.  Please advise.
> > Thanks!
> >
> > "Dale Howard [MVP]" wrote:
> >
> >> Amy --
> >>
> >> No, Microsoft Project 2007 does NOT automatically flag holidays that 
> >> occur
> >> on a Saturday and Sunday, and then reschedule them to the preceding 
> >> Friday
> >> or following Monday.  The reason the software does not do this is because
> >> every organization has different policies concerning what happens when a
> >> holiday falls on a weekend.  In the 13+ years I have worked with this 
> >> tool,
> >> I have seen the following company policies for weekend holidays:
> >>
> >> -- If the holiday falls on a Saturday, the preceding Friday is the
> >> recognized holiday; if the holiday falls on a Sunday, the following 
> >> Monday
> >> is the recognized holiday (this is the most common, but not every company
> >> does this).
> >>
> >> -- If the holiday falls on a weekend, the preceding Friday is always the
> >> recognized holiday.
> >>
> >> -- If the holiday falls on a weekend, the following Monday is always the
> >> recognized holiday.
> >>
> >> -- If the holiday falls on a weekend, there is no recognized holiday on 
> >> the
> >> preceding Friday or following Monday.  Instead, each worker gets one
> >> additional personal holiday which he/she can use as he/she wishes.
> >>
> >> Given the above scenarios, see why Microsoft Project 2007 doesn't do what
> >> you hoped it would do in regard to weekend holidays?  So, what you need 
> >> to
> >> do is to create additional instances of the holiday according to your
> >> company's policy.  For example, Independence Day this year falls on a
> >> Sunday.  So, you would need to create one additional instance of
> >> Independence Day to set July 5th as the holiday.  Also, when you create 
> >> your
> >> company holidays, click the Details button for each holiday and set the
> >> holiday to recur 2 or more years into the future.  I personally like to
> >> create 5 years of holidays to minimize the amount of work I must do.
> >>
> >> Hope this helps.
> >>
> >> -- 
> >> Dale A. Howard [MVP]
> >> VP of Educational Services
> >> msProjectExperts
> >> http://www.msprojectexperts.com
> >> http://www.projectserverexperts.com
> >> "We write the books on Project Server"
> >>
> >>
> >> "Amy U" <Amy U@discussions.microsoft.com> wrote in message
> >> news:6F1FCE17-A786-4F45-989E-AE771E2D0C88@microsoft.com...
> >> > Does MS Project 2007 automatically flag a holiday that falls on the
> >> > weekend
> >> > to the prior/following work day or is this something that I can change?
> >> > Example, July 4, 2010 was marked as a holiday, but it is showing up as
> >> > July 5
> >> > being a non-working day for the holiday.  The same thing happens for
> >> > Christmas
> >> 
0
Utf
6/4/2010 1:02:52 PM
Amy U --

If the enterprise Standard calendar is "stuck" in a checked out condition, 
you need to force check it in using the following steps:

1.  Log into PWA with administrator permissions.
2.  Click Server Settings - Force Check In Enterprise Objects.
3.  Click the pick list at the top and select the Enterprise Calendars item.
4.  Select the Standard calendar and click the Check In button.

Also, you might find the following books helpful to you in your work with 
Project Server 2007:

http://www.projectserverbooks.com/books/implementingadministeringprojectserver2007.aspx

http://www.projectserverbooks.com/books/managingprojectsprojectserver2007.aspx

Hope this helps.

-- 
Dale A. Howard [MVP]
VP of Educational Services
msProjectExperts
http://www.msprojectexperts.com
http://www.projectserverexperts.com
"We write the books on Project Server"


"Amy U" <AmyU@discussions.microsoft.com> wrote in message 
news:4EAAA2FF-AA8E-4846-B341-C53280E37843@microsoft.com...
> I am the administrator and had looked at the steps that you mentioned,
> however, the Standard calendar looks to be checked out and so the Edit
> Calendar is grayed out and I cannot choose it.  Next steps?
>
> "Dale Howard [MVP]" wrote:
>
>> Amy U --
>>
>> You have to be a Project Server administrator to perform the following
>> steps:
>>
>> 1.  Log into PWA and then click the Server Settings link in the Quick 
>> Launch
>> menu.
>> 2.  Click the Enterprise Calendars link in the Enterprise Data section of
>> the Server Settings page.
>> 3.  Select the Standard calendar (assuming that is the calendar your
>> organization uses) and click the Edit Calendar button.
>>
>> The system opens the enterprise Standard calendar for editing in 
>> Microsoft
>> Project 2007.
>>
>> 4.  Set the holidays according to your company's standards.
>> 5.  Click the OK button.
>>
>> Hope this helps.
>>
>> -- 
>> Dale A. Howard [MVP]
>> VP of Educational Services
>> msProjectExperts
>> http://www.msprojectexperts.com
>> http://www.projectserverexperts.com
>> "We write the books on Project Server"
>>
>>
>> "Amy U" <AmyU@discussions.microsoft.com> wrote in message
>> news:8A9B8386-EDF0-435C-BB04-552B798D2931@microsoft.com...
>> > Dale,
>> >
>> > In my case, in the Enterprise global the holiday is marked as July 5 
>> > vs.
>> > July 4 and I am wondering how to go about changing that.  Please 
>> > advise.
>> > Thanks!
>> >
>> > "Dale Howard [MVP]" wrote:
>> >
>> >> Amy --
>> >>
>> >> No, Microsoft Project 2007 does NOT automatically flag holidays that
>> >> occur
>> >> on a Saturday and Sunday, and then reschedule them to the preceding
>> >> Friday
>> >> or following Monday.  The reason the software does not do this is 
>> >> because
>> >> every organization has different policies concerning what happens when 
>> >> a
>> >> holiday falls on a weekend.  In the 13+ years I have worked with this
>> >> tool,
>> >> I have seen the following company policies for weekend holidays:
>> >>
>> >> -- If the holiday falls on a Saturday, the preceding Friday is the
>> >> recognized holiday; if the holiday falls on a Sunday, the following
>> >> Monday
>> >> is the recognized holiday (this is the most common, but not every 
>> >> company
>> >> does this).
>> >>
>> >> -- If the holiday falls on a weekend, the preceding Friday is always 
>> >> the
>> >> recognized holiday.
>> >>
>> >> -- If the holiday falls on a weekend, the following Monday is always 
>> >> the
>> >> recognized holiday.
>> >>
>> >> -- If the holiday falls on a weekend, there is no recognized holiday 
>> >> on
>> >> the
>> >> preceding Friday or following Monday.  Instead, each worker gets one
>> >> additional personal holiday which he/she can use as he/she wishes.
>> >>
>> >> Given the above scenarios, see why Microsoft Project 2007 doesn't do 
>> >> what
>> >> you hoped it would do in regard to weekend holidays?  So, what you 
>> >> need
>> >> to
>> >> do is to create additional instances of the holiday according to your
>> >> company's policy.  For example, Independence Day this year falls on a
>> >> Sunday.  So, you would need to create one additional instance of
>> >> Independence Day to set July 5th as the holiday.  Also, when you 
>> >> create
>> >> your
>> >> company holidays, click the Details button for each holiday and set 
>> >> the
>> >> holiday to recur 2 or more years into the future.  I personally like 
>> >> to
>> >> create 5 years of holidays to minimize the amount of work I must do.
>> >>
>> >> Hope this helps.
>> >>
>> >> -- 
>> >> Dale A. Howard [MVP]
>> >> VP of Educational Services
>> >> msProjectExperts
>> >> http://www.msprojectexperts.com
>> >> http://www.projectserverexperts.com
>> >> "We write the books on Project Server"
>> >>
>> >>
>> >> "Amy U" <Amy U@discussions.microsoft.com> wrote in message
>> >> news:6F1FCE17-A786-4F45-989E-AE771E2D0C88@microsoft.com...
>> >> > Does MS Project 2007 automatically flag a holiday that falls on the
>> >> > weekend
>> >> > to the prior/following work day or is this something that I can 
>> >> > change?
>> >> > Example, July 4, 2010 was marked as a holiday, but it is showing up 
>> >> > as
>> >> > July 5
>> >> > being a non-working day for the holiday.  The same thing happens for
>> >> > Christmas
>> >> 
0
Dale
6/4/2010 2:14:36 PM
Reply:

Similar Artilces:

External data link change
Hi, I've a sheet linked to an external data on the net, and I would like that a cell in this sheet to indicate the last date and time it was updated, the simplest way the better but I can do some programming too. Thanks for your attention, -- Domingos Junqueira No need of help any more, I solved the question. Thanks again ...

Why does the change change to a number?
Hi all, I've noticed something wierd and always wondered WHY it happens. When you type a date into a cell, and then change the Formatting of it to a 'general' cell, it turns into a number. How does it come up with that number? What is the significance? i.e. type today's date of "12/7/2007" - change it to a 'General' format, and it then says "39423". I'm a trainer of Excel and this question always comes up. I'm curious myself too. Thanks! Joe It's the number of days since January zero 1900 using Excel default for windows (M...

changing the way Excel displays selected cells
Is there a way to change the way Excel displays selected cells? I'm interested in viewing all the selected cells highlighted (with light blue for instance), but by default excel highlights all the cells but not the first one the same occurs when you define a range with no adyacents cells Your definition of the display is not quite correct. Excel highlights the current cell, Excel also highlights a selecte range. The currently selected cell is generally the first of a range, bu press enter and the current cell changes and becomes the second, the third etc in the range. You cannot...

DST changes for Exchange 5.5
I noticed the 2007 DST Calendar Update "Exchange tool" is available now: http://support.microsoft.com/kb/930879 This will seemingly take care of calendars for mailboxes still on Exchange 5.5 servers, as Exchange 5.5 is listed as "compatible" . However would this address the CDO issues such as BlackBerry users and OWA users still on Exchange 5.5 ? Thanks in advance, Itrcb4 On Mon, 12 Feb 2007 14:31:00 -0800, itrcb4 <itrcb4@discussions.microsoft.com> wrote: >I noticed the 2007 DST Calendar Update "Exchange tool" is available now: > >http://su...

Track Changes
How do i remove the track changes in outlook? When i press "Enter", a symbol that represents "Enter" will appears. Same for space etc. ...

more on VBA function name change
I thought I'd start a new thread since I haven't received any replies to my first one... To recap: I've declared a function in a module using mixed case: Function TMDE_Category (FormName As Form) I noticed recently that it appeared in the module as Function tmde_category(FormName As Form) I changed it back to the mixed case declaration, saved the module, exited the app, reopened it and looked. The function had changed back to the all lowercase declaration. Things I've tried since the original post: Using the databse documenter, I selected all ob...

Can't Publish changes with Deploy Manager
After a migration process, I can't publish the changes made on CRM. When I try do this in Deploy Manager I get the follow error: ---------------------------------------------------------------------------- ----- Publish done with errors. See the event log to get deitails NETRA-INOVACAO: ***Error*** Failed to download XSL template files from Web Server ---------------------------------------------------------------------------- ----- Can somebody help me? I don't know if the migration process have any relationship with the error. Thank you for pay attention. []'s Vin�cius Pitta...

enterprise custom field for overdue tasks
I'm trying to create a view that shows overdue tasks and am having some trouble. I went into enterprise custom fields and tried to create a new Task > Date field with the following formula :IIf([Finish]<[Current Date] And [% Complete]<100,"red","green"). Now I would expect it to populate that field with either "red" or "green" depending on if it meets the criteria. Furthermore I would like to use graphical indicators to show red or green stoplights. However, I cannot get this formula to work - When I add the new field to a ...

How to change icon for my application
Hi, I am currently developing an application on visual studio 6.0, and i wish to change the MFC icon on my application header. Anyone can help? Thank you. Raed Sawalha wrote: > Hi, I am currently developing an application on visual studio 6.0, and i > wish to change the MFC icon on my application header. Anyone can help? Thank > you. > > Open the icon resource for editing by double clicking. Then notice the control just above the editing grid that lets you switch between editing the large icon and editing the small one. -- Scott McPhillips [VC++ MVP] thanx that work...

How to change newsgroup message font
Like many other ribbon based programs I sometimes struggle to find how to make a change. This time its how to change the font just for newsgroup messages? regards "nobody" wrote in message news:EWTao.39493$GF5.7129@hurricane... > Like many other ribbon based programs I sometimes struggle to find how to make a change. This time its how to change the font just for newsgroup messages? Newsgroup messages are usually plain text. The font used is that selected at [no name tab] > Options > Mail > Read > Fonts for the encoding specified for the messag...

Notify change of email address when changing ISP
How do I notify my entire address book of an email address when I change ISP's? Thanks By sending a mail to everyone ? If you do so, please use BCC for the adresses, this way you won't spread everybody's e-mail adres to everybody. Niels Bob Baker wrote: > How do I notify my entire address book of an email address when I change ISP's? > Thanks ...

Change a formula to an acual number
I want to change the formula I have created to the number it has created Example: Cell A1 is the number 1. Cell A2 is the formula =a1+1 creatin the number 2. I want this to be a two not a formula. Any ideas? Laura, copy, then paste special, valves -- Paul B Always backup your data before trying something new Please post any response to the newsgroups so others can benefit from it Feedback on answers is always appreciated! Using Excel 2000 & 97 ** remove news from my email address to reply by email ** "Laura" <anonymous@discussions.microsoft.com> wrote in message news...

Problem Changing an Investment Name
I am trying to change an investment name and Money 2006 tells me "The name or symbol 'TRP Spectrum Income' has already been used for a deleted investment. Please enter a different name." When I go to delete investments the name does not appear! Any ideas on how I get Money to accept the name change? This is the first time I have run into this situation and I have made numerous name changes in Money over the years. In microsoft.public.money, Ken wrote: >I am trying to change an investment name and Money 2006 tells me "The name >or symbol 'TRP Spec...

Should I change this code?
Should I change 556 to 560???..............Thanks for your help..........Bob Private Sub Command560_Click() On Error GoTo Err_Command556_Click Dim stDocName As String Dim stLinkCriteria As String stDocName = "frmClientInfomation" DoCmd.OpenForm stDocName, , , stLinkCriteria Exit_Command556_Click: Exit Sub Err_Command556_Click: MsgBox Err.Description Resume Exit_Command556_Click End Sub On Sun, 15 Jul 2007 16:37:26 +1200, "Bob V" <rjvance@ihug.co.nz> wrote: > >Should I change 556 to 560???..............Thanks for your help.....

How to change default font in Outlook 2003
Can someone tell me how to change tthe default font in Outlook 2003 when composing a new email. It always comes up as Times New Roman. I remember somewhere that I specified that Outlook should use Word as the text editor and that seems to be the case. I have Arial as my default font in Word but this seems to make no difference when using Outlook. Hi, Please go to Tools > Setting > Mail Format > Stationery and Fonts > Fonts It's right there :) On 20 Nov 2005 06:28:45 -0800, amarsarit@gmail.com wrote: >Hi, >Please go to Tools > Setting > Mail Format > Statione...

icon changes with change of extension
when we change the extension of a file in windows, its icon also changes..... how does windows do tht. in my application i require a similar approach. i want the icon to be dependent on the file extension not on the attributes of the file. i have gone trough the registry but things are not very clear. Windows has listed all the file extensions avaliable there, but there is no general way to extract icons for those extension... kindly help icon changes with change of extension "Neelu" <nemesia31@gmail.com> wrote in message news:1161232739.720722.120950@b28g2000cwb.google...

Field Type Change
I am trying to change a free text field to a drop down menu in my current database, that already has data entered for this particular field, in order to avoid multiple versions of the same organization that are just typed in differently. I'm assuming that I'll need to recode the different versions of an entry to make them uniform but after that, I'm unsure how to proceed so I won't lose any data. Is this possible or will I need to delete the field, recreate it as a drop down and then re-enter the data? Thanks in advance! Mike Thanks everyone for all the input and advice s...

Tracking Changes
I am the author of a document and am making revisions to it. I want to chnage the redline color to denote new edits from the 1st version. Can anyone guide me through this process? I am sure it is easy but I cannot figure it out. THanks Peter On Wed, 10 Feb 2010 07:08:06 -0800, Peter SSI <Peter SSI@discussions.microsoft.com> wrote: >I am the author of a document and am making revisions to it. I want to >chnage the redline color to denote new edits from the 1st version. Can >anyone guide me through this process? I am sure it is easy but I cannot >figure i...

Save Changes? #2
Sometimes, but not always, Excel asks if I want to save the current file, even though I've made no changes. Does anyone know why this occurs, and if there is a setting I can change to avoid the prompt unless actual changes are made? Thank you. Sprinks There are a number of functions that will update themselves when the workbook is opened, and this causes Excel to act as though the workbook has been changed. These functions include NOW() , TODAY(), ROW(), etc. See Volatile Functions in help for more info. -- Cordially, Chip Pearson Microsoft MVP - Excel Pearson Software Consult...

colour change of dated box
How can I change the colour of a dated box of excel after the date is over. I want the programme to read date automatically from pc and change colour. try Conditional Formatting In 2003: 1. Select the cells you want to format 2. Choose Format, Conditional Formatting 3. Choose Cell Value Is from the first drop down 3. Choose Formula is from the first drop down 4. Choose less than 5. In the third box, enter =TODAY() 6. Click the Format button 7. Choose a color on the Patterns tab (or any available option) 7. Click OK twice. -- Hope this is helpful Appreciate that you provide your feedbac...

Daylight saving time changes for Exchange 2003 server
Hi guys, I was wondering how other real life systems administrators are preparing for the upcoming “2007 global time zone update for Windows” (daylight time change for exchange 2003 server). I'd like to know what contingency plans are being planned out to implement this update and what practical ideas you think thus far are the best. I would greatly value your input. http://www.microsoft.com/windows/timezone/dst2007.mspx -Thanks! ...

changes made but how do I revert !
When I deleted messages they used to dissapear straight away. Now when I delete a message it has a strike through line but the message remains, although it dissapears after I close outlook. I should also add that I use SPAM Inspector but I think this is an Outlook problem caused by some changes. the moral here is change one thing at a time ! Any ideas from anyone. email address required remove to be removed ! Kind regards Nigel Are you using an IMAP account? --� Milly Staples [MVP - Outlook] Post all replies to the group to keep the discussion intact. After searching google.groups.co...

Question about Excel (Office) auditing/changes
I have a document that will need to be posted on a website available for users to download & change/approve. The approval process will not make any changes at all to the document. However, I do need to know they've opened the document. Is there a way to get the name/machine/ip or something regarding who opens a file and when they open it? If so, I would like to do something like that, and either write it to something in the spreadsheet or as an audit trail in a database. If there's no way to do this, I am considering writing a small app that requires them to sign in (somet...

Bus. Card changes font when I change print copies / page. I save
Please use this space top fully ask your question. And we need details. -- JoAnn Paules MVP Microsoft [Publisher] "Grateful" <Grateful@discussions.microsoft.com> wrote in message news:61932EEC-79BB-45DF-87A2-8E5AE4BEC538@microsoft.com... > "JoAnn Paules [MVP]" wrote: > Please use this space top fully ask your question. And we need details. > I modified a design option in business cards. I created it as 1 copy / sheet. I saved it. When I try to print it as 10 / sheet, the font and font color didn't save. I went to styles and formatting...

Can't Send After Changing From/Reply-To
Greetings! I am using Outlook 2003 and Exchange server 2003 to try to send a message From public folder with the replies going to the same public folder. It utterly fails. I created a public folder under Exchange called ContactASA and gave myself "Send on behalf" priviledges. I then created a new message in Outlook, set the From field to ContactASA, and set the "Have replies sent to..." (reply-to) set to ContactASA. When I send the message to my gmail account I get the following error message: Your message did not reach some or all of the intended recipients. S...