Date calculation question

I have a submission date (reg date field) & an expected due date (using 
Workday to calculate 3 workdays from submission date, minus holidays). I 
would like to change the due date so if the document is submitted after 
3:00pm, an extra day is added. 

How would I do this?

Thanks,  
JoAnn
0
JoAnn (49)
2/27/2008 1:49:09 PM
excel.newusers 15348 articles. 2 followers. Follow

3 Replies
623 Views

Similar Articles

[PageSpeed] 25

If you include the time in the submission date, one way:

A1:      27 February 2008 3:30 pm
B1:     =WORKDAY(A1,3+(MOD(A1,1)>15/24), holidays)

assuming no holidays, this will return 4 March 2008


another, simpler, way:

B1:      =WORKDAY(A1+8.99999/24,3)



In article <C26E5809-869A-4732-A977-CDC0C7BACB44@microsoft.com>,
 JoAnn <JoAnn@discussions.microsoft.com> wrote:

> I have a submission date (reg date field) & an expected due date (using 
> Workday to calculate 3 workdays from submission date, minus holidays). I 
> would like to change the due date so if the document is submitted after 
> 3:00pm, an extra day is added. 
> 
> How would I do this?
> 
> Thanks,  
> JoAnn
0
jemcgimpsey (6723)
2/27/2008 2:01:08 PM
Thanks! I'll try that.
-- 
JoAnn


"JE McGimpsey" wrote:

> If you include the time in the submission date, one way:
> 
> A1:      27 February 2008 3:30 pm
> B1:     =WORKDAY(A1,3+(MOD(A1,1)>15/24), holidays)
> 
> assuming no holidays, this will return 4 March 2008
> 
> 
> another, simpler, way:
> 
> B1:      =WORKDAY(A1+8.99999/24,3)
> 
> 
> 
> In article <C26E5809-869A-4732-A977-CDC0C7BACB44@microsoft.com>,
>  JoAnn <JoAnn@discussions.microsoft.com> wrote:
> 
> > I have a submission date (reg date field) & an expected due date (using 
> > Workday to calculate 3 workdays from submission date, minus holidays). I 
> > would like to change the due date so if the document is submitted after 
> > 3:00pm, an extra day is added. 
> > 
> > How would I do this?
> > 
> > Thanks,  
> > JoAnn
> 
0
JoAnn (49)
2/27/2008 2:59:01 PM
Your solution works great!  But the change impacts other parts of my 
spreadsheet.

My Expected Due Date field is actually 2 fields. I have the Workday field 
column hidden (because I can't conditionally format it) and I display its 
result in another regular date field so I can conditionally format it to 
appear in red font if the submitter manually changes the Expected Due Date to 
one that is earlier than the automatically generated 3-day date.  

Although I'm sure there is probably a better way to do this ... for the 
conditional formatting, I have the # of days calculated/displayed in another 
hidden field (# Days).  So  if the value of the # days field is < 3, I apply 
red font to the manually changed Expected Due Date. Since the change, the 
Expected Due Date field is turning red when it shouldn't.

How can I fix this?  I thought I could just do what I did before & create a 
hidden Submission Date CALC field = the value of the Submission date field  
(with a different date format) & then do the #days from that. Unfortunately, 
when I do that, the time still carries over with it. Changing the date format 
 to m/dd/yy doesn't seem to strip the time from it.

Is there any way to perform calculations on dates that have 2 different 
formats? I only need to have the time entered/displayed in the Submission 
field. The expected due date & completion fields need just the date. 

I will also need to determine the turnaround time (completed date - 
submission date), which I am currently using NETWORKDAYS for. 



-- 
JoAnn


"JE McGimpsey" wrote:

> If you include the time in the submission date, one way:
> 
> A1:      27 February 2008 3:30 pm
> B1:     =WORKDAY(A1,3+(MOD(A1,1)>15/24), holidays)
> 
> assuming no holidays, this will return 4 March 2008
> 
> 
> another, simpler, way:
> 
> B1:      =WORKDAY(A1+8.99999/24,3)
> 
> 
> 
> In article <C26E5809-869A-4732-A977-CDC0C7BACB44@microsoft.com>,
>  JoAnn <JoAnn@discussions.microsoft.com> wrote:
> 
> > I have a submission date (reg date field) & an expected due date (using 
> > Workday to calculate 3 workdays from submission date, minus holidays). I 
> > would like to change the due date so if the document is submitted after 
> > 3:00pm, an extra day is added. 
> > 
> > How would I do this?
> > 
> > Thanks,  
> > JoAnn
> 
0
JoAnn (49)
2/27/2008 5:52:00 PM
Reply:

Similar Artilces:

filter by date and action
I have a table with three columns: Name Date Action Fred Today this Fred Today this Fred Today that Wilma Today this I want to sort by name and by date, but only if 'this' was done more than once on the same day, and not if 'that' was done on the same day,They have to perform this more than once, and they cannot have performed that on the same day. If not in excel, mssql maybe? Thanks, Harry On Aug 18, 1:53=A0pm, Harry <hamac...@gmail.com> wrote: > I have a table with three co...

Calculate Years/Months Between Dates and then Average
We are using the formula =DATEDIF(A1,NOW(),"y") & "." & DATEDIF(A1,NOW(),"ym") to calculate the years and months from an employee hire date. Is there an easy way to average the years and months for a group of employees with the results of that formula? You could use: =AVERAGE(A1:A10*1) Array-entered, meaning press ctrl-shift-enter. But you could also just change your current formula to: =1*(DATEDIF(A1,NOW(),"y") & "." & DATEDIF(A1,NOW(),"ym")) Then just use: =AVERAGE(A1:A10) which is *not* array-entered. ...

Exchange 2003 Licensing question
We are a small company of only about 35 employees. We currently have Exch 5.5 and will be upgrading to Exch 2003. Unfortunately due to our large email store we will be force to get the Enterprise edition because we are just over the standard edition's 15 gb message store limit. I was under the impression that an Office 2003 Pro license includes a CAL for accessing Exchange 2003. What I am being told by a sales rep is that Office Pro does not include a CAL to access Exch 2003 therefore I have to buy a CAL for each user. Is this correct? The ironic thing is this. If I buy a CAL ...

Transaction Date VS Business Date
Our accounting department needs/wants to have all RMS SO reporting by business date opposed to transaction date. Usually these are the same unless you have sales and batches that close after midnight. For our store I would like to set 3 a.m. as the business day closing time. So when I run any type of reports I would like to get the information for a business date (range) starting at 3 a.m. till 3 a.m. the next day. I guess I could accomplish this by subtracting 3 hours from all the transaction (date and) times but I would have to do this for every single report which would be a lot of ...

Formula displays does not calculate
Hello: I just typed a formula in a cell and it displays =A4+J13 (the same formula calculates fine in a different cell), instead of claculating the value. Both A4 and J13 contain numeric data. I try Ctrl+~ to toggle and chk if full formula mode was ON? but that did not help either. I also tried looking for feedback through the formula evaluation utility in Excel, no help there either, it says cell being evaluated contains a constant? Your help is appreciated Hi Neil, Perhaps the cell is formatted as text? --- Regards, Norman "Neil Bhandar" <Neil Bhandar@discussions.mic...

Post Dated Checks
I had to prepare some post dated checks and we did not have fiscal periods set up yet to match the dates of the checks. Currently the check batches are waiting to be posted. What is the best way to handle post dated checks? If I create new fiscal years to match these dates, I will end up having 4 Open years. Is this the only way to do it? You can manage post dated checks in Microsoft Dynamics GP with the Payment Document Management module available on the Feature Pack 1 DVD image. For more info, take a look at MVP Mohammad Daoud's post on the subject at: https://communit...

Calculate Column
Word 2007 I have a very simple chart in Word and I would like to make the last cell calculate the total of the above cells, as you can in Excel. To make the calculation Just insert the sum formula in the last cell of your chart. You should be able to access the "sum" button on the toolbar if you are working in charts. If it is a table that you're working with just click on the last cell, select "Table" and then select "formula." "Canon" wrote: > Word 2007 > I have a very simple chart in Word and I would like to make the last c...

Remove "Date: Yesterday" or "Date: Monday" from Outlook Inbox?
Outlook mail inbox now has headers that tell you what day the the email was sent. I find this visually annoying. Each emailalready has the time and day it was sent. I don't need the daily titles in the midst of the list of emails. How do I make them go away? I think you are talking about OL 2003 & the Arrange in Groups setting. Change it in View, Arrange by, uncheck Show in Groups. "silky" wrote: > Outlook mail inbox now has headers that tell you what day the the email was > sent. I find this visually annoying. Each emailalready has the time and day >...

Calculated Fields 04-18-07
We're helping someone with a relatively basic requirement for CRM, but they've thrown two awkward ones into the mix. The first of which is a desire to use some custom fields on an entity which are then automatically totalled. e.g. when they do a quote each item on the quote (free entry) has a custom field for the cost to the organisation of providing the service. On the main quote screen/report they need these to be totalled, in the same way that the built-in sell-price fields are. Is this possible without reaching for Visual Studio? I've had a look through a pile of...

Define an array based on calculations
Hi, well, I just miserably failed in posting my first thread. Hope I will be luckier this time. I have a couple of matrices (170) in one excel sheet and would like to calculate the correlation coefficient of all pair combinations. That will give me about 14000 correlation calculations. I already specified the pair combinations, where each matrix got the label 1, 2, 3... 170 and arranged in two different columns (AB, AC) like this: 1 2 1 3 .. 65 102 .. 169 170 All matrices are in the area of A1 to T4076, where each matrix has 20x20 cells with 4 empty rows between eachother. Basically, I ne...

strange date format problem
Hi, I downloaded some data on excel using Bloomberg. One column has dates and the other has numbers. Dates appear as 01/01/1980 format which I want in Jan-80 format. I have changed the format cell properties but it still appears as 01/01/1980. I have to goto individual cell and press F2 <enter> so see the effect. Dont know why? I cant even copy paste format after that .... TIA/amag I am not sure, but is your workbook set to Auto-Recalculate? Try pushing <F9> to do a manual re-calculation, see if that changes the formats. If it does, go to Tools (on the menu bar), Options, Ca...

hello everyone.im new here and have a question.
i was having Seagate 160 gb hardisk and recently i got a new 320gb seagate hdd and put it as secondary disk. nw i have 4 drives i.r (C:,D:,F:,G:)..'C & D belongs to previous hardisk'.. 2 days back .i was on facebook and someone sent me a message.(link) and when i clicked it a file is downloaded automatically and from that time drives f: and g: are not opening correctly.maybe its due to some virus and ther's no use of scanning for viruses.i tried "norton, eset nod32, mc afee, avast ,avg.".but didnt work..................... if you try to open them directly...

Public Folder Question #3
I recently took over a new mixed-mode Exchange Org and am trying to clean up their Public Folder tree. There is one folder called IPM_SUBTREE that I am not familiar with. Can this be removed or is it some kind of system folder that needs to remain in place? It has several subfolders that were probably moved there by accident and need to be removed, but what about the IPM_SUBTREE? It doesn't have any items in it... DON"T REMOVE IT!!!!! This is the basic tree where your mail enabled public folders live. It is also bound to your public folder store. There are two parts to the ...

How to sort by name then date?
I would like to look through all the emails to a particular person. If I click on the "To" column I can see all the emails to a particular person (actually there is a problem with that which I will mention next) but they seem to be in random order. Is there a way to have them sorted by date? (i.e. by name first, then by date). Actually, sorting on the "To" column does not get all the emails sent to a given email address. Because Outlook uses the "display as" field. It will often give different "display as" names to the same email address. C...

Concatenate including a date so that the date appears as a date
When I try to join the contents of several cells, one of which is a date and time obtained from =now(), the date and time part appears as a number. How can I make it appear as a date and time? I have tried changing the cell formats - probably there is a combination that works but I haven't found it. I also tried copying the original date cell to another cell and changing the latter cell's format and concatenating using that latter cell, but still no success. Use the TEXT function. For example, =TEXT(NOW(),"mmmm d, yyyy") would give January 6, 2010 "dd...

Query Question
Please see the sql code below. What I am after is Sum of [RiskCount]. But due to the join, I get double counting and consequently wrong SUM. Is this an inherent limitaion of Sql? Can be it solved without breaking up the sql into two parts? Thanks for reading this post. CREATE TABLE #Location ( LocationID INT, RiskCount INT) CREATE TABLE #Coverage ( LocationID INT, Peril VARCHAR(10), Coverage VARCHAR(10), TSI Numeric(25,6)) INSERT INTO #Location VALUES (1,1) INSERT INTO #Location VALUES (2,1) INSERT INTO #Location VALUES (3,1) INSERT...

if statement with dates #2
I would like to have a statement like: IF(a1>0,1/1/2004) with 1/1/2004 beint a date. EXCEL is interpreting 1/1/2004 as an arithmetic statement and giving me the result of the arithemtic. I could put in the numeric offste for the date and write IF(a1>0,37987), formatting the cell as a date, but this seems awkward. What else can I do? TIA, Sanford ...

selectNodes question
Hi, I am trying to get nodes (in a VC++ application) using the method IXMLDOMElementPtr::selectNodes. This is part of my XML file: <None-Books> <Summary Books="34" TopContainer="13" Client="27"/> <AAA-1 Type="0" DockingCX="200" DockingCY="120" Title="a"/> <AAA-ar Type="0" DockingCX="138" DockingCY="154" Title="b"/> <Book-3 Type="0" DockingCX="365" DockingCY="120" Title="c"/> <AAA-4 Type="0"...

Counting Dates?
=COUNTIF(A1:A100,"<" & NOW()) This works good for specific cells. I have a similar question. How would I do the same thing given that: 1) You only have a starting date 2) Your only wanting to count work days (in this case 4 day/wk) up to NOW() Thank you for all your help. Aviator On Thu, 6 Jan 2005 12:53:03 -0800, "Aviator" <Aviator@discussions.microsoft.com> wrote: >=COUNTIF(A1:A100,"<" & NOW()) > >This works good for specific cells. I have a similar question. > >How would I do the same thing given that: >1) You only ha...

Count Unique Cells, within a date range (dates stored in separate column).
Hello All: I am attempting to create a formula that will count the number of unique cells (alpha-numeric) in an entire column (no set length, so ex: "$B:$B"). This count will be based on a date range (Between 2 dates). The dates are stored in another column (Ex: "$A:$A"). The following is an example of the cells. Dates PO_Num 1/2/2010 A123456 1/3/2010 B453453 2/2/2010 A123456 3/4/2010 C2342F3K 4/3/2010 123456 I would like to know a formula that can count the number of different PO's based on a given date range. Please help me if you...

An expression for dates from and to
I am trying to create an expression to select items from a date field falling from a certain date to a certain date. I am obviously missing something in my expression. The field name is DateComplete. How can I set up this expression to pull date from a certain date to a certain date? -- Ronnie Hi Ronnie, An example of the SQL would be: SELECT * FROM [TABLE NAME] WHERE DateComplete Between #1/1/2006# And #1/1/2007# ; On May 23, 3:52 pm, Ronnie <Ron...@discussions.microsoft.com> wrote: > I am trying to create an expression to select items from a date field falling > from a...

Shared Borders Question....
Can 'Shared Borders' be .asp rather than .htm? There is a particular script I will like to run, but it can not be .htm. Thanks David No. -- Tom [Pepper] Willett Microsoft MVP - FrontPage Since 1997 --------------------------- "116" <116@discussions.microsoft.com> wrote in message news:52CEB706-E273-461F-9DD9-483EBA3C1F57@microsoft.com... : Can 'Shared Borders' be .asp rather than .htm? There is a particular script : I will like to run, but it can not be .htm. : : Thanks : David The shared border files must be .htm - left.htm, righ...

Returning only MAX(date) not all dates
I want to be able to list the most current date an item is checked out. As I was working through the query I used max as an aggregate function but I still can't get the simple result I want. I'd rather list the fields I have chosen and somehow select just the most current checkout date. Any help would be greatly appreciated. Here is my query: SELECT tblTerritory.TerritoryID, [TerritoryName] & " " & [TerritoryDescription] AS Description, tblTerritory.TerritoryTypeID, tblTerritoryType.TerritoryType, Max(tblTerritoryCheckout.DateCheckedOut) AS Checked...

How do you calculate interest expense on bonds?
Using Excel office on XP. Issued $1mill of 11% 20 year bonds, issued 4-1-04 and paying interest on a yearly bases on 3-31. Need to calculate interest expense for fiscal year ended 9-30-04 assuming a premium of $80,000 amoritized on a streight line bases. Hi, Try having a look at the =PRICE function in help. If this isn't exactly what you need then it should point you in the right direction. HTH, David Jessop "Sprout" wrote: > Using Excel office on XP. Issued $1mill of 11% 20 year bonds, issued 4-1-04 > and paying interest on a yearly bases on 3-31. Need to ...

System Date
Can anyone help me on how to force the system date to a member field of "Date" type? I could not find any help on msdn that comes with visual c++. Any hint or help will be appreciated. Thanks, Behrouzk Are you just trying to get the current date. You can use CTime::GetCurrentTime() or COleDateTime::GetCurrentTime() Tom "Behrouzk" <Behrouzk@discussions.microsoft.com> wrote in message news:D8FA4B6B-73CE-4058-B50C-C9BEBAB67E68@microsoft.com... > Can anyone help me on how to force the system date to a member field of > "Date" type? I could not fi...