RE: Understanding Project's Percent Complete vs. Percent Work Complete

  • Follow


Brian Kennemer wrote the subject-line article several years ago and was very 
informative/enlightening on how % Complete is computed, etc.  However, in 
this article he showed a Microsoft Project view (Figure A) that had both 
"Work" and "Actual Work" rows in the detail lines for each resources on a 
specific task.  Where can I find this view.  I do need to enter actual hours 
worked per resource per day on their respective task

thanks,
David Hamil
MaxVision
256-652-4322
David@MaxVision.com
0
Reply Utf 11/30/2009 2:00:01 PM

Perhaps what you seek is on the resource view or task usage view.  Both are 
under the View menu item.

You can change the details on the right side of the two views. Ineither 
view, hover your mouse over the word "Work" in the details column, right 
click, and select "Detail Styles."  From there, select the desired fields on 
the left and then use the "show" button in the middle of the form to move 
them to the right pane.  Click OK and you should see what you want.

I would be interested in a link to the article you mentioned.  Also, I have 
a similar post in my blog about %Complete, etc.  See the link below.
-- 
If this post was helpful, please consider rating it.

Jim Aksel, MVP

Check out my blog for more information:
http://www.msprojectblog.com



"David L. Hamil" wrote:

> Brian Kennemer wrote the subject-line article several years ago and was very 
> informative/enlightening on how % Complete is computed, etc.  However, in 
> this article he showed a Microsoft Project view (Figure A) that had both 
> "Work" and "Actual Work" rows in the detail lines for each resources on a 
> specific task.  Where can I find this view.  I do need to enter actual hours 
> worked per resource per day on their respective task
> 
> thanks,
> David Hamil
> MaxVision
> 256-652-4322
> David@MaxVision.com