Actual work not showing in Resource Assignments or OLAP1554 (12/3/2009 6:36:01 PM) After actuals were entered through My Tasks in PWA, approved and published
they were still not visible through the resource assignment view or the OLAP
reports. The information was available and correct whe... Utf
2 validate Levels in EPM 20072193 (12/3/2009 9:18:51 AM) Hi all,
I'm using the Microsoft Project Server 2007 Service Pack 3, and in the
installing process, the client ask me a good question, could we set 2
levels of validation the my tasks?
I know that we could... Helder
End date differs among project views1151 (12/3/2009 1:32:01 PM) We utilize project and Project Server 2007.
Using the Gantt Chart view, the finish date for Task A (duration based) is
1/10/10. If I double click on the task in either the Task Usage or Resource
Usage vi... Utf
Potential Bug in Surrogate Timesheet Creation??2479 (11/27/2009 4:49:16 PM) Hi All,
(Project Server Sp2/Aug CU)
I came across a potential bug in Project Server 2007.
Here is the scenario...
1. Create an enterprise lookup table and call it Application Name. Populate
this w... Shane
Keep EPM 2007 Updated4251 (11/23/2009 2:27:33 PM) It's quite difficult to follow all EPM updates : Cumulative Update,
HotFix, for ProjectServer, Office Project, Windows SharePoint and so
on...
To get a clear view and save time in update process we've publis... Xavier
Tasks Do Not Show up in My Tasks4587 (12/2/2009 1:26:01 AM) I created a project and assigned a resource to each task. I published the
project and the resource received an email notifying him that he was assigned
new tasks. When he goes to My Tasks the new tasks ar... Utf
Migration to Project Server 2007 from Artemis1424 (12/2/2009 3:47:01 PM) I'm helping a customer migrate from Artemis to PS 2007. Does anyone have any
experience that they would like to share? Things to watch for? Lessons
learned?
... Utf
My Task progress reporting is inconsistent2135 (12/1/2009 8:33:02 PM) In "My Tasks" (PWA 2007) we are not using timephased, instead we enter
%complete under the 'Progress' column against the assigned task. However, on
some tasks for the very same project, we are restricted t... Utf
Moving from WSS to MOSS 20070201 (12/2/2009 3:58:01 PM) Good morning.
I am looking for the proper steps to move an EPM Project Server 2007 from a
WSS farm to a MOSS 2007 farm.
Thank you in advance,
Luis
... Utf
Help with RBS configure2259 (12/2/2009 9:46:01 AM) I don't know how to configure the following RBS:
Management -> Department 1 -> Department 1.1
-> Department 1.2
-> Department 2 -> Department... Utf