How do I change the colour to a block of bars?

  • Follow


Rather than change each bar individually is it possible to highlight a number 
of bars and change their colour in one operation?
0
Reply Utf 4/23/2010 11:15:01 AM

By "bar" I assume you mean the Gantt Chart bars?

Select all the rows, individually or in block(s), then Menu: Format/Bar. 
  You select rows by clicking in the ID columns (by default it's the 
extreme left column in the Gantt Chart view).

--rms

www.rmschneider.com




On 23/04/10 12:15, 542779 wrote:
> Rather than change each bar individually is it possible to highlight a number
> of bars and change their colour in one operation?
0
Reply Rob 4/23/2010 11:23:26 AM


1 Replies
154 Views

(page loaded in 0.076 seconds)