Timesheet on Published DB, but not in Reporting DB
Any ideas about cause and how to fix?
For a given user & period, I can see the timesheet on Published DB, but not
on Reporting DB. So far, see this with one user.
|
|
0
|
|
|
|
Reply
|
Utf
|
2/23/2010 9:29:03 PM |
|
Learner:
Reporting DB updates can fail from time to time. Things can get out of sync
when you cancel queue jobs. You can refresh the reporting database by
forcing it to rebuild by using the administrative backup feature to backup
you Enterprise custom fields, and then restore them. The restore action
forces the rebuild. See if that helps.
--
Gary L Chefetz, MVP, MCT, MCITP
msProjectExperts http://www.msprojectexperts.com
FAQs and Reference http://www.projectserverexperts.com
BLOG: http://projectserverhelp.com
"MSPLearner" <MSPLearner@discussions.microsoft.com> wrote in message
news:2CF830FC-9E59-4EDA-A16F-389AC9E1D91F@microsoft.com...
> Any ideas about cause and how to fix?
>
> For a given user & period, I can see the timesheet on Published DB, but
> not
> on Reporting DB. So far, see this with one user.
|
|
0
|
|
|
|
Reply
|
Gary
|
2/24/2010 10:33:06 AM
|
|
|
1 Replies
472 Views
(page loaded in 0.043 seconds)
Similiar Articles: Timesheet on Published DB, but not in Reporting DB - microsoft ...Any ideas about cause and how to fix? For a given user & period, I can see the timesheet on Published DB, but not on Reporting DB. So far, see th... Timesheet Custom Fields in Reporting Database MSPS 2007 ...Timesheet on Published DB, but not in Reporting DB - microsoft ... Timesheet Custom Fields in Reporting Database MSPS 2007 ... I added custom enterprise fields ... Timesheet and Timesheet Lines approval statuses - microsoft.public ...Timesheet on Published DB, but not in Reporting DB - microsoft ... Timesheet and Timesheet Lines approval statuses - microsoft.public ... In ... If Timesheets are used, do ... Reporting DB out of Synch with Publish DB - microsoft.public ...Timesheet on Published DB, but not in Reporting DB - microsoft ... Learner: Reporting DB updates can fail from time to time. Things can get out of sync when you cancel ... EPM 2003 Timesheet data in not available in EPM 2007.. - microsoft ...Timesheet on Published DB, but not in Reporting DB - microsoft ... EPM 2003 Timesheet data in not available in EPM 2007.. - microsoft ... After migration i am not able to ... If Timesheets are used, do they have to be approved before task ...Timesheet on Published DB, but not in Reporting DB - microsoft ..... in 'My Tasks ... If Timesheets are used, do they have to be approved before task ... ... they are ... timesheet database template - microsoft.public.accessTimesheet on Published DB, but not in Reporting DB - microsoft ... timesheet database template - microsoft.public.access Timesheet Custom Fields in Reporting Database MSPS ... Project Server - force publish? - microsoft.public.project.server ...Project Server - force publish? - microsoft.public.project.server ... Timesheet on Published DB, but not in Reporting DB - microsoft ... Project Fails in the "Reporting ... Enterprise Custom Fields stored in Database? - microsoft.public ...Timesheet on Published DB, but not in Reporting DB - microsoft ... Enterprise Custom Fields stored in Database? - microsoft.public ... Timesheet Custom Fields in Reporting ... Project Fails in the "Reporting(Project Publish) Step ...Project Server - force publish? - microsoft.public.project.server ... Timesheet on Published DB, but not in Reporting DB - microsoft ... Project Fails in the "Reporting ... Timesheet on Published DB, but not in Reporting DB - microsoft ...Any ideas about cause and how to fix? For a given user & period, I can see the timesheet on Published DB, but not on Reporting DB. So far, see th... Timesheet on Published DB, but not in Reporting DB ProjectAny ideas about cause and how to fix For a given user & period, I can see the timesheet on Published DB, but not on Reporting DB. So far, see this with o Timesheet data confliction between Published DB and Reporting DBHi ALL, We have a setup of PS 2007 SP2 Dec09 CU applied. One of our resource facing issue that she has submitted the timesheet for week'13 from pedriod ... Data in the project server published DB and Reporting DB are not ...Hi All, I am working with project server 2007 with SP2 and SQL server 2008 with SP1 The issue is that when a resource submits his timesheet the status ... Custom Fields and the Reporting Database - Microsoft Corporation ...The Reporting database (RDB) in Microsoft Project ... Server data easier than querying the Published database. ... data at the time of submission is not changed. Timesheet ... 7/20/2012 2:28:11 PM
|
|
|
|
|
|
|
|
|