MSP Summary task
Why summart task is showing fraction, even though calender and
duration are set correct?this has occured after i have rescheduled the
entire project, i have inserted some new task % complete 0%
|
|
0
|
|
|
|
Reply
|
AR
|
4/20/2010 10:08:24 AM |
|
Hi,
What is "correct"? Go to Tools, Options, View, and set the upmost date
format from the lookup list (the one with time of day). That will show you
that the finish hour of the summary task is not the same as the start hour
of the summary task. There probably is a mismatch between teh definition of
"hours per day" in teh Calendar options with the working time in the Project
Calendar.
Hope this helps,
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
"AR S S Iyer" <ars.satheesh@gmail.com> wrote in message
news:53861898-7309-4306-9d9d-0c285b0db2cc@a27g2000prj.googlegroups.com...
> Why summart task is showing fraction, even though calender and
> duration are set correct?this has occured after i have rescheduled the
> entire project, i have inserted some new task % complete 0%
|
|
0
|
|
|
|
Reply
|
Jan
|
4/20/2010 11:43:13 AM
|
|
|
1 Replies
363 Views
(page loaded in 0.034 seconds)
Similiar Articles: Concatenate Tasks With Summary Tasks in Reports - microsoft.public ...I think I have found in other posts but I want to ask directly just in case someone else has other info... Can MSP concatenate each task in a report with its summary ... Show summary task headings on reports - microsoft.public.project ...for each group of tasks I need to display summary task headings on my do to list ... Have you check out the visual reports in MSP 2007? If you have access to MSP ... MSP 2007 - How to add custom fields to visual reports - microsoft ...I've created a very simple test MSP file. It has 4 sub-tasks and 2 summary tasks. I've added resources and duration. I've also inserted the Text1 fi... Cashflow Summary Task - microsoft.public.projectConcatenate Tasks With Summary Tasks in Reports - microsoft.public ... MSP 2007 - How to add custom ... ... Cashflow Summary Task - microsoft.public.project MSP 2007 ... What does Microsoft Project Levels 1, 2, 3, 4, schedules mean ...I'm a MSP new user and I want a detailed explanation to the following ... So, the summary tasks with outline level value 1 or 2 should mostly be features of the ... Resource Usage Work Rollup - microsoft.public.projectWhen the macro completed, I noticed about half the resources contained 0 hours in the summary work but contains work on their assigned tasks. MSP identified some ... how to display work by resource for a summary task - microsoft ...I am trying to show the minimum slack value for a summary task on my project. ... Resource Usage Work Rollup - microsoft.public.project I am using MSP 2007 and Calculation ... What table contains the data displayed in 'My Tasks' view ...... able to get work submitted as a summary with following statement (Published DB!!!): SELECT dbo.MSP_RESOURCES.RES_NAME, dbo.MSP_PROJECTS.PROJ_NAME, Selected_ASSN.TASK ... Project 2007 - Problem with Multiple Tasks, Resources and ...The attached project (http://www.demandmanagement.com/project/summary_problem.mpp), a ... You should know that MSP is based on the Critical Path Method, which means ... How do I eliminate multiple task status reports in Outlook ...Concatenate Tasks With Summary Tasks in Reports - microsoft.public ... MSP 2007 - How to add custom fields to visual reports - microsoft ... Concatenate Tasks With Summary ... Msp Summary Task - Free PPT downloadsATC Project Work Plans. MSP Controls Schedule – HP-PPM gathers Actuals – provides all MSP... Summary Task Owners - added in the Project Participant tab or through ... Business Rules, MSP Import and Export - IBM - United StatesRecurring tasks. When a recurring task is created in Microsoft Project, a summary task is created with a number of occurrences nested beneath it. How to Use Microsoft Project (MSP)select msp_tasks.task_start_var, msp_tasks.task_is_summary, msp_tasks.task_outline_level, msp_tasks.task_start_date, msp_tasks.task_finish_date, msp_tasks.task_name, msp ... How do I add summary task as a selectable field for custom reports ...You can find the GUID for summary task as TaskParentUID for each task in MSP_EpmTask_UserView. You link them similar to following: SELECT SummaryTask ... Roll up a Gantt bar to its summary task bar - Project - Office.comOn the summary task bar, rolled-up tasks are represented by bars and milestone (milestone: A reference point marking a major event in a project and used to monitor the ... 7/18/2012 5:58:30 PM
|
|
|
|
|
|
|
|
|