How to reflect resource on vacation
Hi,
I use MS Project 2007. I wish to know the best way to represent when a
resource will be on vacation for a particular day(s) in my schedule. Can
anyone throw some light on this please? If you give an example that would be
great. Thank you in advance.
--
Thanks and Regards,
Aravind G
|
|
0
|
|
|
|
Reply
|
Utf
|
12/10/2009 8:34:01 AM |
|
Hi,
Edit the Resource's calendar and set the vacation days to non-working.
Tools, Change Working time.
--
Rod Gill
Microsoft MVP for Project
Author of the only book on Project VBA, see:
http://www.projectvbabook.com
"Aravind G" <AravindG@discussions.microsoft.com> wrote in message
news:7BD64423-BAF6-4EB0-8665-6E47E78D2891@microsoft.com...
> Hi,
>
> I use MS Project 2007. I wish to know the best way to represent when a
> resource will be on vacation for a particular day(s) in my schedule. Can
> anyone throw some light on this please? If you give an example that would
> be
> great. Thank you in advance.
>
> --
>
> Thanks and Regards,
> Aravind G
>
> __________ Information from ESET Smart Security, version of virus
> signature database 4674 (20091209) __________
>
> The message was checked by ESET Smart Security.
>
> http://www.eset.com
>
>
>
__________ Information from ESET Smart Security, version of virus signature database 4674 (20091209) __________
The message was checked by ESET Smart Security.
http://www.eset.com
|
|
0
|
|
|
|
Reply
|
Rod
|
12/10/2009 9:16:11 AM
|
|
Hi Aravind
Adding on to Rod's suggestion. If you want to identify the non working day
as a vacation. In 'Exceptions' tab of 'Change working time' window for that
non working day you may write that it is for the vacation.
I hope it helps.
Vanita
--
Project Management consultant and trainer
vanita_ahuja@yahoo.com
"Aravind G" wrote:
> Hi,
>
> I use MS Project 2007. I wish to know the best way to represent when a
> resource will be on vacation for a particular day(s) in my schedule. Can
> anyone throw some light on this please? If you give an example that would be
> great. Thank you in advance.
>
> --
>
> Thanks and Regards,
> Aravind G
|
|
0
|
|
|
|
Reply
|
Utf
|
12/11/2009 4:40:01 AM
|
|
|
2 Replies
838 Views
(page loaded in 0.048 seconds)
Similiar Articles: How to reflect resource on vacation - microsoft.public.project ...Hi, I use MS Project 2007. I wish to know the best way to represent when a resource will be on vacation for a particular day(s) in my schedule. C... How to plan resource vacations in Project Server 2007 - microsoft ...How to reflect resource on vacation - microsoft.public.project ... Hi, I use MS Project 2007. I wish to know the best way to represent when a resource will be on vacation ... Vacation Response - microsoft.public.windows.vista.mail ...How to reflect resource on vacation - microsoft.public.project ... Vacation Response - microsoft.public.windows.vista.mail ... How to reflect resource on vacation ... Task w/ Multiple Resource - schedule around availability ...It so happens that one of the resources that must perform the task is away on vacation when the predecessor finishes. Even though the vacation is entered as an ... how do I set availability at less than 8 hours per day ...How to reflect resource on vacation - microsoft.public.project ... how do I set availability at less than 8 hours per day ... Is there a way to set Project to have the ... Project 2007 non working day - microsoft.public.project ...How to reflect resource on vacation - microsoft.public.project ... Project 2007 non working day - microsoft.public.project ... How to reflect resource on vacation ... Enter vacation dates without moving tasks timelines - microsoft ...You may establish vacation dates for individual resources in Project 2003 (and later) in two ways. 1. What I do is use "exceptions". In P2003, go to the resource ... date stamp on delay delivery mail - microsoft.public.outlook ...You would need to send on the date you want the stamp to reflect. MKT Columbia ... date stamp on delay delivery mail - microsoft.public.outlook ..... on vacation ... Replace the Resource - microsoft.public.projectI could able to replace the assigned resource using Task Information dialog box’s ... rather than just focussing on getting the task's resource assignment to reflect ... Milestone Levels - microsoft.public.project> > I was wondering how best to reflect the milestone levels in the Gantt > view ... Leveling Resource in Linked Project - microsoft.public.project ... > > To enter and ... How to reflect resource on vacation - microsoft.public.project ...Hi, I use MS Project 2007. I wish to know the best way to represent when a resource will be on vacation for a particular day(s) in my schedule. C... Reflect Resources - Marketing, Technology, Consulting - Acworth ...Reflect Resources - Marketing, Technology, Consulting, Acworth, GA. 61 likes · 3 talking about this Reflect Resources | LinkedInJoin LinkedIn and see how you are connected to Reflect Resources. It's free.Get access to insightful information about your network at thousands of companies! How to Set Up Mirrors to See Your Trailer | eHow.comAdd side mirror extenders if the trailer or load you carry obstructs your view and prevents safe travel. ... Resources. National Highway Traffic Safety ... How to Reflect More Light | eHow.comResources. University of Missouri Extension; Landscaping ... How Does Light Travel? In order to understand how light ... If you stand in front of the mirror and... Science ... 7/25/2012 1:31:36 PM
|
|
|
|
|
|
|
|
|