|
|
RE: Understanding Project's Percent Complete vs. Percent Work Complete
Brian Kennemer wrote the subject-line article several years ago and was very
informative/enlightening on how % Complete is computed, etc. However, in
this article he showed a Microsoft Project view (Figure A) that had both
"Work" and "Actual Work" rows in the detail lines for each resources on a
specific task. Where can I find this view. I do need to enter actual hours
worked per resource per day on their respective task
thanks,
David Hamil
MaxVision
256-652-4322
David@MaxVision.com
|
|
0
|
|
|
|
Reply
|
Utf
|
11/30/2009 2:00:01 PM |
|
Perhaps what you seek is on the resource view or task usage view. Both are
under the View menu item.
You can change the details on the right side of the two views. Ineither
view, hover your mouse over the word "Work" in the details column, right
click, and select "Detail Styles." From there, select the desired fields on
the left and then use the "show" button in the middle of the form to move
them to the right pane. Click OK and you should see what you want.
I would be interested in a link to the article you mentioned. Also, I have
a similar post in my blog about %Complete, etc. See the link below.
--
If this post was helpful, please consider rating it.
Jim Aksel, MVP
Check out my blog for more information:
http://www.msprojectblog.com
"David L. Hamil" wrote:
> Brian Kennemer wrote the subject-line article several years ago and was very
> informative/enlightening on how % Complete is computed, etc. However, in
> this article he showed a Microsoft Project view (Figure A) that had both
> "Work" and "Actual Work" rows in the detail lines for each resources on a
> specific task. Where can I find this view. I do need to enter actual hours
> worked per resource per day on their respective task
>
> thanks,
> David Hamil
> MaxVision
> 256-652-4322
> David@MaxVision.com
|
|
0
|
|
|
|
Reply
|
Utf
|
11/30/2009 2:10:01 PM
|
|
|
1 Replies
604 Views
(page loaded in 0.042 seconds)
Similiar Articles: RE: Understanding Project's Percent Complete vs. Percent Work ...Brian Kennemer wrote the subject-line article several years ago and was very informative/enlightening on how % Complete is computed, etc. However, ... Physical Percent (%) Complete (task field) - microsoft.public ...Physical Percent (%) Complete (task field) - microsoft.public ... RE: Understanding Project's Percent Complete vs. Percent Work ... ... vs Actual Percentage Completed ... % Complete in Lag time vs. Durations - microsoft.public.project ...RE: Understanding Project's Percent Complete vs. Percent Work ... % Complete in ... edit the=20 percentage ... Understanding Project's Percent Complete vs. Percent Work ... % Complete Versus Physical % Complete - microsoft.public.project ...RE: Understanding Project's Percent Complete vs. Percent Work ... Re: % complete vs %wok complete vs ... MS Project calaculates Planned or base percentage complete of work ... Ahead of Schedule task and % complete - microsoft.public.project ...RE: Understanding Project's Percent Complete vs. Percent Work ... Ahead of Schedule task ... their progress in terms of percentage complete ... RE: Understanding Project's ... Task Percentage Change - microsoft.public.project.server ...RE: Understanding Project's Percent Complete vs. Percent Work ... You can change the ... percentage that a task is complete - Project - Office.com Indicating the percentage ... Critical Path vs. Partially Complete Tasks - microsoft.public ...RE: Understanding Project's Percent Complete vs. Percent Work ... % Work Complete =3D Actual/Total > There are ... from 4 Days to 14 Days, MSP > re-calculates % Complete ... What does Microsoft Project Levels 1, 2, 3, 4, schedules mean ...RE: Understanding Project's Percent Complete vs. Percent Work ... RE: Understanding Project's Percent Complete vs. Percent Work ... What does Microsoft Project Levels 1, 2 ... base vs this - microsoft.public.dotnet.languages.csharp ...It's different, but it isn't contradictory, because you're talking about two ... Is there a way where MS Project calaculates Planned or base percentage complete of work ... Special RAG light - microsoft.public.project... look at some of the white papers I have on "Percent Complete." ... between building the formula off of [work] vs. [duration]. ... Re: Special RAG light - Tech-Archive.net: The ... Understanding Project's Percent Complete vs. Percent Work Complete ...RE: Understanding Project's Percent Complete vs. Percent Work Complete RE: Understanding Project's Percent Complete vs. Percent Work ...Brian Kennemer wrote the subject-line article several years ago and was very informative/enlightening on how % Complete is computed, etc. However, ... RE: Understanding Project's Percent Complete vs. Percent Work CompleteMicrosoft Project Forum Members, post questions in this forum if they are related to using Microsoft Project, this includes Gantt Charts, Timelines, Drawings ... Project 2007 - Understanding Project's Percent Complete vs ...Project 2007 - Understanding Project's Percent Complete vs. Percent Work Complete ... difference between the Percent Complete and Percent Work Complete functions in MS Project ... DEFINING %COMPLETE IN MICROSOFT PROJECTMicrosoft Project confirms the calculation: Figure 5 Percent Work Complete Screen ... Values of Percent Complete Method vs. Day %Complete %Work ... the painter has re ... 7/23/2012 1:58:11 PM
|
|
|
|
|
|
|
|
|