Setting week numbers

  • Follow


I would like to set week numbers on a programme from a specific date of my 
choosing rather than project start or end or from fiscal or calendar year 
dates.  Is this possible
-- 
GDD
0
Reply Utf 6/4/2010 7:30:15 AM

As far as I know, there is no way to change how the week numbers are 
computed. However, what you could do is implement your own algorithm for 
computing week number based on date using one of the custom number fields.


--rms

www.rmschneider.com




On 04/06/10 08:30, Gary D wrote:
> I would like to set week numbers on a programme from a specific date of my
> choosing rather than project start or end or from fiscal or calendar year
> dates.  Is this possible
0
Reply Rob 6/4/2010 10:56:03 AM


Hi,

Block the start date of the starting task(s) then set Project Start (in 
Project menu, Project information) to the start of your week counting

-- 
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
"Gary D" <GaryD@discussions.microsoft.com> wrote in message 
news:306705D6-1519-475D-94E0-D57463D21DC3@microsoft.com...
>I would like to set week numbers on a programme from a specific date of my
> choosing rather than project start or end or from fiscal or calendar year
> dates.  Is this possible
> -- 
> GDD 


0
Reply Jan 6/4/2010 11:02:52 AM