View Notes in Project web accees

  • Follow


In Microsoft Office Project 2007 professional / desktop we have some notes 
attached for the milestones and  tasks. 
We have noticed that after publish the project to the server the notes are 
no longer available to view on My task or Project center, but if we open the 
project with Microsoft Office Project 2007 professional (desktop version) we 
can view the attachment. Wondering if there is any way to get access to the 
notes on PWA site (either My task or project center view) .
Please advice.

0
Reply Utf 2/24/2010 11:31:01 PM

Hi Baharam, 

the first thing that springs to my mind is that you may not have  pubslised 
the project? Can you please repbulish the project and let me know if the 
issue has been resolved
Thanks
Marc
-- 
Marc Soester [MVP]
http://www.i-pmo.com.au


"Bahram" wrote:

> In Microsoft Office Project 2007 professional / desktop we have some notes 
> attached for the milestones and  tasks. 
> We have noticed that after publish the project to the server the notes are 
> no longer available to view on My task or Project center, but if we open the 
> project with Microsoft Office Project 2007 professional (desktop version) we 
> can view the attachment. Wondering if there is any way to get access to the 
> notes on PWA site (either My task or project center view) .
> Please advice.
> 
0
Reply Utf 2/25/2010 3:03:01 PM


Hey Marc,

Thanks for your post.
We found the problem, and the problwm was because we not suppose to add the 
notes to the milestones and we have to attach the notes to the task to be 
able to see it on My task view on PWA. I think its because we can not assign 
a milestones to a resources and we have to assign a task (instead on 
milestones) to our resources. If it is not a true statement please let me 
know.
Thanks

"Marc Soester [MVP]" wrote:

> Hi Baharam, 
> 
> the first thing that springs to my mind is that you may not have  pubslised 
> the project? Can you please repbulish the project and let me know if the 
> issue has been resolved
> Thanks
> Marc
> -- 
> Marc Soester [MVP]
> http://www.i-pmo.com.au
> 
> 
> "Bahram" wrote:
> 
> > In Microsoft Office Project 2007 professional / desktop we have some notes 
> > attached for the milestones and  tasks. 
> > We have noticed that after publish the project to the server the notes are 
> > no longer available to view on My task or Project center, but if we open the 
> > project with Microsoft Office Project 2007 professional (desktop version) we 
> > can view the attachment. Wondering if there is any way to get access to the 
> > notes on PWA site (either My task or project center view) .
> > Please advice.
> > 
0
Reply Utf 2/26/2010 12:11:01 AM

Bahram --

In Project Server 2007, you CAN assign a resource to a Milestone task, and 
the resource CAN report progress on the Milestone selecting either the Done 
or Not Done option in the Progress field.  Hope this helps.

-- 
Dale A. Howard [MVP]
VP of Educational Services
msProjectExperts
http://www.msprojectexperts.com
http://www.projectserverexperts.com
"We write the books on Project Server"


"Bahram" <Bahram@discussions.microsoft.com> wrote in message 
news:24FC8289-0CDB-4DFA-A80F-FD4F843F9C99@microsoft.com...
> Hey Marc,
>
> Thanks for your post.
> We found the problem, and the problwm was because we not suppose to add 
> the
> notes to the milestones and we have to attach the notes to the task to be
> able to see it on My task view on PWA. I think its because we can not 
> assign
> a milestones to a resources and we have to assign a task (instead on
> milestones) to our resources. If it is not a true statement please let me
> know.
> Thanks
>
> "Marc Soester [MVP]" wrote:
>
>> Hi Baharam,
>>
>> the first thing that springs to my mind is that you may not have 
>> pubslised
>> the project? Can you please repbulish the project and let me know if the
>> issue has been resolved
>> Thanks
>> Marc
>> -- 
>> Marc Soester [MVP]
>> http://www.i-pmo.com.au
>>
>>
>> "Bahram" wrote:
>>
>> > In Microsoft Office Project 2007 professional / desktop we have some 
>> > notes
>> > attached for the milestones and  tasks.
>> > We have noticed that after publish the project to the server the notes 
>> > are
>> > no longer available to view on My task or Project center, but if we 
>> > open the
>> > project with Microsoft Office Project 2007 professional (desktop 
>> > version) we
>> > can view the attachment. Wondering if there is any way to get access to 
>> > the
>> > notes on PWA site (either My task or project center view) .
>> > Please advice.
>> > 
0
Reply Dale 2/26/2010 12:55:34 PM

3 Replies
599 Views

(page loaded in 0.078 seconds)