send tasks to outlook

  • Follow


I need to send reminders of tasks to my resource people.
I heard it is possible to send tasks to outlook. How can I do it?

Txs

Silene 
0
Reply Silene 5/10/2010 1:21:14 PM

Hi,

this option is still available in Microsoft Project 2002, 2003, 2007 and 
2010 -
how ever hidden. To show this feature, please perfom
the following steps for Project previous to 2010:

1. Go to "Tools/Customize/Toolbars"
2. Switch to tab "Commands"
3. Select "All Commands"
4. Scroll to "ReminderSet"
5. Drop the toolbar button on a toolbar of your choice
6. Click "Close"

For Microsoft Project 2010 take these steps:
1. Go to "File/Options/Quick Access Toolbar"
2. Under "Choose commands from" select "All Commands"
3. Scroll to "Set Reminder" and
4. Click "Add"
5. Click "OK"

Now you can add a reminder in your local Outlook as task with reminder for
selected Project tasks from you local MS Project.

Best,
Renke

Linking Outlook and Notes with Project Server
http://www.allocatus.com

Project MVP Germany
http://www.holert.com

-- 
Renke Holert

Project MVP Germany
http://www.holert.com

"Silene" <sileneev@hotmail.com> wrote in message 
news:32CD2E3E-322B-408B-8669-DFCFEAC9DE6F@microsoft.com...
> I need to send reminders of tasks to my resource people.
> I heard it is possible to send tasks to outlook. How can I do it?
>
> Txs
>
> Silene 

2
Reply Renke 5/10/2010 4:24:19 PM


Hi Silene,

I'd like to add that with versions newer than Project 98 it's not possible 
to send these tasks directly to your resources out-of-the-box, how ever with 
Project Server that's possible. Depending on the version you can use the 
Outlook Add-in or the Exchange Server Integration. What's exact the scenario 
you prefer?

Best,
Renke

Project MVP Germany
http://www.holert.com

"Renke Holert" <news@holert.com> wrote in message
news:A9733C63-0E39-4A9E-BA37-B844D66B3BFE@microsoft.com...
> Hi,
>
> this option is still available in Microsoft Project 2002, 2003, 2007 and
> 2010 -
> how ever hidden. To show this feature, please perfom
> the following steps for Project previous to 2010:
>
> 1. Go to "Tools/Customize/Toolbars"
> 2. Switch to tab "Commands"
> 3. Select "All Commands"
> 4. Scroll to "ReminderSet"
> 5. Drop the toolbar button on a toolbar of your choice
> 6. Click "Close"
>
> For Microsoft Project 2010 take these steps:
> 1. Go to "File/Options/Quick Access Toolbar"
> 2. Under "Choose commands from" select "All Commands"
> 3. Scroll to "Set Reminder" and
> 4. Click "Add"
> 5. Click "OK"
>
> Now you can add a reminder in your local Outlook as task with reminder for
> selected Project tasks from you local MS Project.
>
> Best,
> Renke
>
> Linking Outlook and Notes with Project Server
> http://www.allocatus.com
>
> Project MVP Germany
> http://www.holert.com
>
> -- 
> Renke Holert
>
> Project MVP Germany
> http://www.holert.com
>
> "Silene" <sileneev@hotmail.com> wrote in message
> news:32CD2E3E-322B-408B-8669-DFCFEAC9DE6F@microsoft.com...
>> I need to send reminders of tasks to my resource people.
>> I heard it is possible to send tasks to outlook. How can I do it?
>>
>> Txs
>>
>> Silene
> 
0
Reply Renke 5/10/2010 4:45:43 PM

On another note, every implementation I've been involved with that had email 
reminders, turned them off within a short period of time as the emails were 
treated as spam. Once you get more then one or two emails on a topic 
regularly, users tend to create rules to dump them to the delete folder or 
complain. So don't spend too much time or money on your solution!

-- 

Rod Gill
Microsoft MVP for Project - http://www.project-systems.co.nz

Author of the only book on Project VBA, see: http://www.projectvbabook.com




"Renke Holert" <news@holert.com> wrote in message 
news:3B385C2D-7357-48F0-AE03-B824404D5E90@microsoft.com...
> Hi Silene,
>
> I'd like to add that with versions newer than Project 98 it's not possible 
> to send these tasks directly to your resources out-of-the-box, how ever 
> with Project Server that's possible. Depending on the version you can use 
> the Outlook Add-in or the Exchange Server Integration. What's exact the 
> scenario you prefer?
>
> Best,
> Renke
>
> Project MVP Germany
> http://www.holert.com
>
> "Renke Holert" <news@holert.com> wrote in message
> news:A9733C63-0E39-4A9E-BA37-B844D66B3BFE@microsoft.com...
>> Hi,
>>
>> this option is still available in Microsoft Project 2002, 2003, 2007 and
>> 2010 -
>> how ever hidden. To show this feature, please perfom
>> the following steps for Project previous to 2010:
>>
>> 1. Go to "Tools/Customize/Toolbars"
>> 2. Switch to tab "Commands"
>> 3. Select "All Commands"
>> 4. Scroll to "ReminderSet"
>> 5. Drop the toolbar button on a toolbar of your choice
>> 6. Click "Close"
>>
>> For Microsoft Project 2010 take these steps:
>> 1. Go to "File/Options/Quick Access Toolbar"
>> 2. Under "Choose commands from" select "All Commands"
>> 3. Scroll to "Set Reminder" and
>> 4. Click "Add"
>> 5. Click "OK"
>>
>> Now you can add a reminder in your local Outlook as task with reminder 
>> for
>> selected Project tasks from you local MS Project.
>>
>> Best,
>> Renke
>>
>> Linking Outlook and Notes with Project Server
>> http://www.allocatus.com
>>
>> Project MVP Germany
>> http://www.holert.com
>>
>> -- 
>> Renke Holert
>>
>> Project MVP Germany
>> http://www.holert.com
>>
>> "Silene" <sileneev@hotmail.com> wrote in message
>> news:32CD2E3E-322B-408B-8669-DFCFEAC9DE6F@microsoft.com...
>>> I need to send reminders of tasks to my resource people.
>>> I heard it is possible to send tasks to outlook. How can I do it?
>>>
>>> Txs
>>>
>>> Silene
>>
>
> __________ Information from ESET Smart Security, version of virus 
> signature database 5103 (20100510) __________
>
> The message was checked by ESET Smart Security.
>
> http://www.eset.com
>
>
> 

__________ Information from ESET Smart Security, version of virus signature database 5103 (20100510) __________

The message was checked by ESET Smart Security.

http://www.eset.com



0
Reply Rod 5/10/2010 8:24:16 PM

I brought the reminder icon into MS project but I still don't know how to 
send tasks from MS 2007 to the Outlook 2007.
I don't have Project Server and I don't know how to use the Outlook Add-in.

Txs,
Silene

"Renke Holert" <news@holert.com> wrote in message 
news:3B385C2D-7357-48F0-AE03-B824404D5E90@microsoft.com...
> Hi Silene,
>
> I'd like to add that with versions newer than Project 98 it's not possible 
> to send these tasks directly to your resources out-of-the-box, how ever 
> with Project Server that's possible. Depending on the version you can use 
> the Outlook Add-in or the Exchange Server Integration. What's exact the 
> scenario you prefer?
>
> Best,
> Renke
>
> Project MVP Germany
> http://www.holert.com
>
> "Renke Holert" <news@holert.com> wrote in message
> news:A9733C63-0E39-4A9E-BA37-B844D66B3BFE@microsoft.com...
>> Hi,
>>
>> this option is still available in Microsoft Project 2002, 2003, 2007 and
>> 2010 -
>> how ever hidden. To show this feature, please perfom
>> the following steps for Project previous to 2010:
>>
>> 1. Go to "Tools/Customize/Toolbars"
>> 2. Switch to tab "Commands"
>> 3. Select "All Commands"
>> 4. Scroll to "ReminderSet"
>> 5. Drop the toolbar button on a toolbar of your choice
>> 6. Click "Close"
>>
>> For Microsoft Project 2010 take these steps:
>> 1. Go to "File/Options/Quick Access Toolbar"
>> 2. Under "Choose commands from" select "All Commands"
>> 3. Scroll to "Set Reminder" and
>> 4. Click "Add"
>> 5. Click "OK"
>>
>> Now you can add a reminder in your local Outlook as task with reminder 
>> for
>> selected Project tasks from you local MS Project.
>>
>> Best,
>> Renke
>>
>> Linking Outlook and Notes with Project Server
>> http://www.allocatus.com
>>
>> Project MVP Germany
>> http://www.holert.com
>>
>> -- 
>> Renke Holert
>>
>> Project MVP Germany
>> http://www.holert.com
>>
>> "Silene" <sileneev@hotmail.com> wrote in message
>> news:32CD2E3E-322B-408B-8669-DFCFEAC9DE6F@microsoft.com...
>>> I need to send reminders of tasks to my resource people.
>>> I heard it is possible to send tasks to outlook. How can I do it?
>>>
>>> Txs
>>>
>>> Silene
>> 
0
Reply Silene 5/12/2010 7:44:19 AM

Silene,

My experience is as with Rod. A noticeable number of people often ask 
for such functionality; then when provided it they abandon.  It's been 
years since I've had to deal with this.

Via Google "project tasks to outlook" I found for you 
http://office.microsoft.com/en-us/project/HA010842281033.aspx

This document refers to Project 2003 which my recollection is the last 
version of Project for which this was provided.

Project is best a tool to compute project schedule/costs and provide a 
framework for project governance and reporting.  It's not designed for 
task management and attempts to make it be are usually not successful.


--rms

www.rmschneider.com




On 12/05/10 08:44, Silene wrote:
> I brought the reminder icon into MS project but I still don't know how
> to send tasks from MS 2007 to the Outlook 2007.
> I don't have Project Server and I don't know how to use the Outlook Add-in.
>
> Txs,
> Silene
>
> "Renke Holert" <news@holert.com> wrote in message
> news:3B385C2D-7357-48F0-AE03-B824404D5E90@microsoft.com...
>> Hi Silene,
>>
>> I'd like to add that with versions newer than Project 98 it's not
>> possible to send these tasks directly to your resources
>> out-of-the-box, how ever with Project Server that's possible.
>> Depending on the version you can use the Outlook Add-in or the
>> Exchange Server Integration. What's exact the scenario you prefer?
>>
>> Best,
>> Renke
>>
>> Project MVP Germany
>> http://www.holert.com
>>
>> "Renke Holert" <news@holert.com> wrote in message
>> news:A9733C63-0E39-4A9E-BA37-B844D66B3BFE@microsoft.com...
>>> Hi,
>>>
>>> this option is still available in Microsoft Project 2002, 2003, 2007 and
>>> 2010 -
>>> how ever hidden. To show this feature, please perfom
>>> the following steps for Project previous to 2010:
>>>
>>> 1. Go to "Tools/Customize/Toolbars"
>>> 2. Switch to tab "Commands"
>>> 3. Select "All Commands"
>>> 4. Scroll to "ReminderSet"
>>> 5. Drop the toolbar button on a toolbar of your choice
>>> 6. Click "Close"
>>>
>>> For Microsoft Project 2010 take these steps:
>>> 1. Go to "File/Options/Quick Access Toolbar"
>>> 2. Under "Choose commands from" select "All Commands"
>>> 3. Scroll to "Set Reminder" and
>>> 4. Click "Add"
>>> 5. Click "OK"
>>>
>>> Now you can add a reminder in your local Outlook as task with
>>> reminder for
>>> selected Project tasks from you local MS Project.
>>>
>>> Best,
>>> Renke
>>>
>>> Linking Outlook and Notes with Project Server
>>> http://www.allocatus.com
>>>
>>> Project MVP Germany
>>> http://www.holert.com
>>>
>>> --
>>> Renke Holert
>>>
>>> Project MVP Germany
>>> http://www.holert.com
>>>
>>> "Silene" <sileneev@hotmail.com> wrote in message
>>> news:32CD2E3E-322B-408B-8669-DFCFEAC9DE6F@microsoft.com...
>>>> I need to send reminders of tasks to my resource people.
>>>> I heard it is possible to send tasks to outlook. How can I do it?
>>>>
>>>> Txs
>>>>
>>>> Silene
>>>
0
Reply Rob 5/12/2010 7:58:45 AM

On second glance, this URL seems to refer to Project Server, which you 
say you don't have.  I guess just read carefully and experiment to see 
if it can work without Server.


--rms

www.rmschneider.com




On 12/05/10 08:58, Rob Schneider wrote:
> Silene,
>
> My experience is as with Rod. A noticeable number of people often ask
> for such functionality; then when provided it they abandon. It's been
> years since I've had to deal with this.
>
> Via Google "project tasks to outlook" I found for you
> http://office.microsoft.com/en-us/project/HA010842281033.aspx
>
> This document refers to Project 2003 which my recollection is the last
> version of Project for which this was provided.
>
> Project is best a tool to compute project schedule/costs and provide a
> framework for project governance and reporting. It's not designed for
> task management and attempts to make it be are usually not successful.
>
>
> --rms
>
> www.rmschneider.com
>
>
>
>
> On 12/05/10 08:44, Silene wrote:
>> I brought the reminder icon into MS project but I still don't know how
>> to send tasks from MS 2007 to the Outlook 2007.
>> I don't have Project Server and I don't know how to use the Outlook
>> Add-in.
>>
>> Txs,
>> Silene
>>
>> "Renke Holert" <news@holert.com> wrote in message
>> news:3B385C2D-7357-48F0-AE03-B824404D5E90@microsoft.com...
>>> Hi Silene,
>>>
>>> I'd like to add that with versions newer than Project 98 it's not
>>> possible to send these tasks directly to your resources
>>> out-of-the-box, how ever with Project Server that's possible.
>>> Depending on the version you can use the Outlook Add-in or the
>>> Exchange Server Integration. What's exact the scenario you prefer?
>>>
>>> Best,
>>> Renke
>>>
>>> Project MVP Germany
>>> http://www.holert.com
>>>
>>> "Renke Holert" <news@holert.com> wrote in message
>>> news:A9733C63-0E39-4A9E-BA37-B844D66B3BFE@microsoft.com...
>>>> Hi,
>>>>
>>>> this option is still available in Microsoft Project 2002, 2003, 2007
>>>> and
>>>> 2010 -
>>>> how ever hidden. To show this feature, please perfom
>>>> the following steps for Project previous to 2010:
>>>>
>>>> 1. Go to "Tools/Customize/Toolbars"
>>>> 2. Switch to tab "Commands"
>>>> 3. Select "All Commands"
>>>> 4. Scroll to "ReminderSet"
>>>> 5. Drop the toolbar button on a toolbar of your choice
>>>> 6. Click "Close"
>>>>
>>>> For Microsoft Project 2010 take these steps:
>>>> 1. Go to "File/Options/Quick Access Toolbar"
>>>> 2. Under "Choose commands from" select "All Commands"
>>>> 3. Scroll to "Set Reminder" and
>>>> 4. Click "Add"
>>>> 5. Click "OK"
>>>>
>>>> Now you can add a reminder in your local Outlook as task with
>>>> reminder for
>>>> selected Project tasks from you local MS Project.
>>>>
>>>> Best,
>>>> Renke
>>>>
>>>> Linking Outlook and Notes with Project Server
>>>> http://www.allocatus.com
>>>>
>>>> Project MVP Germany
>>>> http://www.holert.com
>>>>
>>>> --
>>>> Renke Holert
>>>>
>>>> Project MVP Germany
>>>> http://www.holert.com
>>>>
>>>> "Silene" <sileneev@hotmail.com> wrote in message
>>>> news:32CD2E3E-322B-408B-8669-DFCFEAC9DE6F@microsoft.com...
>>>>> I need to send reminders of tasks to my resource people.
>>>>> I heard it is possible to send tasks to outlook. How can I do it?
>>>>>
>>>>> Txs
>>>>>
>>>>> Silene
>>>>
0
Reply Rob 5/12/2010 8:02:41 AM

Hello Silene,

To use the set reminder in Project 2007:
  - ensure the resource assigned to the task has an email 
address.  Double click the resource's name and enter an email 
address for each resource.
- select the task and click the Set Reminder button.
- Look at the task list and the "To-Do bar" to see the reminders.

I hope this helps.  Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project

On 5/12/2010 3:44 AM, Silene wrote:
> I brought the reminder icon into MS project but I still don't know how
> to send tasks from MS 2007 to the Outlook 2007.
> I don't have Project Server and I don't know how to use the Outlook Add-in.
>
> Txs,
> Silene
>
> "Renke Holert" <news@holert.com> wrote in message
> news:3B385C2D-7357-48F0-AE03-B824404D5E90@microsoft.com...
>> Hi Silene,
>>
>> I'd like to add that with versions newer than Project 98 it's not
>> possible to send these tasks directly to your resources
>> out-of-the-box, how ever with Project Server that's possible.
>> Depending on the version you can use the Outlook Add-in or the
>> Exchange Server Integration. What's exact the scenario you prefer?
>>
>> Best,
>> Renke
>>
>> Project MVP Germany
>> http://www.holert.com
>>
>> "Renke Holert" <news@holert.com> wrote in message
>> news:A9733C63-0E39-4A9E-BA37-B844D66B3BFE@microsoft.com...
>>> Hi,
>>>
>>> this option is still available in Microsoft Project 2002, 2003, 2007 and
>>> 2010 -
>>> how ever hidden. To show this feature, please perfom
>>> the following steps for Project previous to 2010:
>>>
>>> 1. Go to "Tools/Customize/Toolbars"
>>> 2. Switch to tab "Commands"
>>> 3. Select "All Commands"
>>> 4. Scroll to "ReminderSet"
>>> 5. Drop the toolbar button on a toolbar of your choice
>>> 6. Click "Close"
>>>
>>> For Microsoft Project 2010 take these steps:
>>> 1. Go to "File/Options/Quick Access Toolbar"
>>> 2. Under "Choose commands from" select "All Commands"
>>> 3. Scroll to "Set Reminder" and
>>> 4. Click "Add"
>>> 5. Click "OK"
>>>
>>> Now you can add a reminder in your local Outlook as task with
>>> reminder for
>>> selected Project tasks from you local MS Project.
>>>
>>> Best,
>>> Renke
>>>
>>> Linking Outlook and Notes with Project Server
>>> http://www.allocatus.com
>>>
>>> Project MVP Germany
>>> http://www.holert.com
>>>
>>> --
>>> Renke Holert
>>>
>>> Project MVP Germany
>>> http://www.holert.com
>>>
>>> "Silene" <sileneev@hotmail.com> wrote in message
>>> news:32CD2E3E-322B-408B-8669-DFCFEAC9DE6F@microsoft.com...
>>>> I need to send reminders of tasks to my resource people.
>>>> I heard it is possible to send tasks to outlook. How can I do it?
>>>>
>>>> Txs
>>>>
>>>> Silene
>>>
0
Reply JulieS 5/12/2010 10:13:15 AM

7 Replies
1984 Views

(page loaded in 0.373 seconds)