Microsoft project 2007 resources help

  • Follow


Hi all,

Three questions:
1. What the constraint A<B,C means and how can I entering in the MSP?
2. I have 3 kinds of human resources. Lets say for example, kind A are
engineers. I have 8 of them and everyone is costing 1500 Euros/month.
Task A needs 4 engineers. How can I assign them to the task and add the
appropriate cost?
3. I have 3 machines as a resource. Each machine has a usage cost of
3000 euros per task and function cost 2400 euros per month. How can I
assign them in the appropriate tasks? And how can I distribute their
cost?

Thank you in advance


-- 
loukas_t
------------------------------------------------------------------------
loukas_t's Profile: http://forums.techarena.in/members/153572.htm
View this thread: http://forums.techarena.in/microsoft-project/1274342.htm

http://forums.techarena.in

0
Reply loukas_t 11/23/2009 6:39:00 PM

Hi,

No idea what you mean by A<B,C. Please explain

In the View Resource Sheet
Enter a Resource Engineer.
Set Max units to 800%
Set rate to the relevant Euro / hour (per month is not accurate as number of 
working hours per month changes).
Enter Machines as a Resource
Enter cost/use of Euro 3000
Enter hourly rate

For each Task, assign resources (see help for assigning Resources) and costs 
will display accurately

In a Gantt Chart select Window Split. Make sure the hours of work estimated 
is accurate as Project calculates cost on hours*rate plus cost per use.

-- 

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
http://www.projectvbabook.com




"loukas_t" <loukas_t.424c3a@DoNotSpam.com> wrote in message 
news:loukas_t.424c3a@DoNotSpam.com...
>
> Hi all,
>
> Three questions:
> 1. What the constraint A<B,C means and how can I entering in the MSP?
> 2. I have 3 kinds of human resources. Lets say for example, kind A are
> engineers. I have 8 of them and everyone is costing 1500 Euros/month.
> Task A needs 4 engineers. How can I assign them to the task and add the
> appropriate cost?
> 3. I have 3 machines as a resource. Each machine has a usage cost of
> 3000 euros per task and function cost 2400 euros per month. How can I
> assign them in the appropriate tasks? And how can I distribute their
> cost?
>
> Thank you in advance
>
>
> -- 
> loukas_t
> ------------------------------------------------------------------------
> loukas_t's Profile: http://forums.techarena.in/members/153572.htm
> View this thread: http://forums.techarena.in/microsoft-project/1274342.htm
>
> http://forums.techarena.in
>
>
> __________ Information from ESET Smart Security, version of virus 
> signature database 4631 (20091123) __________
>
> The message was checked by ESET Smart Security.
>
> http://www.eset.com
>
>
> 

__________ Information from ESET Smart Security, version of virus signature database 4631 (20091123) __________

The message was checked by ESET Smart Security.

http://www.eset.com



0
Reply Rod 11/24/2009 2:52:51 AM


Rod thank you for the help.

Lets say that A,B,C are tasks and the relationship of these tasks (as a 
dapendence) is A<B,C. Does it mean that B and C are predecessors of A or what?

Is it clear?
-- 
-


"Rod Gill" wrote:

> Hi,
> 
> No idea what you mean by A<B,C. Please explain
> 
> In the View Resource Sheet
> Enter a Resource Engineer.
> Set Max units to 800%
> Set rate to the relevant Euro / hour (per month is not accurate as number of 
> working hours per month changes).
> Enter Machines as a Resource
> Enter cost/use of Euro 3000
> Enter hourly rate
> 
> For each Task, assign resources (see help for assigning Resources) and costs 
> will display accurately
> 
> In a Gantt Chart select Window Split. Make sure the hours of work estimated 
> is accurate as Project calculates cost on hours*rate plus cost per use.
> 
> -- 
> 
> Rod Gill
> Microsoft MVP for Project
> 
> Author of the only book on Project VBA, see:
> http://www.projectvbabook.com
> 
> 
> 
> 
> "loukas_t" <loukas_t.424c3a@DoNotSpam.com> wrote in message 
> news:loukas_t.424c3a@DoNotSpam.com...
> >
> > Hi all,
> >
> > Three questions:
> > 1. What the constraint A<B,C means and how can I entering in the MSP?
> > 2. I have 3 kinds of human resources. Lets say for example, kind A are
> > engineers. I have 8 of them and everyone is costing 1500 Euros/month.
> > Task A needs 4 engineers. How can I assign them to the task and add the
> > appropriate cost?
> > 3. I have 3 machines as a resource. Each machine has a usage cost of
> > 3000 euros per task and function cost 2400 euros per month. How can I
> > assign them in the appropriate tasks? And how can I distribute their
> > cost?
> >
> > Thank you in advance
> >
> >
> > -- 
> > loukas_t
> > ------------------------------------------------------------------------
> > loukas_t's Profile: http://forums.techarena.in/members/153572.htm
> > View this thread: http://forums.techarena.in/microsoft-project/1274342.htm
> >
> > http://forums.techarena.in
> >
> >
> > __________ Information from ESET Smart Security, version of virus 
> > signature database 4631 (20091123) __________
> >
> > The message was checked by ESET Smart Security.
> >
> > http://www.eset.com
> >
> >
> > 
> 
> __________ Information from ESET Smart Security, version of virus signature database 4631 (20091123) __________
> 
> The message was checked by ESET Smart Security.
> 
> http://www.eset.com
> 
> 
> 
> .
> 
0
Reply 11/24/2009 6:57:02 AM

A<B means nothing to me except in an algebra context. What does it mean to 
you? If you don't know, please ask the person who old you!

-- 

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
http://www.projectvbabook.com




<-> wrote in message 
news:CC30EF0F-C7FD-489F-AFAC-B41BA41D7AAE@microsoft.com...
> Rod thank you for the help.
>
> Lets say that A,B,C are tasks and the relationship of these tasks (as a
> dapendence) is A<B,C. Does it mean that B and C are predecessors of A or 
> what?
>
> Is it clear?
> -- 
> -
>
>
> "Rod Gill" wrote:
>
>> Hi,
>>
>> No idea what you mean by A<B,C. Please explain
>>
>> In the View Resource Sheet
>> Enter a Resource Engineer.
>> Set Max units to 800%
>> Set rate to the relevant Euro / hour (per month is not accurate as number 
>> of
>> working hours per month changes).
>> Enter Machines as a Resource
>> Enter cost/use of Euro 3000
>> Enter hourly rate
>>
>> For each Task, assign resources (see help for assigning Resources) and 
>> costs
>> will display accurately
>>
>> In a Gantt Chart select Window Split. Make sure the hours of work 
>> estimated
>> is accurate as Project calculates cost on hours*rate plus cost per use.
>>
>> -- 
>>
>> Rod Gill
>> Microsoft MVP for Project
>>
>> Author of the only book on Project VBA, see:
>> http://www.projectvbabook.com
>>
>>
>>
>>
>> "loukas_t" <loukas_t.424c3a@DoNotSpam.com> wrote in message
>> news:loukas_t.424c3a@DoNotSpam.com...
>> >
>> > Hi all,
>> >
>> > Three questions:
>> > 1. What the constraint A<B,C means and how can I entering in the MSP?
>> > 2. I have 3 kinds of human resources. Lets say for example, kind A are
>> > engineers. I have 8 of them and everyone is costing 1500 Euros/month.
>> > Task A needs 4 engineers. How can I assign them to the task and add the
>> > appropriate cost?
>> > 3. I have 3 machines as a resource. Each machine has a usage cost of
>> > 3000 euros per task and function cost 2400 euros per month. How can I
>> > assign them in the appropriate tasks? And how can I distribute their
>> > cost?
>> >
>> > Thank you in advance
>> >
>> >
>> > -- 
>> > loukas_t
>> > ------------------------------------------------------------------------
>> > loukas_t's Profile: http://forums.techarena.in/members/153572.htm
>> > View this thread: 
>> > http://forums.techarena.in/microsoft-project/1274342.htm
>> >
>> > http://forums.techarena.in
>> >
>> >
>> > __________ Information from ESET Smart Security, version of virus
>> > signature database 4631 (20091123) __________
>> >
>> > The message was checked by ESET Smart Security.
>> >
>> > http://www.eset.com
>> >
>> >
>> >
>>
>> __________ Information from ESET Smart Security, version of virus 
>> signature database 4631 (20091123) __________
>>
>> The message was checked by ESET Smart Security.
>>
>> http://www.eset.com
>>
>>
>>
>> .
>>
>
> __________ Information from ESET Smart Security, version of virus 
> signature database 4631 (20091123) __________
>
> The message was checked by ESET Smart Security.
>
> http://www.eset.com
>
>
> 

__________ Information from ESET Smart Security, version of virus signature database 4631 (20091123) __________

The message was checked by ESET Smart Security.

http://www.eset.com



0
Reply Rod 11/24/2009 8:10:30 AM

I found this type of a constraint in a project's contents table. Anyway
I think this declares that task A has predecessors B and C.

Thanks Rod


-- 
loukas_t
------------------------------------------------------------------------
loukas_t's Profile: http://forums.techarena.in/members/153572.htm
View this thread: http://forums.techarena.in/microsoft-project/1274344.htm

http://forums.techarena.in

0
Reply loukas_t 11/24/2009 8:43:19 AM

I'd ask the person who put it there.
This sort of information needs to be interpreted in order to make any sort 
of modeling decision.

-Jack Dahlgren


"loukas_t" <loukas_t.425ezb@DoNotSpam.com> wrote in message 
news:loukas_t.425ezb@DoNotSpam.com...
>
> I found this type of a constraint in a project's contents table. Anyway
> I think this declares that task A has predecessors B and C.
>
> Thanks Rod
>
>
> -- 
> loukas_t
> ------------------------------------------------------------------------
> loukas_t's Profile: http://forums.techarena.in/members/153572.htm
> View this thread: http://forums.techarena.in/microsoft-project/1274344.htm
>
> http://forums.techarena.in
> 

0
Reply Jack 11/25/2009 5:20:41 PM

5 Replies