Ghost Hours appearing in PWA timesheet

  • Follow


Why are actual hours automatically appearing on a resources timesheet?  They 
go to open their timesheet and there are hours there that they did not log.
0
Reply Utf 5/25/2010 3:15:01 PM

Hi Amy,

does the project manager of these tasks update project progress manually? If 
he does (e.g. set %complete in his project plan), 'Work' for each day will 
be copied to 'Actual Work' for a period. These hours will be pre-populated 
in timesheets. If my assumption is correct, tell them to change remaining 
work rather than %complete to update their project progress.

Regards
Barbara

P.s.: This forum will be closed in the near future. For new questions 
regarding Project Server you should have a look at 
http://social.technet.microsoft.com/Forums/en-US/projectserver2010general 
(don't get confused by "2010" in the name)

"Amy U" <AmyU@discussions.microsoft.com> schrieb im Newsbeitrag 
news:DE24243A-07DA-4C77-8CB5-C1C87ADEA171@microsoft.com...
> Why are actual hours automatically appearing on a resources timesheet? 
> They
> go to open their timesheet and there are hours there that they did not 
> log. 

0
Reply Barbara 5/27/2010 9:59:56 AM


Barbara,

I checked with the PM and here was her response,

"I do not manage my plans that way.  The only time that I modify % complete 
is if I remove all work and the % does not change.  Below is an example of 
when I might modify the % complete, but again only if work is zero.

Example:  Task never started and determined it was not needed.  Remove 
remaining work using task usage view.  Modify % complete in either the task 
detail or column inserted in view."

Your thoughts?

"Barbara Henhapl" wrote:

> Hi Amy,
> 
> does the project manager of these tasks update project progress manually? If 
> he does (e.g. set %complete in his project plan), 'Work' for each day will 
> be copied to 'Actual Work' for a period. These hours will be pre-populated 
> in timesheets. If my assumption is correct, tell them to change remaining 
> work rather than %complete to update their project progress.
> 
> Regards
> Barbara
> 
> P.s.: This forum will be closed in the near future. For new questions 
> regarding Project Server you should have a look at 
> http://social.technet.microsoft.com/Forums/en-US/projectserver2010general 
> (don't get confused by "2010" in the name)
> 
> "Amy U" <AmyU@discussions.microsoft.com> schrieb im Newsbeitrag 
> news:DE24243A-07DA-4C77-8CB5-C1C87ADEA171@microsoft.com...
> > Why are actual hours automatically appearing on a resources timesheet? 
> > They
> > go to open their timesheet and there are hours there that they did not 
> > log. 
> 
0
Reply Utf 6/3/2010 5:55:47 PM

2 Replies