Task w/ Multiple Resource - schedule around availability

  • Follow


I have a task that requires two resources to work concurrently.  It is a
series of presentations that need to occur within a single span of five
days.  Both resources must be available to attend each and every
presentation within that 5 day period.  

There is work that must be complete prior to presentations, therefore
this task has a predecessor.  It so happens that one of the resources
that must perform the task is away on vacation when the predecessor
finishes.  Even though the vacation is entered as an exception in the
calendar of the resource, MS Project still schedules the presentation
task to start right after the predecessor completes, when only one of
the resources is available.

What do I need to do to have the task scheduled asap, but only when both
resources are available?


-- 
KevDev
------------------------------------------------------------------------
KevDev's Profile: http://forums.techarena.in/members/227661.htm
View this thread: http://forums.techarena.in/microsoft-project/1343030.htm

http://forums.techarena.in

0
Reply KevDev 6/2/2010 3:08:34 PM

Hi,

This is explained in detail in an article I wrote about it on my website
http://users.online.be/prom-ade
and click through to Microsoft Project: an abstract

In short, DO NOT enter the absence as a holiday but as a task (with a mucst 
start on constraint). Then do Resource Leveling because leveling has an 
option to keep the reosurces working simultaneously.

HTH

-- 
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
"KevDev" <KevDev.4bxrpb@DoNotSpam.com> wrote in message 
news:KevDev.4bxrpb@DoNotSpam.com...
>
> I have a task that requires two resources to work concurrently.  It is a
> series of presentations that need to occur within a single span of five
> days.  Both resources must be available to attend each and every
> presentation within that 5 day period.
>
> There is work that must be complete prior to presentations, therefore
> this task has a predecessor.  It so happens that one of the resources
> that must perform the task is away on vacation when the predecessor
> finishes.  Even though the vacation is entered as an exception in the
> calendar of the resource, MS Project still schedules the presentation
> task to start right after the predecessor completes, when only one of
> the resources is available.
>
> What do I need to do to have the task scheduled asap, but only when both
> resources are available?
>
>
> -- 
> KevDev
> ------------------------------------------------------------------------
> KevDev's Profile: http://forums.techarena.in/members/227661.htm
> View this thread: http://forums.techarena.in/microsoft-project/1343030.htm
>
> http://forums.techarena.in
> 


0
Reply Jan 6/2/2010 6:54:46 PM


Jan:

Thank you.  Your solution not only worked for me, it is ingenious.  

The task that needs both resources is now scheduled at a time when both
resources are available.  As an added bonus, the non-working time
appears in any task based reports.  Therefore, it will become part of
our periodic review of the plan, and will be better maintained.

Thanks so much,
Kevin


-- 
KevDev
------------------------------------------------------------------------
KevDev's Profile: http://forums.techarena.in/members/227661.htm
View this thread: http://forums.techarena.in/microsoft-project/1343030.htm

http://forums.techarena.in

0
Reply KevDev 6/3/2010 1:09:06 PM

Thanks, Kevin.

-- 
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
"KevDev" <KevDev.4bzgtb@DoNotSpam.com> wrote in message 
news:KevDev.4bzgtb@DoNotSpam.com...
>
> Jan:
>
> Thank you.  Your solution not only worked for me, it is ingenious.
>
> The task that needs both resources is now scheduled at a time when both
> resources are available.  As an added bonus, the non-working time
> appears in any task based reports.  Therefore, it will become part of
> our periodic review of the plan, and will be better maintained.
>
> Thanks so much,
> Kevin
>
>
> -- 
> KevDev
> ------------------------------------------------------------------------
> KevDev's Profile: http://forums.techarena.in/members/227661.htm
> View this thread: http://forums.techarena.in/microsoft-project/1343030.htm
>
> http://forums.techarena.in
> 


0
Reply Jan 6/3/2010 2:38:52 PM

Careful though - the man-hours your resource is spending on the holiday is 
now included in the project's total man-hours even though it not really work 
performed in driving the project's deliverables and similarly, the 
resource's salary costs for those man-hours is included in the total budget. 
Jan and I would have to disagree on desirablility of this method since IMHO 
it artificially inflates both the work and budget for the project, adding 
both work hours and costs attributed of that work into them when neither 
actually exist. It's a handy way of adjusting a schedule but it severely 
distorts everything else except the timeline. I tend to believe that tasks 
in the project schedule should be strictly limited to physical activities 
spent working on project deliverables.  Time off such as holidays, 
vacations, and days off, and time spent waiting for something to happen such 
as the reciept of an approval, etc, are by definition non-activity or 
non-productive activity.  IMHO such factors should never be represented as 
tasks since to do so implies something productive is happening in them when 
in fact it's not.
-- 
Steve House
MS Project Trainer & Consultant



"KevDev" <KevDev.4bzgtb@DoNotSpam.com> wrote in message 
news:KevDev.4bzgtb@DoNotSpam.com...
>
> Jan:
>
> Thank you.  Your solution not only worked for me, it is ingenious.
>
> The task that needs both resources is now scheduled at a time when both
> resources are available.  As an added bonus, the non-working time
> appears in any task based reports.  Therefore, it will become part of
> our periodic review of the plan, and will be better maintained.
>
> Thanks so much,
> Kevin
>
>
> -- 
> KevDev
> ------------------------------------------------------------------------
> KevDev's Profile: http://forums.techarena.in/members/227661.htm
> View this thread: http://forums.techarena.in/microsoft-project/1343030.htm
>
> http://forums.techarena.in
> 

0
Reply Steve 6/6/2010 1:23:58 PM

4 Replies
695 Views

(page loaded in 0.059 seconds)


Reply: