Changing Holiday in Enterprise Global

  • Follow


Does MS Project 2007 automatically flag a holiday that falls on the weekend 
to the prior/following work day or is this something that I can change?  
Example, July 4, 2010 was marked as a holiday, but it is showing up as July 5 
being a non-working day for the holiday.  The same thing happens for Christmas
0
Reply Utf 5/25/2010 3:13:01 PM

Amy --

No, Microsoft Project 2007 does NOT automatically flag holidays that occur 
on a Saturday and Sunday, and then reschedule them to the preceding Friday 
or following Monday.  The reason the software does not do this is because 
every organization has different policies concerning what happens when a 
holiday falls on a weekend.  In the 13+ years I have worked with this tool, 
I have seen the following company policies for weekend holidays:

-- If the holiday falls on a Saturday, the preceding Friday is the 
recognized holiday; if the holiday falls on a Sunday, the following Monday 
is the recognized holiday (this is the most common, but not every company 
does this).

-- If the holiday falls on a weekend, the preceding Friday is always the 
recognized holiday.

-- If the holiday falls on a weekend, the following Monday is always the 
recognized holiday.

-- If the holiday falls on a weekend, there is no recognized holiday on the 
preceding Friday or following Monday.  Instead, each worker gets one 
additional personal holiday which he/she can use as he/she wishes.

Given the above scenarios, see why Microsoft Project 2007 doesn't do what 
you hoped it would do in regard to weekend holidays?  So, what you need to 
do is to create additional instances of the holiday according to your 
company's policy.  For example, Independence Day this year falls on a 
Sunday.  So, you would need to create one additional instance of 
Independence Day to set July 5th as the holiday.  Also, when you create your 
company holidays, click the Details button for each holiday and set the 
holiday to recur 2 or more years into the future.  I personally like to 
create 5 years of holidays to minimize the amount of work I must do.

Hope this helps.

-- 
Dale A. Howard [MVP]
VP of Educational Services
msProjectExperts
http://www.msprojectexperts.com
http://www.projectserverexperts.com
"We write the books on Project Server"


"Amy U" <Amy U@discussions.microsoft.com> wrote in message 
news:6F1FCE17-A786-4F45-989E-AE771E2D0C88@microsoft.com...
> Does MS Project 2007 automatically flag a holiday that falls on the 
> weekend
> to the prior/following work day or is this something that I can change?
> Example, July 4, 2010 was marked as a holiday, but it is showing up as 
> July 5
> being a non-working day for the holiday.  The same thing happens for 
> Christmas 

0
Reply Dale 5/25/2010 8:51:08 PM


Dale,

In my case, in the Enterprise global the holiday is marked as July 5 vs. 
July 4 and I am wondering how to go about changing that.  Please advise.  
Thanks!

"Dale Howard [MVP]" wrote:

> Amy --
> 
> No, Microsoft Project 2007 does NOT automatically flag holidays that occur 
> on a Saturday and Sunday, and then reschedule them to the preceding Friday 
> or following Monday.  The reason the software does not do this is because 
> every organization has different policies concerning what happens when a 
> holiday falls on a weekend.  In the 13+ years I have worked with this tool, 
> I have seen the following company policies for weekend holidays:
> 
> -- If the holiday falls on a Saturday, the preceding Friday is the 
> recognized holiday; if the holiday falls on a Sunday, the following Monday 
> is the recognized holiday (this is the most common, but not every company 
> does this).
> 
> -- If the holiday falls on a weekend, the preceding Friday is always the 
> recognized holiday.
> 
> -- If the holiday falls on a weekend, the following Monday is always the 
> recognized holiday.
> 
> -- If the holiday falls on a weekend, there is no recognized holiday on the 
> preceding Friday or following Monday.  Instead, each worker gets one 
> additional personal holiday which he/she can use as he/she wishes.
> 
> Given the above scenarios, see why Microsoft Project 2007 doesn't do what 
> you hoped it would do in regard to weekend holidays?  So, what you need to 
> do is to create additional instances of the holiday according to your 
> company's policy.  For example, Independence Day this year falls on a 
> Sunday.  So, you would need to create one additional instance of 
> Independence Day to set July 5th as the holiday.  Also, when you create your 
> company holidays, click the Details button for each holiday and set the 
> holiday to recur 2 or more years into the future.  I personally like to 
> create 5 years of holidays to minimize the amount of work I must do.
> 
> Hope this helps.
> 
> -- 
> Dale A. Howard [MVP]
> VP of Educational Services
> msProjectExperts
> http://www.msprojectexperts.com
> http://www.projectserverexperts.com
> "We write the books on Project Server"
> 
> 
> "Amy U" <Amy U@discussions.microsoft.com> wrote in message 
> news:6F1FCE17-A786-4F45-989E-AE771E2D0C88@microsoft.com...
> > Does MS Project 2007 automatically flag a holiday that falls on the 
> > weekend
> > to the prior/following work day or is this something that I can change?
> > Example, July 4, 2010 was marked as a holiday, but it is showing up as 
> > July 5
> > being a non-working day for the holiday.  The same thing happens for 
> > Christmas 
> 
0
Reply Utf 6/3/2010 5:33:01 PM

Amy U --

You have to be a Project Server administrator to perform the following 
steps:

1.  Log into PWA and then click the Server Settings link in the Quick Launch 
menu.
2.  Click the Enterprise Calendars link in the Enterprise Data section of 
the Server Settings page.
3.  Select the Standard calendar (assuming that is the calendar your 
organization uses) and click the Edit Calendar button.

The system opens the enterprise Standard calendar for editing in Microsoft 
Project 2007.

4.  Set the holidays according to your company's standards.
5.  Click the OK button.

Hope this helps.

-- 
Dale A. Howard [MVP]
VP of Educational Services
msProjectExperts
http://www.msprojectexperts.com
http://www.projectserverexperts.com
"We write the books on Project Server"


"Amy U" <AmyU@discussions.microsoft.com> wrote in message 
news:8A9B8386-EDF0-435C-BB04-552B798D2931@microsoft.com...
> Dale,
>
> In my case, in the Enterprise global the holiday is marked as July 5 vs.
> July 4 and I am wondering how to go about changing that.  Please advise.
> Thanks!
>
> "Dale Howard [MVP]" wrote:
>
>> Amy --
>>
>> No, Microsoft Project 2007 does NOT automatically flag holidays that 
>> occur
>> on a Saturday and Sunday, and then reschedule them to the preceding 
>> Friday
>> or following Monday.  The reason the software does not do this is because
>> every organization has different policies concerning what happens when a
>> holiday falls on a weekend.  In the 13+ years I have worked with this 
>> tool,
>> I have seen the following company policies for weekend holidays:
>>
>> -- If the holiday falls on a Saturday, the preceding Friday is the
>> recognized holiday; if the holiday falls on a Sunday, the following 
>> Monday
>> is the recognized holiday (this is the most common, but not every company
>> does this).
>>
>> -- If the holiday falls on a weekend, the preceding Friday is always the
>> recognized holiday.
>>
>> -- If the holiday falls on a weekend, the following Monday is always the
>> recognized holiday.
>>
>> -- If the holiday falls on a weekend, there is no recognized holiday on 
>> the
>> preceding Friday or following Monday.  Instead, each worker gets one
>> additional personal holiday which he/she can use as he/she wishes.
>>
>> Given the above scenarios, see why Microsoft Project 2007 doesn't do what
>> you hoped it would do in regard to weekend holidays?  So, what you need 
>> to
>> do is to create additional instances of the holiday according to your
>> company's policy.  For example, Independence Day this year falls on a
>> Sunday.  So, you would need to create one additional instance of
>> Independence Day to set July 5th as the holiday.  Also, when you create 
>> your
>> company holidays, click the Details button for each holiday and set the
>> holiday to recur 2 or more years into the future.  I personally like to
>> create 5 years of holidays to minimize the amount of work I must do.
>>
>> Hope this helps.
>>
>> -- 
>> Dale A. Howard [MVP]
>> VP of Educational Services
>> msProjectExperts
>> http://www.msprojectexperts.com
>> http://www.projectserverexperts.com
>> "We write the books on Project Server"
>>
>>
>> "Amy U" <Amy U@discussions.microsoft.com> wrote in message
>> news:6F1FCE17-A786-4F45-989E-AE771E2D0C88@microsoft.com...
>> > Does MS Project 2007 automatically flag a holiday that falls on the
>> > weekend
>> > to the prior/following work day or is this something that I can change?
>> > Example, July 4, 2010 was marked as a holiday, but it is showing up as
>> > July 5
>> > being a non-working day for the holiday.  The same thing happens for
>> > Christmas
>> 
0
Reply Dale 6/3/2010 6:30:43 PM

I am the administrator and had looked at the steps that you mentioned, 
however, the Standard calendar looks to be checked out and so the Edit 
Calendar is grayed out and I cannot choose it.  Next steps?

"Dale Howard [MVP]" wrote:

> Amy U --
> 
> You have to be a Project Server administrator to perform the following 
> steps:
> 
> 1.  Log into PWA and then click the Server Settings link in the Quick Launch 
> menu.
> 2.  Click the Enterprise Calendars link in the Enterprise Data section of 
> the Server Settings page.
> 3.  Select the Standard calendar (assuming that is the calendar your 
> organization uses) and click the Edit Calendar button.
> 
> The system opens the enterprise Standard calendar for editing in Microsoft 
> Project 2007.
> 
> 4.  Set the holidays according to your company's standards.
> 5.  Click the OK button.
> 
> Hope this helps.
> 
> -- 
> Dale A. Howard [MVP]
> VP of Educational Services
> msProjectExperts
> http://www.msprojectexperts.com
> http://www.projectserverexperts.com
> "We write the books on Project Server"
> 
> 
> "Amy U" <AmyU@discussions.microsoft.com> wrote in message 
> news:8A9B8386-EDF0-435C-BB04-552B798D2931@microsoft.com...
> > Dale,
> >
> > In my case, in the Enterprise global the holiday is marked as July 5 vs.
> > July 4 and I am wondering how to go about changing that.  Please advise.
> > Thanks!
> >
> > "Dale Howard [MVP]" wrote:
> >
> >> Amy --
> >>
> >> No, Microsoft Project 2007 does NOT automatically flag holidays that 
> >> occur
> >> on a Saturday and Sunday, and then reschedule them to the preceding 
> >> Friday
> >> or following Monday.  The reason the software does not do this is because
> >> every organization has different policies concerning what happens when a
> >> holiday falls on a weekend.  In the 13+ years I have worked with this 
> >> tool,
> >> I have seen the following company policies for weekend holidays:
> >>
> >> -- If the holiday falls on a Saturday, the preceding Friday is the
> >> recognized holiday; if the holiday falls on a Sunday, the following 
> >> Monday
> >> is the recognized holiday (this is the most common, but not every company
> >> does this).
> >>
> >> -- If the holiday falls on a weekend, the preceding Friday is always the
> >> recognized holiday.
> >>
> >> -- If the holiday falls on a weekend, the following Monday is always the
> >> recognized holiday.
> >>
> >> -- If the holiday falls on a weekend, there is no recognized holiday on 
> >> the
> >> preceding Friday or following Monday.  Instead, each worker gets one
> >> additional personal holiday which he/she can use as he/she wishes.
> >>
> >> Given the above scenarios, see why Microsoft Project 2007 doesn't do what
> >> you hoped it would do in regard to weekend holidays?  So, what you need 
> >> to
> >> do is to create additional instances of the holiday according to your
> >> company's policy.  For example, Independence Day this year falls on a
> >> Sunday.  So, you would need to create one additional instance of
> >> Independence Day to set July 5th as the holiday.  Also, when you create 
> >> your
> >> company holidays, click the Details button for each holiday and set the
> >> holiday to recur 2 or more years into the future.  I personally like to
> >> create 5 years of holidays to minimize the amount of work I must do.
> >>
> >> Hope this helps.
> >>
> >> -- 
> >> Dale A. Howard [MVP]
> >> VP of Educational Services
> >> msProjectExperts
> >> http://www.msprojectexperts.com
> >> http://www.projectserverexperts.com
> >> "We write the books on Project Server"
> >>
> >>
> >> "Amy U" <Amy U@discussions.microsoft.com> wrote in message
> >> news:6F1FCE17-A786-4F45-989E-AE771E2D0C88@microsoft.com...
> >> > Does MS Project 2007 automatically flag a holiday that falls on the
> >> > weekend
> >> > to the prior/following work day or is this something that I can change?
> >> > Example, July 4, 2010 was marked as a holiday, but it is showing up as
> >> > July 5
> >> > being a non-working day for the holiday.  The same thing happens for
> >> > Christmas
> >> 
0
Reply Utf 6/4/2010 1:02:52 PM

Amy U --

If the enterprise Standard calendar is "stuck" in a checked out condition, 
you need to force check it in using the following steps:

1.  Log into PWA with administrator permissions.
2.  Click Server Settings - Force Check In Enterprise Objects.
3.  Click the pick list at the top and select the Enterprise Calendars item.
4.  Select the Standard calendar and click the Check In button.

Also, you might find the following books helpful to you in your work with 
Project Server 2007:

http://www.projectserverbooks.com/books/implementingadministeringprojectserver2007.aspx

http://www.projectserverbooks.com/books/managingprojectsprojectserver2007.aspx

Hope this helps.

-- 
Dale A. Howard [MVP]
VP of Educational Services
msProjectExperts
http://www.msprojectexperts.com
http://www.projectserverexperts.com
"We write the books on Project Server"


"Amy U" <AmyU@discussions.microsoft.com> wrote in message 
news:4EAAA2FF-AA8E-4846-B341-C53280E37843@microsoft.com...
> I am the administrator and had looked at the steps that you mentioned,
> however, the Standard calendar looks to be checked out and so the Edit
> Calendar is grayed out and I cannot choose it.  Next steps?
>
> "Dale Howard [MVP]" wrote:
>
>> Amy U --
>>
>> You have to be a Project Server administrator to perform the following
>> steps:
>>
>> 1.  Log into PWA and then click the Server Settings link in the Quick 
>> Launch
>> menu.
>> 2.  Click the Enterprise Calendars link in the Enterprise Data section of
>> the Server Settings page.
>> 3.  Select the Standard calendar (assuming that is the calendar your
>> organization uses) and click the Edit Calendar button.
>>
>> The system opens the enterprise Standard calendar for editing in 
>> Microsoft
>> Project 2007.
>>
>> 4.  Set the holidays according to your company's standards.
>> 5.  Click the OK button.
>>
>> Hope this helps.
>>
>> -- 
>> Dale A. Howard [MVP]
>> VP of Educational Services
>> msProjectExperts
>> http://www.msprojectexperts.com
>> http://www.projectserverexperts.com
>> "We write the books on Project Server"
>>
>>
>> "Amy U" <AmyU@discussions.microsoft.com> wrote in message
>> news:8A9B8386-EDF0-435C-BB04-552B798D2931@microsoft.com...
>> > Dale,
>> >
>> > In my case, in the Enterprise global the holiday is marked as July 5 
>> > vs.
>> > July 4 and I am wondering how to go about changing that.  Please 
>> > advise.
>> > Thanks!
>> >
>> > "Dale Howard [MVP]" wrote:
>> >
>> >> Amy --
>> >>
>> >> No, Microsoft Project 2007 does NOT automatically flag holidays that
>> >> occur
>> >> on a Saturday and Sunday, and then reschedule them to the preceding
>> >> Friday
>> >> or following Monday.  The reason the software does not do this is 
>> >> because
>> >> every organization has different policies concerning what happens when 
>> >> a
>> >> holiday falls on a weekend.  In the 13+ years I have worked with this
>> >> tool,
>> >> I have seen the following company policies for weekend holidays:
>> >>
>> >> -- If the holiday falls on a Saturday, the preceding Friday is the
>> >> recognized holiday; if the holiday falls on a Sunday, the following
>> >> Monday
>> >> is the recognized holiday (this is the most common, but not every 
>> >> company
>> >> does this).
>> >>
>> >> -- If the holiday falls on a weekend, the preceding Friday is always 
>> >> the
>> >> recognized holiday.
>> >>
>> >> -- If the holiday falls on a weekend, the following Monday is always 
>> >> the
>> >> recognized holiday.
>> >>
>> >> -- If the holiday falls on a weekend, there is no recognized holiday 
>> >> on
>> >> the
>> >> preceding Friday or following Monday.  Instead, each worker gets one
>> >> additional personal holiday which he/she can use as he/she wishes.
>> >>
>> >> Given the above scenarios, see why Microsoft Project 2007 doesn't do 
>> >> what
>> >> you hoped it would do in regard to weekend holidays?  So, what you 
>> >> need
>> >> to
>> >> do is to create additional instances of the holiday according to your
>> >> company's policy.  For example, Independence Day this year falls on a
>> >> Sunday.  So, you would need to create one additional instance of
>> >> Independence Day to set July 5th as the holiday.  Also, when you 
>> >> create
>> >> your
>> >> company holidays, click the Details button for each holiday and set 
>> >> the
>> >> holiday to recur 2 or more years into the future.  I personally like 
>> >> to
>> >> create 5 years of holidays to minimize the amount of work I must do.
>> >>
>> >> Hope this helps.
>> >>
>> >> -- 
>> >> Dale A. Howard [MVP]
>> >> VP of Educational Services
>> >> msProjectExperts
>> >> http://www.msprojectexperts.com
>> >> http://www.projectserverexperts.com
>> >> "We write the books on Project Server"
>> >>
>> >>
>> >> "Amy U" <Amy U@discussions.microsoft.com> wrote in message
>> >> news:6F1FCE17-A786-4F45-989E-AE771E2D0C88@microsoft.com...
>> >> > Does MS Project 2007 automatically flag a holiday that falls on the
>> >> > weekend
>> >> > to the prior/following work day or is this something that I can 
>> >> > change?
>> >> > Example, July 4, 2010 was marked as a holiday, but it is showing up 
>> >> > as
>> >> > July 5
>> >> > being a non-working day for the holiday.  The same thing happens for
>> >> > Christmas
>> >> 
0
Reply Dale 6/4/2010 2:14:36 PM

5 Replies
340 Views

(page loaded in 1.135 seconds)

Similiar Articles:







7/22/2012 5:54:34 AM


Reply: