|
|
How to clear Remaining work for Inactive Resources in Project 2003
Hello,
We are using Project Server 2003. Is there any easier way to clear Remaining
work for Inactive Resources other than going to each project and zeroing the
remaing work...may be from backend or pds calls?
Please suggest.
Regards,
Kishore Dodda
|
|
0
|
|
|
|
Reply
|
Utf
|
6/3/2010 1:43:27 AM |
|
Hi,
No. You might be able to do something with PDS but that would take longer
than doing it manually and PDS doesn't work for Project Server 2007 onwards
so waste of time. I would email all project managers and tell them to zero
out remaining work for these resources. They are also the ones who will need
to re-allocate the work to someone else.
--
Rod Gill
Microsoft MVP for Project - http://www.project-systems.co.nz
Author of the only book on Project VBA, see: http://www.projectvbabook.com
"Kishore Dodda" <KishoreDodda@discussions.microsoft.com> wrote in message
news:8B6399D2-73DE-43DB-A4F0-AC1C60A0C47E@microsoft.com...
> Hello,
> We are using Project Server 2003. Is there any easier way to clear
> Remaining
> work for Inactive Resources other than going to each project and zeroing
> the
> remaing work...may be from backend or pds calls?
>
> Please suggest.
>
> Regards,
> Kishore Dodda
>
> __________ Information from ESET Smart Security, version of virus
> signature database 5167 (20100602) __________
>
> The message was checked by ESET Smart Security.
>
> http://www.eset.com
>
>
>
__________ Information from ESET Smart Security, version of virus signature database 5167 (20100602) __________
The message was checked by ESET Smart Security.
http://www.eset.com
|
|
0
|
|
|
|
Reply
|
Rod
|
6/3/2010 3:40:49 AM
|
|
|
1 Replies
753 Views
(page loaded in 0.084 seconds)
Similiar Articles: How to clear Remaining work for Inactive Resources in Project 2003 ...Hello, We are using Project Server 2003. Is there any easier way to clear Remaining work for Inactive Resources other than going to each project an... microsoft.public.project.serverHow to clear Remaining work for Inactive Resources in Project 2003 Utf 1 505 Hello, We are using Project Server 2003. Is there any easier way to clear Remaining work for ... Resources other than cost - microsoft.public.projectHow to clear Remaining work for Inactive Resources in Project 2003 ... Resources other than cost - microsoft.public.project Project Most Valuable Professional +32 495 300 ... How to allocate percentages of resources to projects? - microsoft ...How to clear Remaining work for Inactive Resources in Project 2003 ... They are also the ones who will need to re-allocate the work to someone else. ... public.project ... Actual work not showing in Resource Assignments or OLAP ...How to clear Remaining work for Inactive Resources ... still showing up in Project Pro ... Resource Usage view set up to record actual work ... Prject 2003 Updating Resource ... Report All Resources with Availability/Capacity for each gantt ...... will find all required information as resource, project, availabilty, capacity, work, .... ... could be used in a custom report to ... clear Remaining work for Inactive Resources ... Disabling or Removing tasks from PWA (PS 2003) - microsoft.public ...I have zeroed all the remaining work and changed the project status to "proposed" and then republished, however the tasks still ... tasks from PWA (PS 2003) Project Hi, In ... Replace the Resource - microsoft.public.project... the task, set the remaining work for the resource to ... in the Task Information, Resources dialog box. However, you can still ... the cost rate table of resource in project ... Resource Assignments View Filtered on Booked Type Field ...... the tasks from this project no longer appear in the resources My Tasks view but they do still ... then remove the remaining work for ... MS Project 2003 and Project Server 2003 My Resources Unsubmitted Timesheets not working (MSPS 2007 ...Timesheet Remaining Hours ? - microsoft.public.project ... of all resource under a ..... to ... Inactive Resources in Project ... am working in Project 2003 Resource ... How to clear Remaining work for Inactive Resources in Project 2003 ...Hello, We are using Project Server 2003. Is there any easier way to clear Remaining work for Inactive Resources other than going to each project an... How to clear Remaining work for Inactive Resources in Project 2003 ...Hello, We are using Project Server 2003. Is there any easier way to clear Remaining work for Inactive Resources other than going to each project and zeroi Issues that are fixed in Project 2003 by Project 2003 Service Pack 2... actual work. If you clear ... The remaining work time is not updated in Project Professional 2003 ... an inactive resource active in Project Professional 2003 Distribute project work evenly (level resource assignments ...Distribute project work evenly (level resource assignments) ... automatic leveling, clear the Clear ... by creating splits in the remaining work on tasks or resource ... microsoft.public.project.server | Microsoft NewsgroupsHow to clear Remaining work for Inactive Resources in Project 2003 Utf 1 505 Hello, We are using Project Server 2003. Is there any easier way to clear Remaining work for ... 7/21/2012 2:40:00 AM
|
|
|
|
|
|
|
|
|