My Tasks Page is Blank - However, Tasks are Assigned?

  • Follow


Note:  We are using Project Server Professional (with PWA) 2007 SP1

We have a user that can log in to Project Web Access (PWA) and see the
"My Tasks" link, but when they click on the link, it takes them to a
blank "My Tasks" page.  However, from the Project Server Professional
view, they do have tasks assigned, and tasks have been published.  The
user was able to see and update tasks prior to this happening.

The user believes the action they did that led to this, was they
received an error message when they clicked the "My Tasks" link (the
error message usually being associated with a "stuck" task).  They
clicked on the message to "close all workspaces", and ever since then,
the "My Tasks" page is blank.

We have a script to run for "stuck tasks", and there are no tasks
showing up as stuck for this user.  All projects have also been
confirmed to be checked in.

Any suggestions as to how to bring their "My Tasks" page back?

Thanks

Steve
0
Reply SteveP 1/26/2010 6:32:45 PM

Can you verify whether the user is the assignment owner of the assignments 
he/she has in the project schedule?

Jonathan

"SteveP" <spatton@insightbb.com> wrote in message 
news:4374082f-bc3b-48d2-9e17-bf6584077557@q4g2000yqm.googlegroups.com...
> Note:  We are using Project Server Professional (with PWA) 2007 SP1
>
> We have a user that can log in to Project Web Access (PWA) and see the
> "My Tasks" link, but when they click on the link, it takes them to a
> blank "My Tasks" page.  However, from the Project Server Professional
> view, they do have tasks assigned, and tasks have been published.  The
> user was able to see and update tasks prior to this happening.
>
> The user believes the action they did that led to this, was they
> received an error message when they clicked the "My Tasks" link (the
> error message usually being associated with a "stuck" task).  They
> clicked on the message to "close all workspaces", and ever since then,
> the "My Tasks" page is blank.
>
> We have a script to run for "stuck tasks", and there are no tasks
> showing up as stuck for this user.  All projects have also been
> confirmed to be checked in.
>
> Any suggestions as to how to bring their "My Tasks" page back?
>
> Thanks
>
> Steve 

0
Reply Jonathan 1/27/2010 7:05:36 PM


Also, you may want to have the user try clearing the internet cache.  

"Jonathan Sofer [MVP]" wrote:

> Can you verify whether the user is the assignment owner of the assignments 
> he/she has in the project schedule?
> 
> Jonathan
> 
> "SteveP" <spatton@insightbb.com> wrote in message 
> news:4374082f-bc3b-48d2-9e17-bf6584077557@q4g2000yqm.googlegroups.com...
> > Note:  We are using Project Server Professional (with PWA) 2007 SP1
> >
> > We have a user that can log in to Project Web Access (PWA) and see the
> > "My Tasks" link, but when they click on the link, it takes them to a
> > blank "My Tasks" page.  However, from the Project Server Professional
> > view, they do have tasks assigned, and tasks have been published.  The
> > user was able to see and update tasks prior to this happening.
> >
> > The user believes the action they did that led to this, was they
> > received an error message when they clicked the "My Tasks" link (the
> > error message usually being associated with a "stuck" task).  They
> > clicked on the message to "close all workspaces", and ever since then,
> > the "My Tasks" page is blank.
> >
> > We have a script to run for "stuck tasks", and there are no tasks
> > showing up as stuck for this user.  All projects have also been
> > confirmed to be checked in.
> >
> > Any suggestions as to how to bring their "My Tasks" page back?
> >
> > Thanks
> >
> > Steve 
> 
0
Reply Utf 1/28/2010 6:05:02 PM

2 Replies
938 Views