MSP Summary task

  • Follow


Why summart task is showing fraction, even though calender and
duration are set correct?this has occured after i have rescheduled the
entire project, i have inserted some new task % complete 0%
0
Reply AR 4/20/2010 10:08:24 AM

Hi,

What is "correct"? Go to Tools, Options, View, and set the upmost date 
format from the lookup list (the one with time of day). That will show you 
that the finish hour of the summary task is not the same as the start hour 
of the summary task. There probably is a mismatch between teh definition of 
"hours per day" in teh Calendar options with the working time in the Project 
Calendar.

Hope this helps,
-- 
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
"AR S S Iyer" <ars.satheesh@gmail.com> wrote in message 
news:53861898-7309-4306-9d9d-0c285b0db2cc@a27g2000prj.googlegroups.com...
> Why summart task is showing fraction, even though calender and
> duration are set correct?this has occured after i have rescheduled the
> entire project, i have inserted some new task % complete 0% 


0
Reply Jan 4/20/2010 11:43:13 AM


1 Replies
363 Views

(page loaded in 0.034 seconds)