Hi
Certain tasks in a project (project tracking) will be from the beginning of
the prokject to the end of the project (a single task). If a resource
allocated to this task is assigned to some other tasks there will be
overallocation.
I have corrected this problem by allocating 10% for the project tracking
task and 90% for other tasks.
Is there any other way to solve this problem?
Thanks,
Manu
|
=?Utf-8?B?TWFhbnU=?= <Ma...@discussions.microsoft.com>
3/20/2010 4:02:06 AM
|
Yes, but your solution is best. If you resource assignments are not
accurate, you don't get a meaningful picture of what your resource needs
are.
--
Rod Gill
Microsoft MVP for Project - http://www.project-systems.co.nz
Author of the only book on Project VBA, see: http://www.projectvbabook.com
"Maanu" <Maanu@discussions.microsoft.com> wrote in message
news:E4079B39-5C7C-4B78-922F-64BEA88056DA@microsoft.com...
> Hi
>
> Certain tasks in a project (project tracking) will be from the beginning
> of
> the prokject to the end of the project (a single task). If a resource
> allocated to this task is assigned to some other tasks there will be
> overallocation.
>
> I have corrected this problem by allocating 10% for the project tracking
> task and 90% for other tasks.
>
> Is there any other way to solve this problem?
>
> Thanks,
> Manu
>
>
> __________ Information from ESET Smart Security, version of virus
> signature database 4959 (20100319) __________
>
> The message was checked by ESET Smart Security.
>
> http://www.eset.com
>
>
>
__________ Information from ESET Smart Security, version of virus signature database 4959 (20100319) __________
The message was checked by ESET Smart Security.
http://www.eset.com
|
"Rod Gill" <rodATproject-systemsDOTcoDOTnz>
3/20/2010 5:27:53 AM
|