Calendar View in Project 2007 - Viewing Items off of the screen.
I'm trying to use the Calendar View in Project 2007. My project is large and
when I set my layout option only some of the items are displayed in the day.
There is a dropdown arrow that indicates there are additional items. When
you print the calendar, those items then show up on a followup page and are
not user friendly.
My question is, how do you get to a task so that you can drag it up to be
visible in the calendar view?
I have tried using different sort orders but none of them get all of the
data onto one screen. Neither does the fit as many as possible option.
There is plenty of available space on the screen to move task to be displayed.
|
|
0
|
|
|
|
Reply
|
Utf
|
1/15/2010 7:44:02 PM |
|
Hello Project question,
The calendar view is very limited and even though you have "available
space" when you start dragging tasks about, you are changing the
schedule of the tasks.
About 5-6 tasks scheduled on a specific day are about all you can fit
without running into the "overflow" tasks when you print.
If you are going to print the Calendar view, my suggestion is to filter
the view -- perhaps only showing tasks assigned to a resource or
assigned to a group of resources.
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
On 1/15/2010 2:44 PM, ProjectQuestion wrote:
> I'm trying to use the Calendar View in Project 2007. My project is large and
> when I set my layout option only some of the items are displayed in the day.
> There is a dropdown arrow that indicates there are additional items. When
> you print the calendar, those items then show up on a followup page and are
> not user friendly.
>
> My question is, how do you get to a task so that you can drag it up to be
> visible in the calendar view?
>
> I have tried using different sort orders but none of them get all of the
> data onto one screen. Neither does the fit as many as possible option.
> There is plenty of available space on the screen to move task to be displayed.
>
|
|
0
|
|
|
|
Reply
|
JulieS
|
1/15/2010 10:30:51 PM
|
|
|
1 Replies
929 Views
(page loaded in 0.205 seconds)
Similiar Articles: Viewing Calendar Entries as a List - microsoft.public.outlook ...Calendar View in Project 2007 - Viewing Items off of the screen ... Viewing Calendar Entries as a List - microsoft.public.outlook ... Employees viewing my shared calendar ... Disappearing Calendar items - microsoft.public.outlook.calendaring ...Calendar View in Project 2007 - Viewing Items off of the screen ... Calendar items older than 60 days disappear ... Calendar View in Project 2007 - Viewing Items off of ... Have tasks automatically show up on calendar - microsoft.public ...Calendar View in Project 2007 - Viewing Items off of the screen ... Have tasks automatically show up on calendar - microsoft.public ..... SharePoint 2007 Is there a way to ... show task notes as either a report or in outlook calender ...Calendar View in Project 2007 - Viewing Items off of the screen ... show task notes as either a report or in outlook calender ... Hi there guys I am working on Project ... How to change font/spacing for Outlook 2007 calendar month view ...Calendar View in Project 2007 - Viewing Items off of the screen ... Change Calendar Week Number in Outlook 2007 - microsoft.public ..... font and line spacing on the ... Is there a way to print/display user permissions of all items in a ...Calendar View in Project 2007 - Viewing Items off of the screen ..... you print the calendar, those items then show up on a followup page and are not user ... Change Calendar Week Number in Outlook 2007 - microsoft.public ...Calendar View in Project 2007 - Viewing Items off of the screen ... Change Calendar Week Number in Outlook 2007 - microsoft.public ..... font and line spacing on the ... WSS Site Usage Report - microsoft.public.project.server ...Calendar View in Project 2007 - Viewing Items off of the screen ... show task notes as either a report or in outlook ... Project Calendar ... screen, as well as the Task ... Charts that are Off-Screen Disappear after update - microsoft ...Charts that are Off-Screen Disappear after update - microsoft ... Calendar items older than 60 days disappear ... Calendar View in Project 2007 - Viewing Items off of the ... Layout View Not Available - microsoft.public.access.forms ...Calendar View in Project 2007 - Viewing Items off of the screen ..... Calendar View in Project 2007. My project is large and when I set my layout ... calendar view is ... How to Display Calendar Items in the Side View of Outlook | eHow.comBy default, Outlook 2007 displays buttons on the left side of the screen that allow you to quickly access the different elements of the program, including the ... Microsoft Outlook 2007 Calendar FeaturesThe Outlook Calendar Screen ... Technology Training Rev 04-2007 -Page 2-Viewing Your Outlook Calendar ... calendar, no special display in calendar view ... Change the appearance of your calendar - Outlook - Office.comThe Microsoft Office Outlook 2007 calendar can be ... Turn bolded dates on or off. In Calendar, on the View menu, point to ... and does not affect the way in which calendar items ... View calendars side-by-side or overlaid - Outlook - Office.com... Outlook 2007 , you can view ... About viewing ... to track a project, a personal schedule, or some other calendar event that you do not want to mix with the items on ... Outlook 2007 Demo: Customize your calendar - YouTubeI have changed the font size in the customized view of my Outlook 2007 Calendar, which is ... Language: English Location: Worldwide Safety: Off 7/13/2012 3:32:28 PM
|
|
|
|
|
|
|
|
|