Why are actual hours automatically appearing on a resources timesheet? They
go to open their timesheet and there are hours there that they did not log.
|
|
0
|
|
|
|
Reply
|
Utf
|
5/25/2010 3:15:01 PM |
|
Hi Amy,
does the project manager of these tasks update project progress manually? If
he does (e.g. set %complete in his project plan), 'Work' for each day will
be copied to 'Actual Work' for a period. These hours will be pre-populated
in timesheets. If my assumption is correct, tell them to change remaining
work rather than %complete to update their project progress.
Regards
Barbara
P.s.: This forum will be closed in the near future. For new questions
regarding Project Server you should have a look at
http://social.technet.microsoft.com/Forums/en-US/projectserver2010general
(don't get confused by "2010" in the name)
"Amy U" <AmyU@discussions.microsoft.com> schrieb im Newsbeitrag
news:DE24243A-07DA-4C77-8CB5-C1C87ADEA171@microsoft.com...
> Why are actual hours automatically appearing on a resources timesheet?
> They
> go to open their timesheet and there are hours there that they did not
> log.
|
|
0
|
|
|
|
Reply
|
Barbara
|
5/27/2010 9:59:56 AM
|
|
Barbara,
I checked with the PM and here was her response,
"I do not manage my plans that way. The only time that I modify % complete
is if I remove all work and the % does not change. Below is an example of
when I might modify the % complete, but again only if work is zero.
Example: Task never started and determined it was not needed. Remove
remaining work using task usage view. Modify % complete in either the task
detail or column inserted in view."
Your thoughts?
"Barbara Henhapl" wrote:
> Hi Amy,
>
> does the project manager of these tasks update project progress manually? If
> he does (e.g. set %complete in his project plan), 'Work' for each day will
> be copied to 'Actual Work' for a period. These hours will be pre-populated
> in timesheets. If my assumption is correct, tell them to change remaining
> work rather than %complete to update their project progress.
>
> Regards
> Barbara
>
> P.s.: This forum will be closed in the near future. For new questions
> regarding Project Server you should have a look at
> http://social.technet.microsoft.com/Forums/en-US/projectserver2010general
> (don't get confused by "2010" in the name)
>
> "Amy U" <AmyU@discussions.microsoft.com> schrieb im Newsbeitrag
> news:DE24243A-07DA-4C77-8CB5-C1C87ADEA171@microsoft.com...
> > Why are actual hours automatically appearing on a resources timesheet?
> > They
> > go to open their timesheet and there are hours there that they did not
> > log.
>
|
|
0
|
|
|
|
Reply
|
Utf
|
6/3/2010 5:55:47 PM
|
|