Enterprise global - Calendars - Tools Options Schedule

  • Follow


Hi,
We work with Project Server 2007. As an administrator, I opened the 
Enterprise Calendars from PWA to modify the Standard calendar and make the 
settings available for all the connected users.
I also opened Enterprise Global from PWA and changed settings in Calendar 
and Schedule tabs, and saved Enterprise Global to server.
When a user connects to the server with Project Professional 2007, the 
standard calendar is the same than the one in the server (expected behaviour) 
but the settings in Tools Options Schedule and Calendar tabs are not the same 
(unexpected behaviour). 
This cause a problem because the settings (task types and so forth) are not 
enforced for all users, and informations coming from "Change working time" 
and Calendar tab (tools option) are not consistent.
Do you know how to manage this ?
Thanks.
Stan


0
Reply Utf 5/21/2010 6:43:01 AM

Hi Stan,

your observation is correct. Settings in Option/Schedule and /Calendar from 
Enterprise Global are not applied to clients, since these are local setting.

To match those, I have used several technical solutions so far (and I am 
looking forward to read any better suggestions):
- put an project_open macro in Enterprise Global to change these settings.
- roll out an registry file with the most important settings
- write a VBScript to set values

Each of these has advantages and disadvantages. So my favorite one is to 
make it a training issue and let people see, what happens if the modify any 
of these settings. The last exercise is to configure according to project 
server.

Regards
Barbara

"Stan" <Stan@discussions.microsoft.com> schrieb im Newsbeitrag 
news:B0D74A32-8388-4C2A-9BCD-EBB2E00ADA73@microsoft.com...
> Hi,
> We work with Project Server 2007. As an administrator, I opened the
> Enterprise Calendars from PWA to modify the Standard calendar and make the
> settings available for all the connected users.
> I also opened Enterprise Global from PWA and changed settings in Calendar
> and Schedule tabs, and saved Enterprise Global to server.
> When a user connects to the server with Project Professional 2007, the
> standard calendar is the same than the one in the server (expected 
> behaviour)
> but the settings in Tools Options Schedule and Calendar tabs are not the 
> same
> (unexpected behaviour).
> This cause a problem because the settings (task types and so forth) are 
> not
> enforced for all users, and informations coming from "Change working time"
> and Calendar tab (tools option) are not consistent.
> Do you know how to manage this ?
> Thanks.
> Stan
>
> 

0
Reply Barbara 5/21/2010 10:07:09 AM


Stan --

As Barbara already noted in her excellent answer to your question, you 
cannot specify Options settings for each user by setting them in the Options 
dialog in the Enterprise Global file.  Your assumption was one that new 
Project Server administrators usually make, and as you know now, the 
assumption is incorrect.  A better way to think of the Enterprise Global is 
your organization's "library" of custom enterprise Views, Tables, Filters, 
Groups, Reports, etc.  To resolve your Options settings issue, Barbara has 
offered you several automated ways to address it.  Personally, I prefer that 
a company address this in a training session so that PMs can specify their 
own Options settings, can know why they are choosing these settings, and 
know how those settings affect their environment.  Of course, this training 
should be part of a larger training program to help the organization's PMs 
become proficient in creating and managing projects effectively in Project 
Server.  Hope this helps.

-- 
Dale A. Howard [MVP]
VP of Educational Services
msProjectExperts
http://www.msprojectexperts.com
http://www.projectserverexperts.com
"We write the books on Project Server"


"Stan" <Stan@discussions.microsoft.com> wrote in message 
news:B0D74A32-8388-4C2A-9BCD-EBB2E00ADA73@microsoft.com...
> Hi,
> We work with Project Server 2007. As an administrator, I opened the
> Enterprise Calendars from PWA to modify the Standard calendar and make the
> settings available for all the connected users.
> I also opened Enterprise Global from PWA and changed settings in Calendar
> and Schedule tabs, and saved Enterprise Global to server.
> When a user connects to the server with Project Professional 2007, the
> standard calendar is the same than the one in the server (expected 
> behaviour)
> but the settings in Tools Options Schedule and Calendar tabs are not the 
> same
> (unexpected behaviour).
> This cause a problem because the settings (task types and so forth) are 
> not
> enforced for all users, and informations coming from "Change working time"
> and Calendar tab (tools option) are not consistent.
> Do you know how to manage this ?
> Thanks.
> Stan
>
> 
0
Reply Dale 5/21/2010 12:50:40 PM

Hi Dale,

I completely agree with your preference! As I wrote, my most favorite 
solution is to make it a training issue. The knowledge of the impact of 
options is essential for PMs from my point of view.
However,  I have had one implementation so far, where customer insisted on a 
technical solution. I have tested the listed ones, all of them have some 
advantages but also a few risks.

Regards
Barbara

"Dale Howard [MVP]" <dale[dot]howard[at]msprojectexperts[dot]com> schrieb im 
Newsbeitrag news:D982ABFE-510B-45F7-B3E2-A099118A4703@microsoft.com...
> Stan --
>
> As Barbara already noted in her excellent answer to your question, you 
> cannot specify Options settings for each user by setting them in the 
> Options dialog in the Enterprise Global file.  Your assumption was one 
> that new Project Server administrators usually make, and as you know now, 
> the assumption is incorrect.  A better way to think of the Enterprise 
> Global is your organization's "library" of custom enterprise Views, 
> Tables, Filters, Groups, Reports, etc.  To resolve your Options settings 
> issue, Barbara has offered you several automated ways to address it. 
> Personally, I prefer that a company address this in a training session so 
> that PMs can specify their own Options settings, can know why they are 
> choosing these settings, and know how those settings affect their 
> environment.  Of course, this training should be part of a larger training 
> program to help the organization's PMs become proficient in creating and 
> managing projects effectively in Project Server.  Hope this helps.
>
> -- 
> Dale A. Howard [MVP]
> VP of Educational Services
> msProjectExperts
> http://www.msprojectexperts.com
> http://www.projectserverexperts.com
> "We write the books on Project Server"
>
>
> "Stan" <Stan@discussions.microsoft.com> wrote in message 
> news:B0D74A32-8388-4C2A-9BCD-EBB2E00ADA73@microsoft.com...
>> Hi,
>> We work with Project Server 2007. As an administrator, I opened the
>> Enterprise Calendars from PWA to modify the Standard calendar and make 
>> the
>> settings available for all the connected users.
>> I also opened Enterprise Global from PWA and changed settings in Calendar
>> and Schedule tabs, and saved Enterprise Global to server.
>> When a user connects to the server with Project Professional 2007, the
>> standard calendar is the same than the one in the server (expected 
>> behaviour)
>> but the settings in Tools Options Schedule and Calendar tabs are not the 
>> same
>> (unexpected behaviour).
>> This cause a problem because the settings (task types and so forth) are 
>> not
>> enforced for all users, and informations coming from "Change working 
>> time"
>> and Calendar tab (tools option) are not consistent.
>> Do you know how to manage this ?
>> Thanks.
>> Stan
>>
>> 