Delete unused resource in MS Project?

  • Follow


Someone has added a list of resources that I now want to delete from the 
resource list to prevent assigning to any tasks.  
0
Reply Utf 1/8/2010 10:55:01 PM

Parris,

If the resources are assigned to tasks, view the Gantt chart use the 
"using resource filter" to filter for those resources, and then 
re-assign those tasks to other resources.  After making sure the 
resources have no tasks assigned, if you are using MS Project (not 
Project Server), open the file, view the Resource Sheet and delete the 
resources.

I sense there may be something more to what you need, but without 
further information from you (are you using server?  are you using a 
resource pool file?) it's tough to give more specific advice.
I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project


On 1/8/2010 5:55 PM, Parris_In_Florida wrote:
> Someone has added a list of resources that I now want to delete from the
> resource list to prevent assigning to any tasks.
>    
0
Reply JulieS 1/8/2010 11:01:24 PM


Parris_In_Florida --

Click View - Resource Sheet.  Select the gray row headers for the resources 
you do not want to use in your project and then press the Delete key on your 
computer keyboard.  Save your project.

If your project is connected to a shared Resource Pool file, the above steps 
will not work.  When you use a shared Resource Pool file, the resource pool 
always shares every resource with your sharing project.  Are you using a 
shared Resource Pool file with your project, by chance?  If not, ignore this 
paragraph!  :)

Hope this helps.

-- 
Dale A. Howard [MVP]
VP of Educational Services
msProjectExperts
http://www.msprojectexperts.com
http://www.projectserverexperts.com
"We write the books on Project Server"


"Parris_In_Florida" <Parris_In_Florida@discussions.microsoft.com> wrote in 
message news:B3F13D6E-ECE5-4777-8887-103585F2C8A8@microsoft.com...
> Someone has added a list of resources that I now want to delete from the
> resource list to prevent assigning to any tasks. 

1
Reply Dale 1/8/2010 11:04:16 PM

2 Replies
7708 Views

(page loaded in 0.181 seconds)

Similiar Articles:
















7/20/2012 8:05:48 PM


Reply: