Top 5 Most Important Reports

  • Follow


Hi,

I was wondering ( based on ALL of your experiences) if you could
share the top 5, lets say, reports that people want to see or know 
about from the Project Manager?

And I understand that different stakeholders are going to want different
things and that no one organization is the same.  However, I have to guess
that there have to be "Best Practice" methods for reporting project 
information right?  Thanks for your help.

-jp
0
Reply Utf 4/8/2010 11:16:01 PM

Earned Value Reports (includes PV, EV, AC, SPI, CPI and their variances)
Critical Path & Total Slack Analysis
Poor performing tasks based on Variance Analysis (Both cost and schedule)
risk register/Schedule Risk Assessment (Monte Carlo Simulations)


-- 
If this post was helpful, please consider rating it.

Jim Aksel, MVP

Check out my blog for more information:
http://www.msprojectblog.com



"jp" wrote:

> 
> Hi,
> 
> I was wondering ( based on ALL of your experiences) if you could
> share the top 5, lets say, reports that people want to see or know 
> about from the Project Manager?
> 
> And I understand that different stakeholders are going to want different
> things and that no one organization is the same.  However, I have to guess
> that there have to be "Best Practice" methods for reporting project 
> information right?  Thanks for your help.
> 
> -jp
0
Reply Utf 4/9/2010 4:50:01 AM


Thanks Jim for your reply,

Question: "risk register/Schedule Risk Assessment (Monte Carlo Simulations)"
Is that in MS Project 2003 or possibly in 2007?  I don't know that I've seen 
that before in MSP.

-jp

"Jim Aksel" wrote:

> Earned Value Reports (includes PV, EV, AC, SPI, CPI and their variances)
> Critical Path & Total Slack Analysis
> Poor performing tasks based on Variance Analysis (Both cost and schedule)
> risk register/Schedule Risk Assessment (Monte Carlo Simulations)
> 
> 
> -- 
> If this post was helpful, please consider rating it.
> 
> Jim Aksel, MVP
> 
> Check out my blog for more information:
> http://www.msprojectblog.com
> 
> 
> 
> "jp" wrote:
> 
> > 
> > Hi,
> > 
> > I was wondering ( based on ALL of your experiences) if you could
> > share the top 5, lets say, reports that people want to see or know 
> > about from the Project Manager?
> > 
> > And I understand that different stakeholders are going to want different
> > things and that no one organization is the same.  However, I have to guess
> > that there have to be "Best Practice" methods for reporting project 
> > information right?  Thanks for your help.
> > 
> > -jp
0
Reply Utf 4/9/2010 1:37:01 PM

Hi Jim,

Would you also know how to best get cost savings and schedule variances
out and into a nice graph created in MS Excel?  I'm working with MSP 2003.
I'm almost positive Executives like to see graphs showing them cost savings 
and schedule speed based on planned vs actuals in a graph format.  As you
can see, I also like graphs...
;-)
 
-jp

"Jim Aksel" wrote:

> Earned Value Reports (includes PV, EV, AC, SPI, CPI and their variances)
> Critical Path & Total Slack Analysis
> Poor performing tasks based on Variance Analysis (Both cost and schedule)
> risk register/Schedule Risk Assessment (Monte Carlo Simulations)
> 
> 
> -- 
> If this post was helpful, please consider rating it.
> 
> Jim Aksel, MVP
> 
> Check out my blog for more information:
> http://www.msprojectblog.com
> 
> 
> 
> "jp" wrote:
> 
> > 
> > Hi,
> > 
> > I was wondering ( based on ALL of your experiences) if you could
> > share the top 5, lets say, reports that people want to see or know 
> > about from the Project Manager?
> > 
> > And I understand that different stakeholders are going to want different
> > things and that no one organization is the same.  However, I have to guess
> > that there have to be "Best Practice" methods for reporting project 
> > information right?  Thanks for your help.
> > 
> > -jp
0
Reply Utf 4/9/2010 1:49:01 PM

jp,

Project out of the box does not have risk register or Motel Carlo 
Simulations.  Risk Register done lots of ways in different 
organisations.  Monte Carlo schedule simulations are doing with 
third-party add-in products.  IMHO, this sort of thing is nearly if not 
the most valuable aspect of making and maintaining a model of the 
project to enable building a discussable point of view about the future.


--rms

www.rmschneider.com




On 09/04/10 14:37, jp wrote:
>
> Thanks Jim for your reply,
>
> Question: "risk register/Schedule Risk Assessment (Monte Carlo Simulations)"
> Is that in MS Project 2003 or possibly in 2007?  I don't know that I've seen
> that before in MSP.
>
> -jp
>
> "Jim Aksel" wrote:
>
>> Earned Value Reports (includes PV, EV, AC, SPI, CPI and their variances)
>> Critical Path&  Total Slack Analysis
>> Poor performing tasks based on Variance Analysis (Both cost and schedule)
>> risk register/Schedule Risk Assessment (Monte Carlo Simulations)
>>
>>
>> --
>> If this post was helpful, please consider rating it.
>>
>> Jim Aksel, MVP
>>
>> Check out my blog for more information:
>> http://www.msprojectblog.com
>>
>>
>>
>> "jp" wrote:
>>
>>>
>>> Hi,
>>>
>>> I was wondering ( based on ALL of your experiences) if you could
>>> share the top 5, lets say, reports that people want to see or know
>>> about from the Project Manager?
>>>
>>> And I understand that different stakeholders are going to want different
>>> things and that no one organization is the same.  However, I have to guess
>>> that there have to be "Best Practice" methods for reporting project
>>> information right?  Thanks for your help.
>>>
>>> -jp
0
Reply Rob 4/9/2010 2:44:51 PM

oh ok.  Yes, I hadn't seen anything on my MSP 2003 that resembled
a Risk Register or a Monte Carlo Model.  Is the "IMHO" a really good
product?


"Rob Schneider" wrote:

> jp,
> 
> Project out of the box does not have risk register or Motel Carlo 
> Simulations.  Risk Register done lots of ways in different 
> organisations.  Monte Carlo schedule simulations are doing with 
> third-party add-in products.  IMHO, this sort of thing is nearly if not 
> the most valuable aspect of making and maintaining a model of the 
> project to enable building a discussable point of view about the future.
> 
> 
> --rms
> 
> www.rmschneider.com
> 
> 
> 
> 
> On 09/04/10 14:37, jp wrote:
> >
> > Thanks Jim for your reply,
> >
> > Question: "risk register/Schedule Risk Assessment (Monte Carlo Simulations)"
> > Is that in MS Project 2003 or possibly in 2007?  I don't know that I've seen
> > that before in MSP.
> >
> > -jp
> >
> > "Jim Aksel" wrote:
> >
> >> Earned Value Reports (includes PV, EV, AC, SPI, CPI and their variances)
> >> Critical Path&  Total Slack Analysis
> >> Poor performing tasks based on Variance Analysis (Both cost and schedule)
> >> risk register/Schedule Risk Assessment (Monte Carlo Simulations)
> >>
> >>
> >> --
> >> If this post was helpful, please consider rating it.
> >>
> >> Jim Aksel, MVP
> >>
> >> Check out my blog for more information:
> >> http://www.msprojectblog.com
> >>
> >>
> >>
> >> "jp" wrote:
> >>
> >>>
> >>> Hi,
> >>>
> >>> I was wondering ( based on ALL of your experiences) if you could
> >>> share the top 5, lets say, reports that people want to see or know
> >>> about from the Project Manager?
> >>>
> >>> And I understand that different stakeholders are going to want different
> >>> things and that no one organization is the same.  However, I have to guess
> >>> that there have to be "Best Practice" methods for reporting project
> >>> information right?  Thanks for your help.
> >>>
> >>> -jp
> .
> 
0
Reply Utf 4/9/2010 4:11:01 PM

It's the best product available in the world.  I'm humble.

"IMHO" is an internet abbreviation for "In My Humble Opinion"

You might also see "AFAIK" which is "As Far As I Know".


--rms

www.rmschneider.com




On 09/04/10 17:11, jp wrote:
>
> oh ok.  Yes, I hadn't seen anything on my MSP 2003 that resembled
> a Risk Register or a Monte Carlo Model.  Is the "IMHO" a really good
> product?
>
>
> "Rob Schneider" wrote:
>
>> jp,
>>
>> Project out of the box does not have risk register or Motel Carlo
>> Simulations.  Risk Register done lots of ways in different
>> organisations.  Monte Carlo schedule simulations are doing with
>> third-party add-in products.  IMHO, this sort of thing is nearly if not
>> the most valuable aspect of making and maintaining a model of the
>> project to enable building a discussable point of view about the future.
>>
>>
>> --rms
>>
>> www.rmschneider.com
>>
>>
>>
>>
>> On 09/04/10 14:37, jp wrote:
>>>
>>> Thanks Jim for your reply,
>>>
>>> Question: "risk register/Schedule Risk Assessment (Monte Carlo Simulations)"
>>> Is that in MS Project 2003 or possibly in 2007?  I don't know that I've seen
>>> that before in MSP.
>>>
>>> -jp
>>>
>>> "Jim Aksel" wrote:
>>>
>>>> Earned Value Reports (includes PV, EV, AC, SPI, CPI and their variances)
>>>> Critical Path&   Total Slack Analysis
>>>> Poor performing tasks based on Variance Analysis (Both cost and schedule)
>>>> risk register/Schedule Risk Assessment (Monte Carlo Simulations)
>>>>
>>>>
>>>> --
>>>> If this post was helpful, please consider rating it.
>>>>
>>>> Jim Aksel, MVP
>>>>
>>>> Check out my blog for more information:
>>>> http://www.msprojectblog.com
>>>>
>>>>
>>>>
>>>> "jp" wrote:
>>>>
>>>>>
>>>>> Hi,
>>>>>
>>>>> I was wondering ( based on ALL of your experiences) if you could
>>>>> share the top 5, lets say, reports that people want to see or know
>>>>> about from the Project Manager?
>>>>>
>>>>> And I understand that different stakeholders are going to want different
>>>>> things and that no one organization is the same.  However, I have to guess
>>>>> that there have to be "Best Practice" methods for reporting project
>>>>> information right?  Thanks for your help.
>>>>>
>>>>> -jp
>> .
>>
0
Reply Rob 4/9/2010 4:52:36 PM

The answer depends on how you're using the plan. If you have a fully 
resourced plan with accurate actual and remaining work, and an accurate 
basline then I'd say:
1. earned value or some derivative thereof that gives a clear measure of 
progress and estimate at complete
2. Report that shows problem activities, tasks, milestones, etc. such as 
tasks with variances 
3. Resource utlization

But if you're managing the plan according to tasks and dates, and not work 
hours then your options are more limited.

"jp" wrote:

> 
> Hi,
> 
> I was wondering ( based on ALL of your experiences) if you could
> share the top 5, lets say, reports that people want to see or know 
> about from the Project Manager?
> 
> And I understand that different stakeholders are going to want different
> things and that no one organization is the same.  However, I have to guess
> that there have to be "Best Practice" methods for reporting project 
> information right?  Thanks for your help.
> 
> -jp
0
Reply Utf 4/9/2010 8:06:04 PM

Wow, you really like hah!
So, where is it found on the Web?
Is it mainly used for the Monte Carlo analysis?

-jp

"Rob Schneider" wrote:

> It's the best product available in the world.  I'm humble.
> 
> "IMHO" is an internet abbreviation for "In My Humble Opinion"
> 
> You might also see "AFAIK" which is "As Far As I Know".
> 
> 
> --rms
> 
> www.rmschneider.com
> 
> 
> 
> 
> On 09/04/10 17:11, jp wrote:
> >
> > oh ok.  Yes, I hadn't seen anything on my MSP 2003 that resembled
> > a Risk Register or a Monte Carlo Model.  Is the "IMHO" a really good
> > product?
> >
> >
> > "Rob Schneider" wrote:
> >
> >> jp,
> >>
> >> Project out of the box does not have risk register or Motel Carlo
> >> Simulations.  Risk Register done lots of ways in different
> >> organisations.  Monte Carlo schedule simulations are doing with
> >> third-party add-in products.  IMHO, this sort of thing is nearly if not
> >> the most valuable aspect of making and maintaining a model of the
> >> project to enable building a discussable point of view about the future.
> >>
> >>
> >> --rms
> >>
> >> www.rmschneider.com
> >>
> >>
> >>
> >>
> >> On 09/04/10 14:37, jp wrote:
> >>>
> >>> Thanks Jim for your reply,
> >>>
> >>> Question: "risk register/Schedule Risk Assessment (Monte Carlo Simulations)"
> >>> Is that in MS Project 2003 or possibly in 2007?  I don't know that I've seen
> >>> that before in MSP.
> >>>
> >>> -jp
> >>>
> >>> "Jim Aksel" wrote:
> >>>
> >>>> Earned Value Reports (includes PV, EV, AC, SPI, CPI and their variances)
> >>>> Critical Path&   Total Slack Analysis
> >>>> Poor performing tasks based on Variance Analysis (Both cost and schedule)
> >>>> risk register/Schedule Risk Assessment (Monte Carlo Simulations)
> >>>>
> >>>>
> >>>> --
> >>>> If this post was helpful, please consider rating it.
> >>>>
> >>>> Jim Aksel, MVP
> >>>>
> >>>> Check out my blog for more information:
> >>>> http://www.msprojectblog.com
> >>>>
> >>>>
> >>>>
> >>>> "jp" wrote:
> >>>>
> >>>>>
> >>>>> Hi,
> >>>>>
> >>>>> I was wondering ( based on ALL of your experiences) if you could
> >>>>> share the top 5, lets say, reports that people want to see or know
> >>>>> about from the Project Manager?
> >>>>>
> >>>>> And I understand that different stakeholders are going to want different
> >>>>> things and that no one organization is the same.  However, I have to guess
> >>>>> that there have to be "Best Practice" methods for reporting project
> >>>>> information right?  Thanks for your help.
> >>>>>
> >>>>> -jp
> >> .
> >>
> .
> 
0
Reply Utf 4/9/2010 9:55:01 PM

oh ok.  Thanks lbethel

-jp
;-)

"lbethel" wrote:

> The answer depends on how you're using the plan. If you have a fully 
> resourced plan with accurate actual and remaining work, and an accurate 
> basline then I'd say:
> 1. earned value or some derivative thereof that gives a clear measure of 
> progress and estimate at complete
> 2. Report that shows problem activities, tasks, milestones, etc. such as 
> tasks with variances 
> 3. Resource utlization
> 
> But if you're managing the plan according to tasks and dates, and not work 
> hours then your options are more limited.
> 
> "jp" wrote:
> 
> > 
> > Hi,
> > 
> > I was wondering ( based on ALL of your experiences) if you could
> > share the top 5, lets say, reports that people want to see or know 
> > about from the Project Manager?
> > 
> > And I understand that different stakeholders are going to want different
> > things and that no one organization is the same.  However, I have to guess
> > that there have to be "Best Practice" methods for reporting project 
> > information right?  Thanks for your help.
> > 
> > -jp
0
Reply Utf 4/9/2010 9:56:01 PM

See http://project.mvps.org/comprods.htm

Also can search Google on "project monte carlo" to get some leads.


--rms

www.rmschneider.com




On 09/04/10 22:55, jp wrote:
>
> Wow, you really like hah!
> So, where is it found on the Web?
> Is it mainly used for the Monte Carlo analysis?
>
> -jp
>
> "Rob Schneider" wrote:
>
>> It's the best product available in the world.  I'm humble.
>>
>> "IMHO" is an internet abbreviation for "In My Humble Opinion"
>>
>> You might also see "AFAIK" which is "As Far As I Know".
>>
>>
>> --rms
>>
>> www.rmschneider.com
>>
>>
>>
>>
>> On 09/04/10 17:11, jp wrote:
>>>
>>> oh ok.  Yes, I hadn't seen anything on my MSP 2003 that resembled
>>> a Risk Register or a Monte Carlo Model.  Is the "IMHO" a really good
>>> product?
>>>
>>>
>>> "Rob Schneider" wrote:
>>>
>>>> jp,
>>>>
>>>> Project out of the box does not have risk register or Motel Carlo
>>>> Simulations.  Risk Register done lots of ways in different
>>>> organisations.  Monte Carlo schedule simulations are doing with
>>>> third-party add-in products.  IMHO, this sort of thing is nearly if not
>>>> the most valuable aspect of making and maintaining a model of the
>>>> project to enable building a discussable point of view about the future.
>>>>
>>>>
>>>> --rms
>>>>
>>>> www.rmschneider.com
>>>>
>>>>
>>>>
>>>>
>>>> On 09/04/10 14:37, jp wrote:
>>>>>
>>>>> Thanks Jim for your reply,
>>>>>
>>>>> Question: "risk register/Schedule Risk Assessment (Monte Carlo Simulations)"
>>>>> Is that in MS Project 2003 or possibly in 2007?  I don't know that I've seen
>>>>> that before in MSP.
>>>>>
>>>>> -jp
>>>>>
>>>>> "Jim Aksel" wrote:
>>>>>
>>>>>> Earned Value Reports (includes PV, EV, AC, SPI, CPI and their variances)
>>>>>> Critical Path&    Total Slack Analysis
>>>>>> Poor performing tasks based on Variance Analysis (Both cost and schedule)
>>>>>> risk register/Schedule Risk Assessment (Monte Carlo Simulations)
>>>>>>
>>>>>>
>>>>>> --
>>>>>> If this post was helpful, please consider rating it.
>>>>>>
>>>>>> Jim Aksel, MVP
>>>>>>
>>>>>> Check out my blog for more information:
>>>>>> http://www.msprojectblog.com
>>>>>>
>>>>>>
>>>>>>
>>>>>> "jp" wrote:
>>>>>>
>>>>>>>
>>>>>>> Hi,
>>>>>>>
>>>>>>> I was wondering ( based on ALL of your experiences) if you could
>>>>>>> share the top 5, lets say, reports that people want to see or know
>>>>>>> about from the Project Manager?
>>>>>>>
>>>>>>> And I understand that different stakeholders are going to want different
>>>>>>> things and that no one organization is the same.  However, I have to guess
>>>>>>> that there have to be "Best Practice" methods for reporting project
>>>>>>> information right?  Thanks for your help.
>>>>>>>
>>>>>>> -jp
>>>> .
>>>>
>> .
>>
0
Reply Rob 4/10/2010 5:39:25 AM

Use the Export to Excel on the Analysis toolbar.  Make sure you select the 
variance items.
-- 
If this post was helpful, please consider rating it.

Jim Aksel, MVP

Check out my blog for more information:
http://www.msprojectblog.com



"jp" wrote:

> 
> Hi Jim,
> 
> Would you also know how to best get cost savings and schedule variances
> out and into a nice graph created in MS Excel?  I'm working with MSP 2003.
> I'm almost positive Executives like to see graphs showing them cost savings 
> and schedule speed based on planned vs actuals in a graph format.  As you
> can see, I also like graphs...
> ;-)
>  
> -jp
> 
> "Jim Aksel" wrote:
> 
> > Earned Value Reports (includes PV, EV, AC, SPI, CPI and their variances)
> > Critical Path & Total Slack Analysis
> > Poor performing tasks based on Variance Analysis (Both cost and schedule)
> > risk register/Schedule Risk Assessment (Monte Carlo Simulations)
> > 
> > 
> > -- 
> > If this post was helpful, please consider rating it.
> > 
> > Jim Aksel, MVP
> > 
> > Check out my blog for more information:
> > http://www.msprojectblog.com
> > 
> > 
> > 
> > "jp" wrote:
> > 
> > > 
> > > Hi,
> > > 
> > > I was wondering ( based on ALL of your experiences) if you could
> > > share the top 5, lets say, reports that people want to see or know 
> > > about from the Project Manager?
> > > 
> > > And I understand that different stakeholders are going to want different
> > > things and that no one organization is the same.  However, I have to guess
> > > that there have to be "Best Practice" methods for reporting project 
> > > information right?  Thanks for your help.
> > > 
> > > -jp
0
Reply Utf 4/10/2010 9:04:01 PM

There are a couple out there ... I presonally use Deltek Risk Plus 
(http://www.deltek.com/products/riskplus/)

There is another called RiskyProject that is pretty good, and the ones Rob 
referred you to on the MVP site.
-- 
If this post was helpful, please consider rating it.

Jim Aksel, MVP

Check out my blog for more information:
http://www.msprojectblog.com



"jp" wrote:

> 
> Wow, you really like hah!
> So, where is it found on the Web?
> Is it mainly used for the Monte Carlo analysis?
> 
> -jp
> 
> "Rob Schneider" wrote:
> 
> > It's the best product available in the world.  I'm humble.
> > 
> > "IMHO" is an internet abbreviation for "In My Humble Opinion"
> > 
> > You might also see "AFAIK" which is "As Far As I Know".
> > 
> > 
> > --rms
> > 
> > www.rmschneider.com
> > 
> > 
> > 
> > 
> > On 09/04/10 17:11, jp wrote:
> > >
> > > oh ok.  Yes, I hadn't seen anything on my MSP 2003 that resembled
> > > a Risk Register or a Monte Carlo Model.  Is the "IMHO" a really good
> > > product?
> > >
> > >
> > > "Rob Schneider" wrote:
> > >
> > >> jp,
> > >>
> > >> Project out of the box does not have risk register or Motel Carlo
> > >> Simulations.  Risk Register done lots of ways in different
> > >> organisations.  Monte Carlo schedule simulations are doing with
> > >> third-party add-in products.  IMHO, this sort of thing is nearly if not
> > >> the most valuable aspect of making and maintaining a model of the
> > >> project to enable building a discussable point of view about the future.
> > >>
> > >>
> > >> --rms
> > >>
> > >> www.rmschneider.com
> > >>
> > >>
> > >>
> > >>
> > >> On 09/04/10 14:37, jp wrote:
> > >>>
> > >>> Thanks Jim for your reply,
> > >>>
> > >>> Question: "risk register/Schedule Risk Assessment (Monte Carlo Simulations)"
> > >>> Is that in MS Project 2003 or possibly in 2007?  I don't know that I've seen
> > >>> that before in MSP.
> > >>>
> > >>> -jp
> > >>>
> > >>> "Jim Aksel" wrote:
> > >>>
> > >>>> Earned Value Reports (includes PV, EV, AC, SPI, CPI and their variances)
> > >>>> Critical Path&   Total Slack Analysis
> > >>>> Poor performing tasks based on Variance Analysis (Both cost and schedule)
> > >>>> risk register/Schedule Risk Assessment (Monte Carlo Simulations)
> > >>>>
> > >>>>
> > >>>> --
> > >>>> If this post was helpful, please consider rating it.
> > >>>>
> > >>>> Jim Aksel, MVP
> > >>>>
> > >>>> Check out my blog for more information:
> > >>>> http://www.msprojectblog.com
> > >>>>
> > >>>>
> > >>>>
> > >>>> "jp" wrote:
> > >>>>
> > >>>>>
> > >>>>> Hi,
> > >>>>>
> > >>>>> I was wondering ( based on ALL of your experiences) if you could
> > >>>>> share the top 5, lets say, reports that people want to see or know
> > >>>>> about from the Project Manager?
> > >>>>>
> > >>>>> And I understand that different stakeholders are going to want different
> > >>>>> things and that no one organization is the same.  However, I have to guess
> > >>>>> that there have to be "Best Practice" methods for reporting project
> > >>>>> information right?  Thanks for your help.
> > >>>>>
> > >>>>> -jp
> > >> .
> > >>
> > .
> > 
0
Reply Utf 4/10/2010 9:06:01 PM

Do you know the URL for IMHO?
Does it cost alot of money?
Is it really good and useful?

-jp

"Rob Schneider" wrote:

> jp,
> 
> Project out of the box does not have risk register or Motel Carlo 
> Simulations.  Risk Register done lots of ways in different 
> organisations.  Monte Carlo schedule simulations are doing with 
> third-party add-in products.  IMHO, this sort of thing is nearly if not 
> the most valuable aspect of making and maintaining a model of the 
> project to enable building a discussable point of view about the future.
> 
> 
> --rms
> 
> www.rmschneider.com
> 
> 
> 
> 
> On 09/04/10 14:37, jp wrote:
> >
> > Thanks Jim for your reply,
> >
> > Question: "risk register/Schedule Risk Assessment (Monte Carlo Simulations)"
> > Is that in MS Project 2003 or possibly in 2007?  I don't know that I've seen
> > that before in MSP.
> >
> > -jp
> >
> > "Jim Aksel" wrote:
> >
> >> Earned Value Reports (includes PV, EV, AC, SPI, CPI and their variances)
> >> Critical Path&  Total Slack Analysis
> >> Poor performing tasks based on Variance Analysis (Both cost and schedule)
> >> risk register/Schedule Risk Assessment (Monte Carlo Simulations)
> >>
> >>
> >> --
> >> If this post was helpful, please consider rating it.
> >>
> >> Jim Aksel, MVP
> >>
> >> Check out my blog for more information:
> >> http://www.msprojectblog.com
> >>
> >>
> >>
> >> "jp" wrote:
> >>
> >>>
> >>> Hi,
> >>>
> >>> I was wondering ( based on ALL of your experiences) if you could
> >>> share the top 5, lets say, reports that people want to see or know
> >>> about from the Project Manager?
> >>>
> >>> And I understand that different stakeholders are going to want different
> >>> things and that no one organization is the same.  However, I have to guess
> >>> that there have to be "Best Practice" methods for reporting project
> >>> information right?  Thanks for your help.
> >>>
> >>> -jp
> .
> 
0
Reply Utf 4/13/2010 4:36:01 PM

13 Replies
423 Views

(page loaded in 1.558 seconds)


Reply: